Professional Documents
Culture Documents
Project Management
Project Management
Project Management
PROJECT MANAGEMENT
Characteristics of Project
Unique purpose
Temporary
Requires resources
Developed using progressive elaboration
Involves uncertainty
Others
A program is a portfolio comprised of multiple projects that are managed and coordinated
as one unit with the objective of achieving (often intangible) outcomes and benefits for
the organization.
Programs can be regarded as subsystems. However, programs are generally defined as
time-phased efforts, whereas systems exist on a continuous basis.
Program is the integrated, time-phased tasks necessary to accomplish a particular
purpose. Projects are normally the first-level subdivision of a program and that programs
are more ongoing than projects. - Air Force Definition
1.2: Project management, benefit and limitation of project management
Project management:
Objectives-oriented
Change-oriented
Single responsibility Centre
Team based
Functional coordination
Planning and control
Constraints (Time, Scope, Quality)
Benefits of Project management:
Identification of functional responsibilities to ensure that all activities are accounted for,
regardless of personnel turnover.
Minimizing the need for continuous reporting
Identification of time limits for scheduling
Measurement of accomplishment against plans.
Early identification of problems so that corrective action may follow
Improved estimating capability for future planning
Knowing when objectives cannot be met or will be exceeded
Limitation of Project Management:
Objectives: A project has a set of objectives. Once the objectives are achieved the project
is treated as completed.
Life cycle: A project has a life cycle. The life cycle consists of four stages.
Uniqueness: Every project is unique and no two projects are similar. Setting up a cement
plant and construction of a highway are two different projects having unique features.
Team Work: Project is teamwork and it normally consists of diverse areas. There will be
personnel specialized in their respective areas and co-ordination among the diverse areas
calls for teamwork.
Complexity: A project is a complex set of activities relating to diverse areas.
A Programme is an extensive and consistent set of action units stating the needs of
interrelated activities to achieve the plan’s objective and goal.
In other words, a Programme is a group of complementary activities of which common
purpose is directed to make a plan successful.
There could be several Programmes within a plan or within a development plan.
Project
Projects are the time-bound specific action units or schemes designated for the
investment of resources with an aim of achieving its established objective/s.
Resources could be in terms of money, materials, human, time, technology, information
etc.
There could be a number of projects functioning either independently or jointly within a
Programme.
Projects always remain at the bottom level of a plan.
Thus, projects are the building blocks of a Programme and programs are the integrated
blocks of a development plan.
A literature review provides the context for your project, by examining and
acknowledging the work of others, and allowing you to establish your position.
It shows Sponsor that you are familiar with significant project in your area and justifies
the importance of your project.
literature review should address:
o What project has already been undertaken in this field/on this sector?
o What were the results and conclusions of this project?
o How do the findings from other project inform the investigation or study of my
project?
o What gaps exist in the literature that will justify my project and ensure the project
hasn't been done before?
The need arises from a problem or situation (internal or external) that either threatens
the organization or presents it with a valued opportunity.
The need may be for a new product or service, for a new process or system, even for
developing new markets; or it may be for cutting back and retrenching a division.
A critical need prompts general management to initiate a project management team.
Benefit/opportunity to the organization for undertaking the project.
The statement should be short, crisp, and to the point.
It should serve as a descriptor for those who although not directly involved on the project
may be indirectly involved in supporting the project.
2.4: Determining project goals
The ultimate result of the program or project is contributing- the impact of the program
or project. Examples, Millennium Development Goals (MDGs), such as (a) improve
maternal health; (b) reduce child mortality; etc.
It is the continual point of reference for settling disputes and misunderstandings about
the project.
This may be a very short but specific statement such as: “Plan and conduct the annual
meeting."
The important thing to remember is that the goal statement must be phrases using
terms that would not mislead anyone.
It must also use terms that measure its completion. For example, "Write the annual
report" is an activity whose completion cannot be measured. On the other hand,
"Receive approval of the annual report” is an activity whose completion is known
once the approving signature is on the document.
Also remember that the project goal directs the course of the entire effort.
The goal will be the standard for resolving conflicts, for clarifying expectations, for
requesting and justifying resources.
The goal is the most important statement for initiating the project.
TOR defines the purpose and structures of a project, to accomplish a shared Goal.
Often referred as the project charter.
Creating detailed TOR is critical, as they define the:
o Vision, objectives, scope (i.e. what has to be achieved),
o Stakeholders roles and responsibilities (who will take part in it)
o Resource, financial and quality plans (how it will be achieved)
o Work breakdown structure and schedule ( when it will be done)
This phrase is often used when describing the task that has been assigned to a
consultant or advisor.
Terms of reference should also provide a documented basis for making future decisions
and developing a common understanding of the scope among stakeholders.
A request for proposal (RFP) is a document that solicits proposal, often made through a
bidding process, by an agency or company interested in procurement of a commodity,
service or valuable asset, to potential suppliers to submit business proposals.
It summarizes the bidding process, contract terms, and provides guidance on how the bid
should be formatted and presented.
The complexity of a project may result for a formal request for proposal.
For e.g., a project moving from a paper-based system to a computer-based system may
request proposals for the hardware, software and user training needed for establishing
and integrating the new system into the project.
Requests for proposals may include a statement of work describing tasks to be performed
by the winning bidder and a timeline for providing finished work.
Another e.g., the MOH issues a request for proposals for financing, designing, constructing,
and maintaining Birthing center building.
Interested parties submit proposals meeting the requirements outlined in the document.
Based on the proposals received by the deadline, the MOH establishes commissions for
further review and development of the proposals.
Statement of Purpose: Describe the extent of products and services your organization is looking
for, as well as, the overall objectives of the contract.
Background Information: Present a brief overview of your organization and its operations,
using statistics, customer demographics, and psychographics. State your strengths and
weaknesses honestly. Don’t forget to include comprehensive information on the people who will
handle future correspondence.
Scope of Work: Enumerate the specific duties to be performed by the provider and the expected
outcomes. Include a detailed listing of responsibilities, particularly when sub- contractors are
involved.
Outcome and Performance Standards: Specify the outcome targets, minimal performance
standards expected from the contractor, and methods for monitoring performance and process
for implementing corrective actions.
Deliverables: Provide a list of all products, reports, and plans that will be delivered to your
organization and propose a delivery schedule.
Term of Contract: Specify length, start date and end date of the contract, and the options for
renewal.
Payments, Incentives, and Penalties: List all the terms of payment for adequate performance.
Highlight the basis for incentives for superior performance and penalties for inadequate
performance or lack of compliance.
Contractual Terms and Conditions: Attach standard contracting forms, certifications, and
assurances. You may include requirements specific to this particular contract.
Requirements for Proposal Preparation: A consistent structure in terms of content,
information, and documents types simplifies things for the people evaluating the proposals.
Therefore, you should request a particular structure for the proposal and provide an exhaustive
list of documents you want to receive.
Evaluation and Award Process: Lay down the procedures and criteria used for evaluating
proposals and for making the final contract award.
Process Schedule: Clearly and concisely present the timeline for the steps leading to the final
decision, such as the dates for submitting the letter of intent, sending questions, attending the
pre-proposal conference, submitting the proposal, etc.
Points of contact for future correspondence: Include a complete list of people to contact for
information on the RFP, or with any other questions. Incorporate their name, title,
responsibilities, and the various ways of contacting them into this list.
Project planning: Project planning is part of project management, which relates to the use of
schedules such as Gantt charts to plan and subsequently report progress within the project
environment. Initially, the project scope is defined and the appropriate methods for completing
the project are determined.
Project Planning: The process of developing a project from determining the needs and
problems to creating activities and writing a budget. Project planning involves a series of steps
that determine how to achieve a particular community or organizational goal or set of related
goals.
Project development: The project development process is initiated in response to an identified
need in the transportation system. It covers a range of activities extending from identification of
a project need to a finished set of contract plans, and to construction
There are typically four major cost categories that may be defined for any activity:
• Labor Cost
• Materials Cost
• Other direct (travel, telephone, contracted services, etc.)
• Indirect cost
• In some cases indirect cost may be a fixed percentage of total direct costs attributable
at the project level rather than at the activity level.
• As a general practice the unallocatable costs, such as administrative overhead,
utilities, building depreciation, etc., are computed as a fixed percentage of total
direct costs.
Using the activities as they are represented in the WBS we can construct the sequence in
which the project activities will be done.
Because each activity has an associated cost and an estimated completion time.
We can build an estimate of the total project cost and completion time.
Simply recognizing that some activities may be done simultaneously (at once) and that
others must be done sequentially (in order) is enough to grasp the complication in
scheduling activities and estimating project completion time.
Identify Critical Activities
The project proposal represents the transition from planning (define, plan) to
implementation (organize, control, close).
It is the foundation on which all management decisions will be made.
A complete description of the project activities, timeline, and resource requirements.
Needed by management to decide whether the project should proceed to the
implementation phase.
A dynamic tool for the project manager and project team to use for decision making
throughout the project life cycle.
Elements of Project Proposal
Project Name
Project Manager
Activity
Schedule
Project Budget
3. Organizing Stage
Technical Expertise
Interpersonal Competence/People Skills
Background and Experience
Proven Managerial Ability
Leadership and Strategic Expertise
Recruit Project Manager
Recruit Project Manager having balanced set of general characteristics for successive completion
of the project in effective and efficient manner.
Organize Project
Organize all human and non- human resources to achieve organizational goal effectively and
efficiently within time and budget constraints
Man Technology
Money Information
Material Time
The work package consists of tasks each of which is continuous activities that can be
assigned to a single individual.
The scheduled start and end date for every task in the work package has been specified.
Managing work packages is aided through the use of simple forms that define exactly what
is to be done, by when, and by whom.
The same form can be used to monitor the status of work packages.
The work package managers clearly understand what is expected and by when.
The resources necessary for each work package have been committed and are available
according to the project schedule.
The task descriptions have been reviewed and approved by the work package manager
and the project manager for completeness.
The persons responsible for the tasks that comprise the work package have reviewed and
understand their task, the expected deliverables, and the timeline.
4. Controlling Stage
Define management style
Establish control tools
Project schedule
Change Orders
The project manager has delegated the appropriate responsibility and authority to the
work package managers to complete their work on time, within budget, and according to
specifications.
The reporting and control system is compatible (well suited) with that of the organization.
The reporting system will alert the project team about out-of-control situations early
enough to take positive corrective action.
Graphical Reporting Tools
A simple graphical way to convey the variance from plan information with cumulative cost
or time.
Managers' time is valuable. To force them to read page after page of data is to waste their
time.
A report that identifies actual performance and clearly display the variance.
For example, the project manager may want to be alerted to any variance that is more
than 10 percent above or below plan.
Exception Report
It is a very important piece of document that is essential to the proper and effective
functioning of a project.
It actually itemizes and documents the major mistakes, or mishaps (unfortunate events).
Essentially the things that went wrong.
It provides a carefully written documentation of the mistakes for look back at a later point
within the life of a project hoping of avoiding making the same mistakes again; however,
it is also important for future projects.
Gantt Charts
A Gantt chart is one of the most convenient, most used, and easy-to-grasp depiction
(picture) of project activities
It is a two-dimensional graphical representation of the activities that include in the
project.
The vertical dimension lists the project activities-one per line-while the horizontal
dimension is time.
Once the scheduled start and completion date of each activity has been determined, the
Gantt chart can be constructed.
The value of a Gantt Chart is the scaling of project activities according to their duration
A project schedule designates work to be done and specifies deadlines for completing
tasks and deliverables.
The project schedule depicts:
Time (duration) estimates for all project tasks
Start and finish dates for the tasks
Names of staffs assigned to complete the tasks
Sequence of tasks
A major component of a project schedule is WBS (work breakdown structure).
The project schedule is constructed to reflect the WBS
Rationale/Purpose
The project manager uses the schedule to help plan, execute and control project tasks and
to track and monitor the progress of the project.
The project schedule defines timelines for key deliverables and sets expectations for
project progress and completion.
Who is involved? Project Manager Project Team
Change Orders
A change order is a document that contractually alters an original agreement between the
signed parties.
Relative to construction, a change order is the result of an owner approved revision to
terms and conditions that are defined in a contract for a project.
Change order is directed by the owner or request by the contractor.
Depending on its specific requirement, a change may or may not impact a project’s
contractual cost and schedule.
If cost is affected, a change may be increased or credited.
Similarly, the duration of activities in a project schedule is identified with change may be
extended or reduced.
Contracts include different conflicting clauses regarding changed work. Eg. The
contractor cannot proceed the work for a change in the absence of a written and approved
change order/the owner has the right to order the contractor to perform extra work
without an agreement for compensation.
The resolution of chance orders can also become source of disputed issues between
owner and contractor.
The disputed issues become further intensified if the chance order process is
inadequately managed
5. Closing Stage
Project deliverables are the products or services that are given to your clients/customers.
Deliverables usually have a due date and is tangible (real), measurable and specific.
A deliverable can be given to either an external or internal customer and satisfies a
milestone or due date.
Without deliverables, projects would be pointless; deliverables are why projects are
created.
Project deliverables are not objectives themselves, but deliverables and objectives are
very closely related.
Objectives are statements of what you plan to accomplish.
Deliverables help to achieve project objectives. For e.g. if your objective is to understand
your customers, you need a customer profile (deliverable).
Examples of Project deliverables
WBS , Variance Reports, Project Network, Critical Path, Work Package Description,
Recruitment Criteria, Work Package Assignments Project Proposal, Staff Allocation
Reports Status Reports, Audit Report, Final Report
Ensure that all deliverables have been installed or implemented according to time,
budget, and specifications
Document completion and compliance with all contractors, consultants, and services
purchased and received.
Prepare a document file of all vendors and contracted services and products terminated.
Ensure that adequate project documentation and baseline information are in place to
facilitate changes that may need for future.
Overall success and performance of the project (using the post-implementation audit
results)
Organization and administration of the project
Techniques used to accomplish project results
Assessment of project strengths and weaknesses
Recommendations from the project manager and team for continuation or extinction of
the project
Conduct post implementation audit
The post-implementation audit is an evaluation of the project's goals and activity achievement as
measured against the project plan, budget, time deadlines, and quality of deliverables,
specifications, and client satisfaction.
The log of the project activities serves as baseline data for this audit. The driving questions
include-
What are the probable time, money, and personnel cost to complete this project?
The project manager determined the needed resources based on the project plan.
3.1.6: Allocate responsibilities for each activity
The project proposal represents the transition from planning (define, plan) to
implementation (organize, control, close).
It is the foundation on which all management decisions will be made.
A complete description of the project activities, timeline, and resource requirements.
A dynamic tool for the project manager and project team to use for decision making
throughout the project life cycle
Project planning is part of project management, which is related to the use of schedules,
to plan and subsequently report progress within the project environment.
Project planning is often used to organize different areas of a project, including project
plans, workloads and the management of teams and individuals.
The inputs of the project-planning phase include the project charter and the concept
proposal.
The outputs of the project-planning phase include the project requirements, the project
schedule, and the project management plan.
Project Planning can be done manually.
Project planning begins by setting the scope of a project and eventually working through
each level of dependent actions, tasks, checkpoints and deadlines.
Definition of project planning
Project planning is the process of thinking through and making explicit the project’s
objective, goal and strategies necessary to bring the project through its life cycle to the
successful termination. David I. Cleland
Project planning is a discipline for stating how to complete a project within a certain
timeframe, usually with defined stages, and with designated resources.
A Project Plan sets out the phases, activities and tasks needed to deliver a project.
The timeframes required to deliver the project, along with the resources and milestones
are also shown in the Project Plan.
Importance of project planning
After the initiation stage, the project is planned to an appropriate level of detail.
The main purpose is to plan time, cost and resources adequately to estimate the work
needed and to effectively manage risk during project execution.
A failure to adequately plan greatly reduces the project's chances of successfully
accomplishing its goals.
It also help to identify the roles and responsibilities
Project planning generally consists of;
1. Determining how to plan
2. Developing the scope statement;
3. Selecting the planning team
4. Identifying deliverables and creating the work breakdown structure
5. Estimating the resource requirements for the activities
6. Estimating time and cost for activities
7. Developing the schedule
8. Developing the budget
9. Risk planning
10. Gaining formal approval to begin work
3. Project execution or production stage:
Executing consists of the processes used to complete the work defined in the project
management plan to accomplish the project's requirements.
Execution process involves coordinating people and resources, as well as integrating and
performing the activities of the project in accordance with the project management plan.
The deliverables are produced as outputs from the processes performed as defined in the
project management plan.
Closing includes the formal acceptance of the project and the ending thereof.
Administrative activities include the archiving of the files and documenting lessons
learned.
This phase consists of:
o Project closing
o Contract closing
Project close
Finalize all activities across all of the process groups to formally close the project or a
project phase.
Contract closure
Complete and settle each contract (including the resolution of any open items) and close
each contract applicable to the project or project phase
3.2.2: Logical frame work approach in project planning- Concept, definition and major
steps in LFA
Meaning of log frame, element of log frame and development of log frame matrix
The first logical framework developed for USAID at the end of 1960’s.
LFA is a methodology mainly used for designing, monitoring & evaluating international
development projects.
LFA is a systematic planning procedure for complete project cycle management.
It is a problem solving approach, which takes into account the views of all stakeholders.
It also agrees on the criteria for project success and lists the major assumptions
A situation analysis has as its core task to find out the actual state of affairs with respect
to an issue to be analyzed; it is focused by problems and an attempt to understand the
system which determines the existence of the problems.
The situation analysis phase is the most critical, yet most difficult, phase of the log frame
approach.
The situation analysis phase consists of three stages
Stakeholder analysis is a tool for clearly defining key stakeholders for a project or other activity,
understanding where stakeholders stand, and developing cooperation between the
stakeholders and the project team. Key questions to ask in preparation for developing the log
frame are:
The problem tree is developed by moving problems from the clusters of problems on the
wall and by adding new problems that emerge as the tree is developed.
Problems can be moved up or down the tree as required.
The tree should end up with one of the main problems and a series of lower order
problems that branch out below the main problem.
The problem tree is constructed by selecting a problem from the list and relating this
problem to a starter problem using the cause-effect rationale described below:
If the problem is a cause of the starter problem it is placed below the starter problem If
the problem is an effect of the starter problem it goes above If it is neither a cause or effect
it goes at the same level.
Objectives Analysis: Objectives are lower level statements that describe the specific, tangible
products and deliverables that the project will deliver.
3.2.3: Meaning of log frame, element of log frame and development of log frame matrix
A log frame is a tool for improving the planning, implementation, management, monitor- ing and
evaluation of projects. The log frame is a way of structuring the main elements in a project and
highlighting the logical linkages between them.
GOAL
PURPOSE
OUTPUTS
ACTIVITIES INPUTS
The LOGFRAME MATRIX is a participatory Planning, Monitoring & Evaluation tool whose
power depends on the degree to which it incorporates the full range of views of intended
beneficiaries and others who have a stake in the programme design.
It is a tool for summarizing the key features of a programme and is best used to help
programme designers and stakeholders.
Develop a common understanding of the expectations of a programme by delineating a
hierarchy of aims;
Define indicators of success and establish criteria for monitoring and evaluation;
Define critical assumptions on which the programme is based; and
Identify means of verifying programme accomplishments
Log frame matrix serves following functions
3.2.4: Time management and development of work plan/GANNT chart, its importance in
project management.
Time Management
Time is money. Time is the greatest resource. Time is a highly perishable commodity an
individual possesses.
We have to be concerned in managing time more effectively for greater accomplishment.
Organizing One's Job to Function More Effectively
From the management, point of view, Peter Drucker has come out with a very strong
notion which unwarily every manager knows it. He said “Time is the scarcest resource,
and unless it is managed, nothing else can be managed”.
It does appear that time is most valuable resource a manager has and if he can manage it
effectively and efficiently by consideringcertain concepts of ‘Time Management System’,
he will be able to manage any other resources.
To make it more concise, generally speaking, there are six steps in managing time:-
Analyzing time use- discovering what is happening now and what should be changed.
Clarifying objectives establishing a basis for evaluating the best use of our time.
Setting priorities focusing on the activities that are most valuable
Planning time- making sure that our activities match our objectivities
Scheduling –arranging our day to get more done in less time
Evaluating Programmes-determining if things are working out well
In the late 1800s, Polish engineer Karol Adamiecki developed a visual work flow chart
that he called a "harmonogram." A Gnatt chart is a visual project management tool
developed by Henry Laurence Gnatt, an American mechanical engineer and social
scientist.
In around 1910, Henry Gantt, a management consultant and engineer, took Adamiecki's
concept to the next stage.
His chart was designed to help manufacturing supervisors see whether their work was
on, ahead of, or behind schedule, and it formed the foundation of the tool we use today.
The main objective of a Gantt chart is to assess how long a project should take and to
establish the order in which tasks need to be carried out by the ending of the project
o It is a graphical representation of the duration of tasks against the progression of
time also known as bar chart, time line or milestone chart.
o In other words, they can show the progress and the detailed time frame, from start
to finish, for an assignment.
o It is frequently used in project management, it provides a graphical illustration of a
schedule that helps to plan, coordinate, and track specific tasks in a project.
o It displays time on the horizontal axis and arranges the activities vertically, from top
to bottom, in the order of their start dates.
o The horizontal position of the bar shows the start and end of the activity, and the
length of the bar indicates duration.
o Provide a graphical illustration of a schedule that helps to plan, coordinate and track
specific task in a project.
o A Gnatt chart is a useful tool for planning, scheduling projects and monitoring a
project's progress.
o It lets you see immediately what should have been achieved at any point in time.
o A Gnatt chart lets you see how remedial action may bring the project back on course.
An estimate of costs, revenues, and resources over a specified period, reflecting a reading
of future financial conditions and goals.
One of the most important administrative tools, a budget serves also as a
o Plan of action for achieving quantified objectives,
o Standard for measuring performance, and
o Device for coping with foreseeable adverse situations.
A budget is a statement of future expenditure for planning and controlling project’s
financial resources.
The budget is a plan for income and expenses for certain period of time usually one year
period.
A budget is a statement of future expenditures and incomes for planning and controlling
financial resources. It is generally one year period.
Budget is a plan for allocation of resources and a control making sure that results comply
(fulfill, abide by) with the plans.
“Budget is an operational plan for a definite period usually a year expresses in financial
terms and based on expected income and expenditure”.
“Budget is formal quantitative statement of the resources set aside for carrying out
planned activities over periods of time” (Stoner, 1995).
Purpose of Budget:
The primary purpose is to ensure the most effective use of scarce financial and non–
financial resources.
The secondary purposes are:
o To coordinate efforts among the department or units within the organization;
o To provide the frame of reference for the managerial decisions;
o To provide criterion for measuring the managerial performance.
Advantages:
Personal investment
Venture capital
Business incubators
Government grants and subsidies
INGOS/NGOS supports
Bank loans etc
3.3.3: Transparency of project fund process
Transparency in Project Management: The more knowledge someone has about the status of
a project, the easier it is to make a decision. If we can transparent in all level of project activity it
would be better for the organization.
Evaluator can evaluate of Project transparency from the following:
Revenue
Grants
Foundation (non-profit)
Investment
Crowd funding
Seed money
Micro finance
Mutual fund
Trust Fund
Equity fund and
others
The allocation of project tasks to project team within the project organization.
It is based on plans and design set down during the project planning phase
Project should be implemented effectively
Phase of project implementation
1. Preparing for project implementation
2. Engaging and supervising consultants
3. Contracting for civil works: prequalification’s, tendering, awarding contract
4. Procurement of goods, services, equipments
5. Supervision of equipment installation and civil works
6. Receiving project budget
7. Monitoring and control.
1. Preparing for project implementation
Step for implementation, It involves
Guidelines, procedures, financial rules and regulation are followed for contracting of civil
works
Selection of contractors is based on
Tender document(including engineering design)
Prequalification of contractors
Financial rules and regulations and guidelines for procurement of required goods,
services and equipment for the projects are followed
Procurement can be through direct purchase from the market
Quotation-based, generally three quotations are required
Tender-based, which can be local, national or global
5. Supervision of equipment installation and civil works
The financial resources for the project are required from the donor or customer
International donor agencies generally provide budget on a reimbursement basis
A separate project account is opened in the bank for each project
7. Monitoring and control
This category refers to internal monitoring of financial, physical and organizational issues
affecting the project.
Financial monitoring tracks project inputs and costs by activity within predefined
categories of expenditure.
Physical monitoring tracks the distribution and delivery of project activities and
outputs/interventions.
Organizational monitoring tracks sustainability, institutional development and capacity
building in the project and direct partners.
2. Context Monitoring
The process of tracking the context in which a project is operating, as it affects critical
assumptions and risks to the project.
This includes monitoring institutional and policy issues that may affect the capacity of the
project to act or the capability of the target population to respond to the project.
These concerns are handled to some extent during monitoring, but principally during
evaluations.
3. Results Monitoring
The process of tracking project objectives and strategies for continuing relevance to the
target population and its changing needs
5. Project monitoring Matrix
It ensures that right things are done in the right manner and at the right time.
Control is measuring, evaluating and correcting actual performance to achieve panned
targets.
4.4.1: Financial control process
The first step is to conduct an exhaustive, reliable and detailed analysis of the company’s
situation across various areas: cash, profitability, sales, etc.
Step 2.Preparation of Forecasts and Simulations
On the basis of the initial situation analyzed above and the establishment of a set of
parameters or indicators, a set of forecasts and simulations of different contexts and
scenarios can be prepared.
These simulations are immeasurably helpful in making appropriate decisions on such
crucial aspects as investments, profitability, changes in production systems, etc.
Step 3. Detection of deviations in the basic financial statements
The basic financial statements are the documents which must be created by the
company in preparing the annual accounts.
o The three most important documents are the general balance sheet, the profit
and loss account and the cash flow statement.
o These analyses and tests in different environments are a fundamental part of
financial control, since they permit problems, errors and deviations from the ideal
situation or initial objectives to be detected early
Step 4. Correction of deviations
Process of obtaining the human resources needed for completing the project.
Inputs
Tools & Techniques
Outputs
Develop Project Team
Plans targeting the improvement of team competencies and interaction of team members
to enhance project performance throughout the project life cycle.
Objectives
Improve skills of team members in order to increase their ability to complete project
activities.
Improve feelings of trust and cohesiveness among team members in order to raise
productivity through greater teamwork
Activities control process
Consultive: The manager discuss with subordinates to gather information, then makes
the decision himself / herself.
Democratic: The manager solicits not only information from subordinates but also
request their involvement in the generation of alternatives and selection of decision.
Establish control tools
By comparing the planned schedule of activities with what actually happened, the project
manager will be aware of variances from plan and help to take appropriate corrective
measures.
Project variance report:
Total
The project manager has delegated the appropriate responsibility and authority to the
work package managers to complete their work on time, within budget, and according to
specifications.
The reporting and control system is compatible (well suited) with that of the organization.
The reporting system will alert the project team about out-of-control situations early
enough to take positive corrective action.
Graphical reporting tool
A simple graphical way to convey the variance from plan information with cumulative
cost or time.
A report that identifies actual performance and clearly display the variance.
For example, the project manager may want to be alerted to any variance that is more
than 10 percent above or below plan.
Exception report
It is a very important piece of document that is essential to the proper and effective
functioning of a project.
It actually itemizes and documents the major mistakes, or mishaps (unfortunate events).
It provides a carefully written documentation of the mistakes for look back at a later point
within the life of a project, hoping of avoiding making the same mistakes again;
A Gantt chart is one of the most convenient, most used, and easy-to-grasp depiction
(picture) of project activities.
The vertical dimension lists the project activities-one per line-while the horizontal
dimension is time.
Once the scheduled start and completion date of each activity has been determined, the
Gantt chart can be constructed.
The value of a Gantt chart is the scaling of project activities according to their duration.
The project manager uses the schedule to help plan, execute and control project tasks and
to track and monitor the progress of the project.
The project schedule defines timelines for key deliverables and sets expectations for
project progress and completion.
Who is involved?
Project Manager
Project Team
A project schedule designates work to be done and specifies deadlines for completing
tasks and deliverables. The project schedule depicts:
o Time (duration) estimates for all project tasks
A change order is a document that contractually alters an original agreement between the
signed parties.
Depending on its specific requirement, a change may or may not impact a project’s
contractual cost and schedule.
Similarly, the duration of activities in a project schedule is identified with change may be
extended or reduced.
4.5: Evaluation
Project evaluation
Baseline study
Annual review
Mid-term evaluation
Final evaluation
Ex-post evaluation
Baseline Study
The assessment of a selected set of indicators about target population conditions after
project start-up but before the beginning of project interventions.
Annual Review
The internal assessment of the performance and progress of a project’s development over
successive one-year periods.
Usually includes an assessment of effects (target population responses to project
outputs/interventions) and project strategies
Mid Term Evaluation
Usually an external (and thus ‘objective’) assessment of a project, which focuses on its
performance, organizational capacity, and mid-course corrections to improve
achievement in the remaining project period.
Final Evaluation
An external or internal assessment of the effects and impacts generated by the project, as
well as cost-effectiveness or cost-benefit assessment.
Usually done just before or just after the project ends.
Ex-post evaluation
An external and in-depth study of the impact of a project on the target population.
The preferred interval between project termination and an ex-post evaluation is 5-10
years.
Rarely done due to lack of donor willingness to fund
It means the project work as scheduled is either successfully or unsuccessfully done and
the decision to terminate is agreed upon.
Closing relationships and preparation of the final report must be completed.
This type of termination may cause more stress if the originally planned goals of the
project may not have been achieved.
The project may end because it has been successful and achieved its goals
The project may also be stopped because it is unsuccessful or has been superseded.
A special case of termination by extinction is “termination by murder” which can range
from political assassination to accidental projecticide.
Termination by inclusion
Termination process can be as complicated and lengthy as the size, complexity, and scope
of the project itself.
A systematic process is required to assist the PM in order to terminate contracts and
relationships successfully.
Steps of Termination process
1. Prepare Termination logistics,
2. Document the Project,
3. Conduct post-implementation audit and prepare and submit final report,
4. Obtain client approval, and
5. Close operations.
Prepare termination logistics
Purpose
Audience
Issues
Resources
Evidence
Data gathering technique
The cycle is completed only when the development objectives are realized. Closing the
project with a celebration of the effort. The project manager's last effort is to bring the
team together to review their journey. This is a way of closing informal as well as formal
relationships.
Not all projects terminate on a cheerful mood.
A final meeting, party, dinner, or celebration brings the project life cycle full circle come
to the end
Importance of Termination
Time to move on: when a project is nearing completion, It is tempting for project
manager and team to turn their focus to the next project in the horizon and start to put
their efforts in to new pieces of work rather than closing down the current project
correctly before moving on.
Administrative Closure
Following activities must be address in the project closure plan:
It is a level of performance that describes a process that uses the lowest amount of inputs
to create the greatest amount of outputs.
It can also be stated as the act of being adequate in performance with a minimum of waste,
effort, time.
Efficiency can only be delivered by improving productivity, procurement processes,
working practices
Meaning of Effectiveness
Output:
Outputs are those results which are achieved immediately after implementing an activity.
For example, if we are organizing a workshop on human rights, participants who attended
it have now got a clear understanding on human rights issues. So, this is an output the
project has achieved and it is achieved right after the conclusion of the workshop.
The term output refers specifically to any particular services, results, and or products that
are generated as a result of a particular project related process.
Output can come in a multitude of formats from written long form reports, written short
form reports, other verbal means of output.
Output may also be a formalized type of material or it can be inform and in some cases
informational only.
Outcomes
Outcomes can be considered as mid-term results. They are not seen immediately after the
end of the project activity. But after some time, when we see some change at the ground
level because of the project activity, then it can be termed as an outcome.
Taking the above example of a human rights workshop, if the participants have started to
mobilize their community members to seek their human rights, then it is an outcome of
the project.
Results of the changes derived from the use of the project's specialist outputs by the users.
PERT (Program Evaluation and Review Technique) is used to assist in project scheduling similar
to CPM
4. Estimation of Activity Times: Weeks are a commonly used unit of time for activity to be
completed, but any consistent unit of time can be used, for example, hours or days. A
distinguishing feature of PERT is its ability to deal with uncertainty in activity completion
times. For each activity, the model usually includes three time estimates:
Optimistic time- generally the shortest time in which the activity can be completed. It is
common practice to specify optimistic times to be three standard deviations from the
mean so that there is approximately a 1% chance that the activity will be completed
within the optimistic time.
Steps of CPM:
1. List the activities to be considered in approximate order.
2. Number the events, estimate the time required for each, and determine the antecedents.
3. Arrange the events in a CPM diagram showing the numbered events, time required, and
antecedent relationships with connecting lines.
4. Determine the earliest times for starting and ending the events.
5. Determine the latest times for starting the events.
6. Determine the critical path.
Comparison between PERT and CPM
What is it? A technique of planning and A method to control cost and time.
control of time.
Suitable for Research and Development Project Non-research projects like civil
construction, ship building etc.
Strengths: attributes of the person or company that is helpful to achieving the objectives.
Weakness: attributes of the person or company that is harmful to achieving the
objectives.
Opportunities: external conditions that is helpful to achieving the objectives.
Threats: external conditions which could do damage to the objectives.
SWOT matrix is an important matching tool that helps managers to develop four types of
strategies: i.e. SO, ST, WO AND WT. Matching key external and internal factors is the most difficult
part of SWOT matrix, and requires good judgment and there is no one best set of matches.
Always match O with S (make SO strategy), O with W (make WO strategy), T with S (make ST
strategy) and T with W (and make WT strategy).
6.6: Overview of Environmental Impact Assessment (EIA)
EIA can be defined as the study to predict the effect of a proposed activity/ project on the
environment.
EIA compares various alternatives for a project and seek to identify the one which
represents the best combination of economic and environmental costs and benefits.
EIA can often prevent future liabilities or expensive alternations in project design
Core values of EIA
Integrity: the EIA process should be fair, objectives, unbiased and balanced.
Utility: the EIA process should provide balanced, credible information for decision
making.
Identify risks.
Perform qualitative risk analysis.
Perform quantitative risk analysis.
Plan risk responses.
Monitor and control risks.
A report is any information work (usually of writing, speech, television or film) made with
the specific Intention of relaying information in a widely presentable form.
A document containing information organized in a narrative, graphic or tabular form
prepared on ad hoc, periodic, recurring, regular, or as required basis.
Reports may refer to specific periods, events, occurrence or subjects and may be
communicated or presented in oral or written form.
Reporting
Reporting is the process of communicating the recorded information to the higher or any
other level.
Reporting is the written or oral information communicated to the higher level offices
about the programme activities, progress, problems and suggestions for improvement.
Reporting and recording are interdependent activities.
Reporting should be carried out at various intervals.
Reporting is one of the most important managerial functions and thus should be carried
out promptly and accurately.
Sound
Well defined
Concise
Itemized
Discrete, especially towards the feelings of persons likely to be affected
Fully considered, including their consequences, which should be stated and costed, where
appropriate?
Part 5: Appendices: True appendix material is that which the reader does not need to study in
order to understand the report, but which he may turn to if wishes to examine in detail the
supporting evidence. It includes;
Statistical tables
Detailed result of experiments, series of graphs
Summaries of results obtained elsewhere
Correspondence
Lengthy quotations from outside authority
Maps, charts and diagrams
Part 6: Bibliography: A bibliography is a list of works consulted by the author of the report. It has
two purposes:
To show the extent to which the author ‘cast his net’ in gathering information.
To help the reader, and particularly the student, to find suitale background reading matter
on the subject of the report.
1. Technical proposal
A technical proposal, often called a "Statement of Work”.
Objectives: -
A financing proposal contains the details on how you intend to achieve your business plan
outlining:
Amount of money needed
How that money will be used
Expected returns
Security
Financial Proposal will be based on project plan, which is basically a written summary of
what your project is, where you intend to take it, and how you plan to get there.
Cover page: company name, address, telephone number, email address, website and key
contacts
Table of contents: referenced by page numbers
Summary: one page about the company
Industry Overview: overview of your business highlighting key dates and facts
Management structure: background, qualifications and responsibilities
The products and services
The market: previous and forecasted financial performance of production and supply
Financing outline: emphasizing application of funds
Basic information: bank, accountants, lawyers, incorporation, board of directors;
shareholders
Appendices: detailed management biographies, product literature, valuations of assets,
financial statements (preferably audited), detailed projections – profit & loss, cash flow
and major contracts.