NO.

KONTRAK :
CIVIL SP3MK-
005/PG3400/2022-S7

NOMOR DOKUMEN: 4 Halaman


SNBP-EPC-00-CIV-MTO-001

JASA PERANCANGAN, PENGADAAN DAN KONSTRUKSI (EPC)


PEMBANGUNAN PIPA GAS SENIPAH-BALIKPAPAN

CIVIL – MATERIAL TAKE OFF

TRI 25/11/22

AK 25/11/22

A 25/11/2022 Issued for Information ISN ASW EFC

DISIAPKAN DIPERIKSA DISETUJUI DISETUJUI


REV TANGGAL TUJUAN
PT PGAS SOLUTION PT PERTAMINA GAS
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 1 of 14

REVISION TABLE

REVISION CODE REVISION CODE REVISION CODE


Page Page Attachment
A B C 0 1 2 3 A B C 0 1 2 3 A B C 0 1 2 3

1
2
3
4
5
6
7
8
9
10
11
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 2 of 14

RECORD OF REVISION

Rev. Implemented
Page Client Comment Explanation
Code (Y/N)
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 3 of 14

TABLE OF CONTENT

1 INTRODUCTION .................................................................................................................................... 4
1.1 Project Overview ........................................................................................................................ 4
1.2 Scope .......................................................................................................................................... 4
2 DEFINITION ........................................................................................................................................... 5
3 CONFLICTING REQUIREMENT ........................................................................................................... 5
4 CODES, STANDARD, AND REFERENCES ......................................................................................... 5
5 MTO CIVIL AND STRUCTURES ........................................................................................................... 7
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 4 of 14

1 INTRODUCTION

1.1 Project Overview

PT Pertamina Gas (Pertagas) plans to deliver gas from Senipah KP 7.2 (tap off from 42”
pipeline) that is operated by Pertamina Hulu Mahakan to PT Pertamina (Persero) Refinery Unit
(RU) V Balikpapan, East Kalimantan, to fulfill the gas demand at Refinery Unit (RU) V
Balikpapan as part of the RDMP program.
The Onshore Pipeline Senipah – RU V Balikpapan scope will comprise of development of mini
facility in Senipah and RU V Balikpapan area consist of gas metering, pigging facilities, utilities
and an onshore gas pipeline.

Figure 1-1 Pipeline Route from Senipah to Refinery Unit (RU) V Balikpapan

1.2 Scope

This document is intended to present the Material Take Off of project Jasa Perancangan,
Pengadaan, dan Konstruksi Pembangunan Pipa Gas Senipah – Balikpapan.
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 5 of 14

2 DEFINITION

PROJECT : Jasa Perancangan, Pengadaan, dan Konstruksi


Pembangunan Pipa Gas Senipah – Balikpapan.
COMPANY : PT Pertamina Gas (Pertagas) as the owner of the Project
CONTRACTOR : PT PGAS Solution
VENDOR : The party which supply materials, equipment, technical
document/drawing, and service to perform the duties by
the CONTRACTOR.
MANUFACTURER : Party which manufactures equipment/materials specified
and ordered by CONTRACTOR (or COMPANY).
MIGAS : Direktorat Jendral Minyak dan Gas Bumi
Purchaser : Persons responsible for procurement of equipment,
materials and or services

3 CONFLICTING REQUIREMENT

In the event of conflict, inconsistency, or ambiguity between Data sheets, drawings, this
procedure, standards, codes, and regulations referenced herein, or other documents, the
VENDOR or CONTRACTOR shall refer to COMPANY, whose decision shall prevail. In
principle, the requirements of the most stringent document shall apply.

4 CODES, STANDARD, AND REFERENCES

The following documents shall be complied with, unless stated otherwise in this Standard
specification. The latest editions and revisions of each Code and/or specification, as of the
Contract Document date, shall apply, unless otherwise specifically noted on the Contract
Documents or approved, in writing, by the Company.
1. ASME B16.5 Standard specification for Pipe Flanges and Flanged Fittings:
covers pressure-temperature ratings, materials, dimensions
2. ASME B36.10 Standard specification for welded and seamless wrought steel
pipes which are used for high or low temperatures and
pressures.
3. ASTM A105 Standards for forged carbon steel piping components, that is,
flanges, fittings, valves, and similar parts, for use in pressure
systems at ambient and higher-temperature service conditions
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 6 of 14

4. ASTM A193 Standard covers alloy steel and stainless steel bolting materials
for high temperature or high-pressure service. This
specification includes fasteners intended for use in pressure
vessels, valves, flanges, and fittings.
5. References Document
SNBP-EPC-00-CIV-DRW-002 LBCV House Foundation Plan, Structure Detail & Section
.
SNBP-EPC-00-CIV-DRW-010 Typical Drawing for Retaining Wall/ Slope Protection
SNBP-EPC-10-CIV-DRW-006 Senipah Gas Metering Package Foundation Plan And Section
SNBP-EPC-10-CIV-DRW-007 Senipah Pig Launcher Foundation Plan And Section
SNBP-EPC-10-CIV-DRW-008 Senipah Air Compressor & Air Dryer Package Foundation Plan
And Section
SNBP-EPC-10-CIV-DRW-009 Diesel Storage Foundation Plan And Section
SNBP-EPC-10-CIV-DRW-010 Metering Control Foundation Plan And Section
SNBP-EPC-10-CIV-DRW-012 Security Gate House Foundation Plan And Section
SNBP-EPC-10-CIV-DRW-014 Emergency Diesel Generator Foundation Plan And Section
SNBP-EPC-10-CIV-DRW-016 Gas Metering Shelter Foundation Plan And Section
SNBP-EPC-10-CIV-DRW-027 Lighting Protection Foundation Plan And Section
SNBP-EPC-10-CIV-DRW-031 Windsock & Flag Pole Foundation Plan And Section
SNBP EPC 10 CIV DRW 036 Co2 Snuffing Package Foundation Plan And Section
- - - - -

SNBP-EPC- 10-CIV-DRW -038 Miscellaneous Foundation Plan And Section


SNBP-EPC- 10-CIV-DRW -040 Corrosion Inhibitor Tank Foundation Plan And Section
SNBP-EPC- 10-CIV-DRW -044 Area Vent K.O Foundation Plan And Section
SNBP-EPC- 10-CIV-DRW -046 Transformer Foundation Foundation Plan And Section
SNBP-EPC- 10-CIV-DRW -053 Temporary Bridge Structure
SNBP-EPC- 20-CIV-DRW -007 Gas Metering Package Foundation Plan And Section
SNBP-EPC- 20-CIV-DRW -008 Gas Metering Shelter Foundation Plan And Section
SNBP-EPC- 20-CIV-DRW -009 Pig Receiver Foundation Plan And Section
SNBP-EPC- 20-CIV-DRW -010 Gas Receiver Foundation Plan And Section
NBP-EPC-20 -CIV-DRW-013 Metering Control Room Foundation Plan And Section
SNBP-EPC- 20-CIV-DRW-018 Air Compressor & Air Dryer Foundation Plan And Section
SNBP-EPC-20-CIV-DRW-020 Diesel Storage Foundation Plan And Section
SNBP-EPC-20-CIV-DRW-026 Lighting Protection Foundation Plan And Section
SNBP-EPC-20-CIV-DRW-027 Lighting Pole Foundation Plan And Section
SNBP-EPC-20-CIV-DRW-030 Wind Shock & Flag Pole Foundation Plan And Section
SNBP-EPC-20-CIV-DRW-033 Fire Water System Foundation
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 7 of 14

SNBP-EPC-20-CIV-DRW-035 Miscellaneous Drawing


SNBP-EPC-20-CIV-DRW-039 Ru V Balikpapan - Vent K.O Pot Foundation
SNBP-EPC-20-CIV-DRW-040 Ru V Balikpapan Transformer Foundation
SNBP-EPC-20-CIV-DRW-042 Ru V Balikpapan Gas Filter Foundation Plan & Section

5 MTO CIVIL AND STRUCTURES

No. DESCRIPTION UNIT VOLUME


1 SNBP-EPC-00-CIV-DRW-010 Typical Drawing for Retaining Wall/ Slope Protection
Footing
Concrete m3 0,6
Reinforcement Bar kg 65,1
Wall
Concrete m3 1,3
Formwork m 2
20
Reinforcement Bar kg 145,32
SNBP-EPC-10-CIV-DRW-006 SENIPAH GAS METERING PACKAGE FOUNDATION
2
PLAN AND SECTION
Slab
Concrete m3 60
Reinforcement Bar kg 44631,11
Formwork m 2
30
Leanconcrete m 2 5,25
SNBP-EPC-10-CIV-DRW-007 SENIPAH PIG LAUNCHER FOUNDATION PLAN AND
3
SECTION
Footing
Concrete m3 3,15
Reinforcement Bar kg 316,3
Formwork m 2
7,8
Pedestal
Concrete m3 1,24
Reinforcement Bar kg 94,08
Formwork m2 4,92
Tie Beam
Concrete m3 0,65
Reinforcement Bar kg 51,63
Formwork m 2 4,86
SNBP-EPC-10-CIV-DRW-008 SENIPAH AIR COMPRESSOR & AIR DRYER PACKAGE
4
FOUNDATION PLAN AND SECTION
Slab
Concrete m3 8,89
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 8 of 14

Reinforcement Bar kg 630,28


Formwork m 2
9,96
Leanconcrete m 2
0,83
5 SNBP-EPC-10-CIV-DRW-009 DIESEL STORAGE FOUNDATION PLAN AND SECTION
Slab
Concrete m3 6,3
Reinforcement Bar kg 292,48
Formwork m2 10,2
Leanconcrete m 2
0,61
Pedestal
Concrete m3 0,54
Reinforcement Bar kg 124,83
Formwork m2 10,8
SNBP-EPC-10-CIV-DRW-010 METERING CONTROL FOUNDATION PLAN AND
6
SECTION
Footing F1
Concrete m3 28,8
Reinforcement Bar kg 2626,42
Formwork m 2
57,6
Pedestal F1
Concrete m3 1,43
Reinforcement Bar kg 306,54
Formwork m 2
16,38
Footing F2
Concrete m3 3,75
Reinforcement Bar kg 301,25
Formwork m 2 6
SNBP-EPC-10-CIV-DRW-012 SECURITY GATE HOUSE FOUNDATION PLAN AND
7
SECTION
Footing
Concrete m3 3,89
Reinforcement Bar kg 497,84
Formwork m 2
8,64
Pedestal
Concrete m3 0,12
Reinforcement Bar kg 16,88
Formwork m 2 2,24
SNBP-EPC-10-CIV-DRW-014 EMERGENCY DIESEL GENERATOR FOUNDATION PLAN
8
AND SECTION
Slab
Concrete m3 8
Reinforcement Bar kg 480,51
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 9 of 14

Formwork m2 11,2
SNBP-EPC-10-CIV-DRW-016 GAS METERING SHELTER FOUNDATION PLAN AND
9
SECTION
Footing
Concrete m3 5,76
Reinforcement Bar kg 869,61
Formwork m 2
19,2
Pedestal
Concrete m3 2,6
Reinforcement Bar kg 571,2
Formwork m 2
23
Tiebeam Arah X
Concrete m3 3,84
Reinforcement Bar kg 389,68
Formwork m 2
35,2
Tiebeam Arah Y
Concrete m3 1,4
Reinforcement Bar kg 137,1
Formwork m 2
12,76
SNBP-EPC-10-CIV-DRW-027 LIGHTING PROTECTION FOUNDATION PLAN AND
10
SECTION
Footing
Concrete m3 0,68
Reinforcement Bar kg 78,77
Formwork m 2
1,8
Pedestal
Concrete m3 0,38
Reinforcement Bar kg 55,09
Formwork m 2 3
SNBP-EPC-10-CIV-DRW-031 WINDSOCK & FLAG POLE FOUNDATION PLAN AND
11
SECTION
Footing
Concrete m3 0,3
Reinforcement Bar kg 40,55
Formwork m 2 1,2
Pedestal
Concrete m3 0,16
Reinforcement Bar kg 32,27
Formwork m 2 1,8
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 10 of 14

SNBP-EPC-10-CIV-DRW-036 CO2 SNUFFING PACKAGE FOUNDATION PLAN AND


12
SECTION
Slab
Concrete m3 2,62
Reinforcement Bar kg 149,36
Formwork m 2 5,16
13 SNBP-EPC-10-CIV-DRW-038 MISCELLANEOUS FOUNDATION PLAN AND SECTION
Slab
Concrete m3 0,24
Reinforcement Bar kg 27,72
Formwork m 2 1,68
SNBP-EPC-10-CIV-DRW-040 CORROSION INHIBITOR TANK FOUNDATION PLAN AND
14
SECTION
Slab
Concrete m3 8,06
Reinforcement Bar kg 543,61
Formwork m 2
8,88
15 SNBP-EPC-10-CIV-DRW-044 AREA VENT K.O FOUNDATION PLAN AND SECTION
Footing
Concrete m3 3,75
Reinforcement Bar kg 272,49
Formwork m 2
6
Pedestal
Concrete m3 3,97
Reinforcement Bar kg 180,92
Formwork m2 8,36
SNBP-EPC-10-CIV-DRW-046 TRANSFORMER FOUNDATION FOUNDATION PLAN AND
16
SECTION
Slab
Concrete m3 1,35
Reinforcement Bar kg 115,15
Formwork m2 3,6
17 SNBP-EPC-10-CIV-DRW-053 TEMPORARY BRIDGE STRUCTURE
Footing
Concrete m3 2,5
Reinforcement Bar kg 83,15
Formwork m 2 4
SNBP-EPC-20-CIV-DRW-007 GAS METERING PACKAGE FOUNDATION PLAN AND
18
SECTION
Slab
Concrete m3 75
Reinforcement Bar kg 3608,2
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 11 of 14

Formwork m2 37,5
SNBP-EPC-20-CIV-DRW-008 GAS METERING SHELTER FOUNDATION PLAN AND
19
SECTION
Footing
Concrete m3 6
Reinforcement Bar kg 744,61
Formwork m 2
24
Pedestal
Concrete m3 3,4
Reinforcement Bar kg 577,9
Formwork m 2
26,8
Tiebeam Arah X
Concrete m3 4,32
Reinforcement Bar kg 431,84
Formwork m 2
39,6
Tiebeam Arah Y
Concrete m3 1,44
Reinforcement Bar kg 139,6
Formwork m 2
13,2
20 SNBP-EPC-20-CIV-DRW-009 PIG RECEIVER FOUNDATION PLAN AND SECTION
Footing
Concrete m3 1,8
Reinforcement Bar kg 247,59
Formwork m 2
6
Pedestal
Concrete m3 0,24
Reinforcement Bar kg 46,4
Formwork m2 2,56
Tiebeam
Concrete m3 1,81
Reinforcement Bar kg 132,16
Formwork m 2 12,08
21 SNBP-EPC-20-CIV-DRW-010 GAS RECEIVER FOUNDATION PLAN AND SECTION
Footing
Concrete m3 4,05
Reinforcement Bar kg 274,37
Formwork m2 5,4
Pedestal
Concrete m3 2,42
Reinforcement Bar kg 592,62
Formwork m2 4,4
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 12 of 14

SNBP-EPC-20-CIV-DRW-012 INSTRUMENT AIR RECEIVER FOUNDATION PLAN AND


22
SECTION
Slab
Concrete m3 1,73
Reinforcement Bar kg 140,91
Formwork m 2
4,08
SNBP-EPC-20-CIV-DRW-013 METERING CONTROL ROOM FOUNDATION PLAN AND
23
SECTION
Footing 1
Concrete m3 9,5
Reinforcement Bar kg 693,15
Formwork m 2
31,68
Footing 2
Concrete m3 2,95
Reinforcement Bar kg 190,12
Formwork m 2
6,36
Footing 3
Concrete m3 0,21
Reinforcement Bar kg 30,38
Formwork m 2
1,02
Pedestal 3
Concrete m3 0,08
Reinforcement Bar kg 21,16
Formwork m 2 0,96
SNBP-EPC-20-CIV-DRW-018 AIR COMPRESSOR & AIR DRYER FOUNDATION PLAN
24
AND SECTION
Slab
Concrete m3 8,89
Reinforcement Bar kg 402,79
Formwork m 2
9,96
25 SNBP-EPC-20-CIV-DRW-020 DIESEL STORAGE FOUNDATION PLAN AND SECTION
Footing
Concrete m3 5,18
Reinforcement Bar kg 472,6
Formwork m2 17,28
Footing Stair
Concrete m3 0,21
Reinforcement Bar kg 30,38
Formwork m2 1,02
Pedestal
Concrete m3 1,08
Reinforcement Bar kg 287,28
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 13 of 14

Formwork m2 10,2
Pedestal Stair
Concrete m3 0,08
Reinforcement Bar kg 21,16
Formwork m 2
0,96
SNBP-EPC-20-CIV-DRW-026 LIGHTING PROTECTION FOUNDATION PLAN AND
26
SECTION
Footing
Concrete m3 0,68
Reinforcement Bar kg 78,77
Formwork m 2
1,8
Pedestal
Concrete m3 0,38
Reinforcement Bar kg 51,06
Formwork m 2
3
27 SNBP-EPC-20-CIV-DRW-027 LIGHTING POLE FOUNDATION PLAN AND SECTION
Footing
Concrete m3 0,3
Reinforcement Bar kg 40,55
Formwork m2 1,2
Pedestal
Concrete m3 0,38
Reinforcement Bar kg 51,06
Formwork m 2 3,00
SNBP-EPC-20-CIV-DRW-030 WIND SHOCK & FLAG POLE FOUNDATION PLAN AND
28
SECTION
Footing
Concrete m3 0,12
Reinforcement Bar kg 27,11
Formwork m 2
1,35
Pedestal
Concrete m3 0,38
Reinforcement Bar kg 51,06
Formwork m2 3,00
29 SNBP-EPC-20-CIV-DRW-033 FIRE WATER SYSTEM FOUNDATION
Slab
Concrete m3 0,18
Reinforcement Bar kg 19,21
Formwork m2 1,17
30 SNBP-EPC-20-CIV-DRW-035 MISCELLANEOUS DRAWING
Footing
Concrete m3 0,24
JASA PERANCANGAN, PENGADAAN, DAN
KONSTRUKSI PEMBANGUNAN PIPA GAS
SENIPAH – BALIKPAPAN

Document No. Rev. Date: 25/11/2022


CIVIL – MATERIAL TAKE OFF
SNBP-EPC-00-CIV-MTO-001 A Page 14 of 14

Reinforcement Bar kg 24,19


Formwork m2 1,68
31 SNBP-EPC-20-CIV-DRW-039 RU V Balikpapan - Vent K.O Pot Foundation
Footing
Concrete m3 3,75
Reinforcement Bar kg 269,18
Formwork m2 6
Pedestal
Concrete m3 3,97
Reinforcement Bar kg 180,5
Formwork m 2 8,36
32 SNBP-EPC-20-CIV-DRW-040 RU V BALIKPAPAN TRANSFORMER FOUNDATION
Slab
Concrete m3 13,5
Reinforcement Bar kg 115,15
Formwork m2 3,60
SNBP-EPC-20-CIV-DRW-042 RU V BALIKPAPAN GAS FILTER FOUNDATION PLAN &
33
SECTION
Slab
Concrete m3 0,6
Reinforcement Bar kg 67,42
Formwork m 2 2,40