PEMBANGUNAN CLARIFIER IWTP PHASE - 1 Doc.

No : SAJR/SCS/CRF/MS/01
PT SURYACIPTA SWADAYA Date : 22 December 2020
KARAWANG Rev. :2
Desember Januari februari Maret April Mei Juni
No Uraian Pekerjaan Satuan Volume Bobot W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26
11-20 21-27 28-3 4-10 11-17 18-24 25-31 1-7 8-14 15-21 22-28 1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-2 3-9 11-16 17-23 24-30 31-6 7-9

A Pekerjaan Persiapan

1 Mobilisasi dan Demobilisasi ( Tenaga,Alat Kerja Dan Matrial ) ls 1.00 0.557% 0.139% 0.139% 0.139% 0.139%

2 Keamanan Lapangan ls 1.00 0.414% 0.069% 0.069% 0.069% 0.069% 0.069% 0.069%

3 Direksi Keet + Listrik , Air kerja ls 1.00 1.588% 0.265% 0.265% 0.265% 0.265% 0.265% 0.265%

4 Shop & As-built Drawing ls 1.00 0.413% 0.103% 0.029% 0.074% 0.103% 0.088% 0.015%

5 Laporan Progress & Foto Dokumentasi ls 1.00 0.236% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020% 0.020%

6 C.A.R ( Include 3 Person Owner ) ls 1.00 0.787% 0.047% 0.028% 0.028% 0.033% 0.033% 0.033% 0.033% 0.033% 0.028% 0.033% 0.033% 0.028% 0.028% 0.033% 0.033% 0.028% 0.033% 0.033% 0.033% 0.028% 0.033% 0.009% 0.033% 0.028% 0.028% 0.014%

7 Tes Kebocoran / Tes Rendam ls 1.00 0.331% 0.050% 0.116% 0.033% 0.116% 0.017%

8 Tes Tarik Besi Beton / Tes Tekan Mutu Beton ( I T B ) ls 1.00 0.427% 0.131% 0.033% 0.033% 0.066% 0.033% 0.033% 0.066% 0.033%

9 Pengukuran / bouplank ls 1.00 0.315% 0.079% 0.067% 0.011% 0.034% 0.011% 0.022% 0.011% 0.022% 0.011% 0.011% 0.011% 0.011% 0.011%

10 Proteksi Lokasi Kerja ls 1.00 0.413% 0.025% 0.015% 0.015% 0.017% 0.017% 0.017% 0.017% 0.017% 0.015% 0.017% 0.017% 0.015% 0.015% 0.017% 0.017% 0.015% 0.017% 0.017% 0.017% 0.015% 0.017% 0.005% 0.017% 0.015% 0.015% 0.007%

11 Safety / HSE ls 1.00 0.497% 0.030% 0.018% 0.018% 0.021% 0.021% 0.021% 0.021% 0.021% 0.018% 0.021% 0.021% 0.018% 0.018% 0.021% 0.021% 0.018% 0.021% 0.021% 0.021% 0.018% 0.021% 0.006% 0.021% 0.018% 0.018% 0.009%

12 Pembersihan Lokasi ls 1.00 0.241% 0.052% 0.021% 0.021% 0.016% 0.037% 0.010% 0.016% 0.005% 0.021% 0.026% 0.016%

13 Soil Test / Sondir Ttk 2.00 1.842% 0.921% 0.921%

Sub Total A 8.060%

B Pekerjaan Clarifier

1 Bor pile f 40 cm , L = 15 m ( K 350 ) nos 9.00 3.386% 0.806% 1.129% 1.129% 0.322%

2 Bobok Borpile f 40 cm nos 9.00 0.109% 0.109%

3 Galian tanah dan Buang Disposal ( Jarak 2 km ) m3 76.50 1.109% 0.222% 0.222% 0.259% 0.259% 0.148%

4 Lean Concrete t = 5 cm K175 m3 5.10 0.188% 0.188%

5 Compacted Sand t = 10 cm m3 10.20 0.167% 0.167%

6 Bekisting (EXPOSE) m2 394.43 6.065% 0.217% 1.300% 0.433% 1.083% 1.300% 1.083% 0.650%

7 Water stop PVC Lebar 25 cm e Estopper atau Setara m1 45.60 0.513% 0.257% 0.128% 0.128%

8 Beton K - 350 m3 139.87 5.944% 1.717% 0.264% 1.717% 0.264% 1.585% 0.396%

9 Besi D 10 - 150 kg 130.73 0.078% 0.029% 0.049%

10 Besi D 13 - 150 kg 3023.44 1.810% 0.217% 0.434% 0.145% 0.434% 0.362% 0.217%

11 Besi D 16 - 100 kg 4921.25 2.946% 0.184% 0.644% 0.644% 0.644% 0.644% 0.184%

12 Besi D 19 - 100 kg 11558.84 6.919% 1.339% 1.562% 1.562% 1.562% 0.893%

13 Surface Protection setara Araldite tebal 300 mikron ( luar, dalam ) m2 488.23 5.533% 2.075% 2.421% 1.037%

(ex.Delta floor TC301SF)

Sub Total B 34.766%

C Pekerjaan Pemipaan + Aksesoris

1 Pipa Galvanise f 400 + Pengecatan m1 35.14 5.254% 0.233% 0.817% 0.700% 0.817% 0.817% 0.817% 0.700% 0.350%

2 Butterfly Valve f 400 ( Kitz 10 K) bh 6.00 6.752% 0.844% 1.266% 0.844% 0.844% 1.266% 0.844% 0.844%

3 Pipa Galvanise f 350 + Pengecatan m 1


130.97 16.697% 0.278% 1.670% 1.948% 1.948% 1.670% 1.948% 1.948% 1.948% 1.670% 1.670%

4 Butterfly Valve f 350 ( Kitz 10 K ) bh 10.00 9.208% 0.921% 0.921% 1.381% 1.842% 0.921% 0.921% 0.921% 1.381%

5 Tiang Support ( Baja ) 8 titik ls 1.00 3.110% 1.037% 1.037% 1.037%

6 Tangga baja ( H 4 m ) ls 1.00 0.197% 0.039% 0.118% 0.039%

Sub Total C 41.217%

D Pekerjaan Lain - lain

1 Tee Equal f 400 + Pengecatan bh 6.00 3.015% 0.603% 0.905% 0.603% 0.905%

2 Tee Equal f 350 + Pengecatan bh 6.00 2.302% 0.691% 0.460% 0.691% 0.460%

3 Elbow 900 f 400 + Pengecatan bh 6.00 2.205% 0.441% 0.882% 0.882%

4 Elbow 900 f 350 + Pengecatan bh 6.00 1.927% 0.385% 0.193% 1.156% 0.193%

5 Flange SO 10 K f 400 + Pengecatan bh 12.00 2.899% 0.870% 0.580% 0.580% 0.580% 0.290%

6 Flange SO 10 K f 350 + Pengecatan bh 12.00 2.585% 0.776% 0.517% 1.293%

7 Relokasi PJU & Pompa + Aksesoris ls 1.00 1.023% 0.146% 0.438% 0.438%

Sub Total D 15.957%

Day

1.610% 1.597% 1.247% 1.852% 3.495% 3.713% 2.928% 3.320% 2.940% 2.654% 2.207% 2.154% 3.637% 5.449% 7.862% 10.542% 12.609% 9.961% 9.163% 6.079% 4.391% 0.053% 0.187% 0.077% 0.226% 0.046%
100%
TOTAL A + B + C + D 1.610% 3.207% 4.454% 6.306% 9.801% 13.514% 16.442% 19.762% 22.703% 25.357% 27.563% 29.717% 33.354% 38.803% 46.665% 57.207% 69.816% 79.777% 88.939% 95.019% 99.410% 99.463% 99.650% 99.728% 99.954% 100.000%

PT . SURYACIPTA SWADAYA PT . SARANA ABADI JAYA RAYA


Note:
- Pekerjaan Dimulai pada tanggal 11 Desember 2020 s.d 9 Juni 2021 (Sesuai Kontrak)

Surya Mardani Arjuna Indra Sawlani


Construction Manager Project Manager
PEMBANGUNAN CLARIFIER IWTP PHASE-1
PT. SURYACIPTA SWADAYA
KARAWANG

NO URAIAN PEKERJAAN
A Pekerjaan Persiapan
1 Mobilisasi dan Demobilisasi (Tenaga,alat kerja dan Material
2 Keamanan Lapangan
3 Direksi keet + Listrik, Air kerja
4 Shop & As Built Drawing
5 Laporan progres dan Foto dokumentasi
6 C.A.R ( include 3 person owner )
7 Tes kebocoran / Tes Rendam
8 Tes tarik besi beton / Tes tekan Mutu beton
9 Pengukuran / bouwplank
10 Proteksi lokasi kerja
11 Safety / HSE
12 Pembersihan Lokasi
13 Soil test /Sondir

B Pekerjaan Clarifier
1 Bor Pile f40 cm , L = 15 m ( k350)
2 Bobok borplie f40 cm
3 Galian tanah & Buang Disposal ( jarak 2 km )
4 Lean Concrete t=5cm K175
5 Compacted Sand = 10 cm
6 Bekisting (EXPOSE)
7 Water stop PVC lebar 25 cm ex Estoper atau setara
8 Beton K-350
9 Besi D 10-150
10 Besi D 13-150
11 Besi D 16-100
12 Besi D 19-100
13 Surface Porotection setara Araldite tebal 300 mikron (luar,dalam)
(ex Delta floor TC301SF)

C Pekerjaan Pemipaan dan Aksesoris


1 Pipa Galvanise f400+Pengecatan
2 Buterfly Valve f400 (kit2 10K)
3 Pipa Galvanise f350+ pengecatan
4 Buterfly Valve f350 (kit2 10K)
5 Tiang Suport (Baja) 8 titik
6 Tangga baja ( H 4 m)
D Pekerjaan Lain-lain
1 Tee Equal f400+pengecatan
2 Tee Equal f350+pengecatan
3 Elbow 90' f400 + pengecatan
4 Elbow 90' f350 + pengecatan
5 Flange SO 10 K f400 + pengecatan
6 Flange SO 10 K f350 + pengecatan
7 Relokasi PJU & pompa + aksesoris
ANGUNAN CLARIFIER IWTP PHASE-1
PT. SURYACIPTA SWADAYA
KARAWANG

SATUAN VOLUME HARGA SATUAN (RP) JUMLAH HARGA (RP) BOBOT

ls 1.00 12,090,000 12,090,000 0.56%


ls 1.00 9,000,000 9,000,000 0.41%
ls 1.00 34,486,995 34,486,995 1.59%
ls 1.00 8,964,500 8,964,500 0.41%
ls 1.00 5,127,500 5,127,500 0.24%
ls 1.00 17,091,500 17,091,500 0.79%
ls 1.00 7,178,500 7,178,500 0.33%
ls 1.00 9,280,500 9,280,500 0.43%
ls 1.00 6,836,750 6,836,750 0.31%
ls 1.00 8,964,000 8,964,000 0.41%
ls 1.00 10,800,000 10,800,000 0.50%
ls 1.00 5,225,000 5,225,000 0.24%
Ttk 2.00 20,000,000 40,000,000 1.84%
Sub Total A 175,045,245 8.06%

nos 9.00 8,169,950 73,529,550 3.39%


nos 9.00 262,200 2,359,800 0.11%
m3 76.50 314,800 24,082,200 1.11%
m3 5.10 799,900 4,079,490 0.19%
m3 10.20 355,500 3,626,100 0.17%
m2 394.43 333,975 131,729,759 6.07%
m1 45.60 244,425 11,145,780 0.51%
m3 139.87 922,965 129,095,115 5.94%
kg 130.73 13,000 1,699,490 0.08%
kg 3023.44 13,000 39,304,720 1.81%
kg 4921.25 13,000 63,976,250 2.95%
kg 11558.84 13,000 150,264,920 6.92%
m2 488.23 246,125 120,165,609 5.53%

Sub Total B 755,058,783 34.77%

m1 35.14 3,247,000 114,099,580 5.25%


bh 6.00 24,438,500 146,631,000 6.75%
m1 130.97 2,768,850 362,636,285 16.70%
bh 10.00 19,997,500 199,975,000 9.21%
ls 1.00 67,547,000 67,547,000 3.11%
ls 1.00 4,272,975 4,272,975 0.20%
Sub Total C 895,161,840 41.22%
bh 6.00 10,914,875 65,489,250 3.02%
bh 6.00 8,334,000 50,004,000 2.30%
bh 6.00 7,981,900 47,891,400 2.21%
bh 6.00 6,973,500 41,841,000 1.93%
bh 12.00 5,247,200 62,966,400 2.90%
bh 12.00 4,678,750 56,145,000 2.59%
ls 1.00 22,219,450 22,219,450 1.02%
Sub Total D 346,556,500 15.96%
100.00%
TOTAL A + B + C + D 2,171,822,367
PPN 10% 217,182,237
GRAND TOTAL 2,389,004,604
PEMBULATAN 2,389,000,000
RINGKASAN LAPORAN MINGGUAN
Pekerjaan Pembangunan Clarifier IWTP Phase-I, Kota Industri Suryacipta
DESEMBER
PROGRESS RENCANA PROGRESS REALISASI SELISIH PROGRESS

STATUS LAPORAN WAKTU PELAKSANAAN BOBOT

DATA PROGRESS SAMPAI MINGGU LALU


NO URAIAN PEKERJAAN S/D S/D S/D KET
(%) S/D MINGGU
MINGGU INI MINGGU
S/D MINGGU MINGGU
MINGGU
S/D MINGGU
MINGGU INI MINGGU
LALU LALU INI LALU
INI INI INI

90
A. PEKERJAAN PERSIAPAN
MINGGU KE : 1 hari kalender 1 Mobilisasi dan Demobilisasi (Tenaga,alat kerja dan Material 0.56% 0.000% 0.000% 0.000% 0.000% 0.010% 0.010% 0.000% 0.010% 0.010%

TGL DIBUAT 18-Dec-20 2 Keamanan Lapangan 0.41% 0.000% 0.069% 0.069% 0.000% 0.069% 0.069% 0.000% 0.000% 0.000%

TERPAKAI SISA 3

4
Direksi keet + Listrik, Air kerja

Shop & As Built Drawing


1.59%

0.41%
0.000%

0.000%
0.265%

0.103%
0.265%

0.103%
0.000%

0.000%
0.265%

0.050%
0.265%

0.050%
0.000%

0.000%
0.000%

-0.053%
0.000%

-0.053%
RENCANA MINGGU LALU (%) : 0.00%
PERIODE
DARI SAMPAI (hari) (%) (hari) (%) 5

6
Laporan progres dan Foto dokumentasi

C.A.R ( include 3 person owner )


0.24%

0.79%
0.000%

0.000%
0.020%

0.047%
0.020%

0.047%
0.000%

0.000%
0.020%

0.000%
0.020%

0.000%
0.000%

0.000%
0.000%

-0.047%
0.000%

-0.047%

11-Dec-20 18-Dec-20
7 Tes kebocoran / Tes Rendam 0.33% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% REALISASI MINGGU LALU (%) : 0.00%
8 8.889 82 91.111 8 Tes tarik besi beton / Tes tekan Mutu beton 0.43% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

9 Pengukuran / bouwplank 0.31% 0.000% 0.079% 0.079% 0.000% 0.079% 0.079% 0.000% 0.000% 0.000%

10 Proteksi lokasi kerja 0.41% 0.000% 0.025% 0.025% 0.000% 0.025% 0.025% 0.000% 0.000% 0.000%

DATA PROYEK 11 Safety / HSE 0.50% 0.000% 0.030% 0.030% 0.000% 0.030% 0.030% 0.000% 0.000% 0.000% SELISIH MINGGU LALU (%) : 0.00%
12 Pembersihan Lokasi 0.24% 0.000% 0.052% 0.052% 0.000% 0.052% 0.052% 0.000% 0.000% 0.000%

PROPINSI : JAWA BARAT 13 Soil test /Sondir 1.84% 0.000% 0.921% 0.921% 0.000% 0.921% 0.921% 0.000% 0.000% 0.000%

PROJECT : Pekerjaan Pembangunan Clarifier IWT Phase-I B. PEKERJAAN CLARIFIER

Kota Industri Suryacipta


1

2
Bor Pile f40 c m , L = 15 m ( k350)

Bobok borplie f40 cm


3.39%

0.11%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000% DATA PROGRESS PENCAPAIAN MINGGU INI


3 Galian tanah & Buang Disposal ( jarak 2 km ) 1.11% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
NAMA BANGUNAN : Bangunan Clarifier IWTP 4 Lean Concrete t=5cm K175 0.19% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

RENCANA MINGGU INI (%) : 1.61%


5 Compacted Sand = 10 cm 0.17% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
CONSTR. MANAGER : SURYA MARDANI 6 Bekisting (EXPOSE) 6.07% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

7 W ater stop PVC lebar 25 cm ex Estoper atau setara 0.51% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
SUPERVISOR : NOVRIANTO SYAFRUDIN 8 Beton K-350 5.94% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

REALISASI MINGGU INI (%) : 1.52%


9 Besi D 10-150 0.08% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
: -- 10 Besi D 13-150 1.81% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

11 Besi D 16-100 2.95% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
INSPECTOR : AGUS SURYANTO 12 Besi D 19-100 6.92% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

SELISIH MINGGU INI (%) : -0.09%


13 Surface Porotection setara Araldite tebal 300 mikron (luar,dalam) 5.53% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
DATA KONTRAKTOR
NAMA KONTRAKTOR : PT. SARANA ABADI JAYA RAYA C. PEKERJAAN PEMIPAAN & AKSESORIS
1 Pipa Galvanise f400+Pengecatan 5.25% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
PROJECT MANAGER : ARJUNA INDRA SAWLANI 2 Buterfly Valve f400 (kit2 10K) 6.75% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

DATA PROGRESS SAMPAI DGN MINGGU INI


3 Pipa Galvanise f350+ pengecatan 16.70% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
ALAMAT KANTOR : Jl. Raya Galuh Mas, Ruko Casabella No. 3-5, Ds. Sukaharja
4 Buterfly Valve f350 (kit2 10K) 9.21% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
Kec. Teluk Jambe, Kab. Karawang, Jawa Barat 5 Tiang Suport (Baja) 8 titik 3.11% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

6 Tangga baja ( H 4 m) 0.20% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
TGL & NO KONTRAK : 4 Desember 2020 - 010/SCS-EDM/SPP/XII/2020

TGL & NO SPMK : 04 Desember 2020 - 004/SCS-EDM/SPMK/XII/2020 D. PEKERJAAN LAIN-LAIN RENCANA S/D MINGGU INI (%) : 1.61%
1 Tee Equal f400+pengecatan 3.02% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
NILAI KONTRAK : Rp 2,389,000,000.00
2 Tee Equal f350+pengecatan 2.30% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

MASA PELAKSANAAN : 90 (Sembilan Puluh) Hari Kalender 3 Elbow 90' f400 + pengecatan 2.21% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

TGL MULAI : 18-Dec-20


4

5
Elbow 90' f350 + pengecatan

Flange SO 10 K f400 + pengecatan


1.93%

2.90%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
0.000%

0.000%
REALISASI S/D MINGGU INI (%) : 1.52%
6 Flange SO 10 K f350 + pengecatan 2.59% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
TGL BERAKHIR : 18-Mar-21
7 Relokasi PJU & pompa + aksesoris 1.02% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

NILAI WAKTU SELISIH S/D MINGGU INI (%) : -0.09%


NO JENIS KONTRAK CATATAN PERUBAHAN KONTRAK T OT AL (%) = 100% 0.000% 1.610% 1.610% 0.000% 1.521% 1.521% 0.000% -0.089% -0.089%
KONTRAK PELAKSANAAN

1 Original 2,389,000,000.00 180 Hari ----


MONITORING STATUS PENYERAPAN KEUANGAN
Pekerjaan sampai Saat Ini Pekerjaan Uang Muka Jaminan Pemeliharaan Hasil Bersih Saat Ini Pajak Pertambahan Nilai Total Pembayaran Keterangan
TOTAL ( Rupiah ) TOTAL ( Rupiah ) TOTAL ( Rupiah ) TOTAL ( Rupiah ) TOTAL ( Rupiah ) TOTAL ( Rupiah ) KEUANG
No Deskripsi FISIK
Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini AN
3
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) % %
4 1 UANG MUKA (10%) - - - - - - - - 1,386,000,000 1,386,000,000 10% 6.04%

Dibuat Oleh :
NO PERMASALAHAN PROYEK USULAN SOLUSINYA KETERANGAN

1 Gambar desain tidak sesuai dengan kondisi aktual lapangan Melakukan inventarisir dan steakout aktual kondisi lapangan
Novrianto Syafrudin
Supervisor

Diperiksa Oleh : Diketahui Oleh :

Surya Mardani Didi Wihardi


Construction Manager
MONITORING STATUS PENYERAPAN KEUANGAN
Pekerjaan sampai Saat Ini Pekerjaan Uang Muka Jaminan Pemeliharaan Hasil Bersih Saat Ini Pajak Pertambahan Nilai Total Pembayaran Keterangan
TOTAL ( Rupiah ) TOTAL ( Rupiah ) TOTAL ( Rupiah ) TOTAL ( Rupiah ) TOTAL ( Rupiah ) TOTAL ( Rupiah ) KEUANG
No Deskripsi FISIK
Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini Saat Ini Sampai Saat Ini AN

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) % %
1 UANG MUKA (10%) - - - - - - - - 1,386,000,000 1,386,000,000 10% 6.04%
WAKTU
NO JENIS KONTRAK NILAI KONTRAK CATATAN PERUBAHAN KONTRAK
PELAKSANAAN

1 Original 2,389,000,000.00 180 Hari ----

7
88

PERIODE
STATUS LAPORAN
DARI SAMPAI
MINGGU KE : 1
11-Dec-20 18-Dec-20
TGL DIBUAT 18-Dec-20
PROGRESS RENCANA PROGRESS REALISASI SELISIH PROGRESS
BOBOT
NO URAIAN PEKERJAAN S/D S/D S/D KET
(%) S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
MINGGU INI MINGGU MINGGU MINGGU INI MINGGU
LALU LALU INI LALU
INI INI INI

A. PEKERJAAN PERSIAPAN

1 Mobilisasi dan Demobilisasi (Tenaga,alat kerja dan Material 0.56% 0.000% 0.000% 0.000% 0.000% 0.010% 0.010% 0.000% 0.010% 0.010%

2 Keamanan Lapangan 0.41% 0.000% 0.069% 0.069% 0.000% 0.069% 0.069% 0.000% 0.000% 0.000%

3 Direksi keet + Listrik, Air kerja 1.59% 0.000% 0.265% 0.265% 0.000% 0.265% 0.265% 0.000% 0.000% 0.000%

4 Shop & As Built Drawing 0.41% 0.000% 0.103% 0.103% 0.000% 0.050% 0.050% 0.000% -0.053% -0.053%

5 Laporan progres dan Foto dokumentasi 0.24% 0.000% 0.020% 0.020% 0.000% 0.020% 0.020% 0.000% 0.000% 0.000%

6 C.A.R ( include 3 person owner ) 0.79% 0.000% 0.047% 0.047% 0.000% 0.000% 0.000% 0.000% -0.047% -0.047%

7 Tes kebocoran / Tes Rendam 0.33% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

8 Tes tarik besi beton / Tes tekan Mutu beton 0.43% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

9 Pengukuran / bouwplank 0.31% 0.000% 0.079% 0.079% 0.000% 0.079% 0.079% 0.000% 0.000% 0.000%

10 Proteksi lokasi kerja 0.41% 0.000% 0.025% 0.025% 0.000% 0.025% 0.025% 0.000% 0.000% 0.000%

11 Safety / HSE 0.50% 0.000% 0.030% 0.030% 0.000% 0.030% 0.030% 0.000% 0.000% 0.000%

12 Pembersihan Lokasi 0.24% 0.000% 0.052% 0.052% 0.000% 0.052% 0.052% 0.000% 0.000% 0.000%

13 Soil test /Sondir 1.84% 0.000% 0.921% 0.921% 0.000% 0.921% 0.921% 0.000% 0.000% 0.000%

B. PEKERJAAN CLARIFIER

1 Bor Pile f40 cm , L = 15 m ( k350) 3.39% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

2 Bobok borplie f40 cm 0.11% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

3 Galian tanah & Buang Disposal ( jarak 2 km ) 1.11% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

4 Lean Concrete t=5cm K175 0.19% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

5 Compacted Sand = 10 cm 0.17% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

6 Bekisting (EXPOSE) 6.07% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

7 Water stop PVC lebar 25 cm ex Estoper atau setara 0.51% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

8 Beton K-350 5.94% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

9 Besi D 10-150 0.08% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

10 Besi D 13-150 1.81% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

11 Besi D 16-100 2.95% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

12 Besi D 19-100 6.92% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

13 Surface Porotection setara Araldite tebal 300 mikron (luar,dalam) 5.53% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

C. PEKERJAAN PEMIPAAN & AKSESORIS


1 Pipa Galvanise f400+Pengecatan 5.25% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

2 Buterfly Valve f400 (kit2 10K) 6.75% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

3 Pipa Galvanise f350+ pengecatan 16.70% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
4 Buterfly Valve f350 (kit2 10K) 9.21% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

5 Tiang Suport (Baja) 8 titik 3.11% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

6 Tangga baja ( H 4 m) 0.20% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

D. PEKERJAAN LAIN-LAIN

1 Tee Equal f400+pengecatan 3.02% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

2 Tee Equal f350+pengecatan 2.30% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

3 Elbow 90' f400 + pengecatan 2.21% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

4 Elbow 90' f350 + pengecatan 1.93% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

5 Flange SO 10 K f400 + pengecatan 2.90% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

6 Flange SO 10 K f350 + pengecatan 2.59% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

7 Relokasi PJU & pompa + aksesoris 1.02% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

TOTAL (%) = 100% 0.000% 1.610% 1.610% 0.000% 1.521% 1.521% 0.000% -0.089% -0.089%
DATA PROYEK
PROPINSI : JAWA BARAT

PROJECT : Pekerjaan Pembangunan Clarifier IWT Phase-I

Kota Industri Suryacipta

NAMA BANGUNAN : Bangunan Clarifier IWTP

CONSTR. MANAGER : SURYA MARDANI

SUPERVISOR : NOVRIANTO SYAFRUDIN

: --

INSPECTOR : AGUS SURYANTO

DATA KONTRAKTOR
NAMA KONTRAKTOR : PT. SARANA ABADI JAYA RAYA

PROJECT MANAGER : ARJUNA INDRA SAWLANI

ALAMAT KANTOR : Jl. Raya Galuh Mas, Ruko Casabella No. 3-5, Ds. Sukaharja

Kec. Teluk Jambe, Kab. Karawang, Jawa Barat

TGL & NO KONTRAK : 4 Desember 2020 - 010/SCS-EDM/SPP/XII/2020

TGL & NO SPMK : 04 Desember 2020 - 004/SCS-EDM/SPMK/XII/2020

NILAI KONTRAK : Rp 2,389,000,000.00

MASA PELAKSANAAN : 90 (Sembilan Puluh) Hari Kalender

TGL MULAI : 18-Dec-20

TGL BERAKHIR : 18-Mar-21


PERMASALAHAN PROYEK & USULAN SOLUS

NO PERMASALAHAN PROYEK

1 Gambar desain tidak sesuai dengan kondisi aktual lapangan


AHAN PROYEK & USULAN SOLUSINYA

USULAN SOLUSINYA KETERANGAN

Melakukan inventarisir dan steakout aktual kondisi lapangan


12/10/2020
12/18/2020
WAKTU PELAKSANAAN

90 hari kalender

TERPAKAI SISA

(hari) (%) (hari) (%)

8 8.889 82 91.111
LAPORAN HARIAN
PEKERJAAN PEMBANGUNAN CLARIFIER IWTP PHASE-1

Kontraktor : PT. Sarana Abadi Jaya Raya


Masa Kerja : 90 Hari Calender

No Tanggal Uraian Pekerjaan Keterangan

1 11/12/2020 Serah Terima Lahan Pekerjaan


( lampiran BAST )
2 12/12/2020 Serah Terima BM, 2 titik BM
( lampiran BAST )
3 15/12/2020 1. Kontainer untuk site office & gudang onsite
2. Pembongkaran tiang PJU existing
3. Pasang patok bowplank
4. Pembersihan Area Kerja

4 16/12/2020 1. Matrial Besi Onsite : Master Steel


- Besi dia. 19"
- Besi dia. 16"
- Besi dia. 13"
- Besi dia. 10"
2. Penyambungan Listrik Kerja (BAST on proses)
3. Penyambungan Air Kerja (BAST on proses)
4. Test Pit untuk titik sondir

5 17/12/2020 1. Test Pit (1x1x1)


2. Persiapan Sondir 2 Titik