Complition schedule of additional work.

External drain
sl no Description starting date complition date
1 Excavation 10.12.21 20.01.22
2 PCC 11.12.21 24.01.22
3 RCC 12.12.21 26.01.22
Internal road side drain
sl no Description starting date complition date
1 Excavation 10.12.21 15.01.22
2 PCC 11.12.21 16.01.22
3 RCC 12.12.21 20.01.22
ROAD
1 Box cutting & rolling 15.12.21 18.01.22
2 Brick bat lating 16.12.21 21.01.22
3 GSB Laying 17.12.21 22.01.22
4 PCC 18.12.21 24.01.22
5 RCC 19.12.21 26.01.22
PIPE SLEEPER
1 Excavation 10.12.21 12.01.22
2 PCC Casting 11.12.21 14.01.22
3 Column casting 13.12.21 15.01.22