Kakinada Smart City Corporation Limited (KSCCL)

Presentation on
Workshop on Digital Integrated
Kakinada Integrated Command &
Command & Control Centers under Control Centre (ICT Solutions)
Smart Cities Mission

1
Profile of Kakinada
Slum Population
(2011 census)
1,32,185

101 slums
~ 40% population
Municipal Area
31.39 sq.km Water Supply
Population 105 lpcd
(2011 Census):
3,25,985 Wastewater
management
Literacy Rate Absent
72% (AP: 67%)
67 Govt. Schools with
Budget (FY 2016-17) 12,105 students
~ Rs. 265.58 Cr.

Internal Revenue
~ Rs. 74.67 Cr.
2
Smart Solutions

Disaster
City wide optical Environmental
IOT platform management
fibre network Censors
System

City Wide LORA


Integrated CC Lightning Public Address
based censor
system detection system System
network

Solid Waste
City WiFi Data Centre, DRC Face recognition
Management

Smart Traffic
City Surveillance Smart Parking Smart Lighting
Management

3
CCC Components
Smart Pole: 10

School

School
Public Address
System: 30
Disaster CCTVs:
Management 350
with VMD: 5
25 Emergency
Call Box 10
120 Smart
SIMKm Poles
Fibre
based based City Network
elements
Integrated Command Control Centre
Smart Solutions
Fiberized
Disaster (Project Cost 94.86 Cr.)
Elements
Management
LoRA BTS
640 Smart Lights 26 Km
City Fibre
Wi-Fi: 470 Environmental
470 Wi-Fi APs
GIS Smart
Automatic Sensors
for
Weather Govt. Offices, Citizens
station
Bus stops
100 Parking sensors 120 Km
88 Public address
& 10system
Schools
350 CCTV FRS6for
Kmcity surveillance
5Lightning
Variabledetection system
Km
ERP messaging displays
&
Wi-Fi
4 ATCS – 20 ANPR -box10 RLVD for
71 Govt. 25
12 Emergency
Elementscall
Environmental
Smart Sensors
over IoT Platform
offices
Smart traffic regulation DC/CCC and DR/NOC with GIS & ERP Integrations
LED Lights with server, storage, routers GSM
30 Public
100+ Address
Waste system bins
management Connectivity

Platform
IoT
Smart Waste
23 slots
available
Mgmt: 110 bins
Smart Light:
640 lights ATCS 4 junction 4
Env. Sensors: 12 Smart Parking: 100
RLVD 10
ANPR 20 | FRS: 10
CCC Components Smart Pole: 10
School

ECB: 25 School

Disaster
Mgmt with Automatic
CCTVs:
weather station &
350 PA: 30
Lightening detection VMD: 6
station

Wi-Fi: 470
Bus stops
Schools

City Fibre
Network
71 Govt. IoT Platform
offices of
120 Km
DC/CCC and DR/NOC
Command Control Center with GIS, ERP & Smart
Solution Integrations

Smart Waste
23 slots
ATCS 4 junction available Mgmt: 110 bins
Smart Light: RLVD 10
640 lights on ANPR 20 | FRS: 10 Env. Sensors: 12 Smart Parking: 100 5
320 poles
Network Architecture

Access Ring -2
Access Ring -1 Core & Aggregation layers:
Routers running on IP/MPLS protocols, with
Agg -Ring1 capacity in multiple of 10G (2 Core and 6
AG1 AG2
Aggression routers)

Access Layer:
Core path-1
Home-1 Home-2 Modular temperature hardened Chassis
C c
Access Ring -3 1
Core path-2
2
Access Ring -4 running IP/MPLS based transport with
VICTORIA KMC capacity of 10G (24 Access routers)
Core path-3

Last mile connectivity:


AG3 Street layer switches will be connected to pre
AG4 Aggregation layer with 1G capacity. (Around
Agg -Ring 2 200 Switches)
Access Ring -5
Access Ring -6
All wired Smart Elements like Camera, WiFi,
ANPR, RLVD, ECB, IP PA, FRS, ATCS, LoRa
BTS.

6
Network Architecture with elements integration

7
CCC Architecture Overview

8
Screen Layout in CCC

• Collect, Co-Relate and Response are the main 3 functions of CCC • Rapid decision-making
• Monitoring and control of dynamic activities • Displays sensor, map on a single layout and on video wall
• Real-time video feeds • Management of transportation
• Data integration with different elements • Crime prevention
• Various data and alert signals • Disaster recovery
• Simplifying control room operation

9
Cost Analysis

S. No Component Cost (Rs. In Crores)

1 66,48,74,880
Infrastructure and Installation Cost
(CAPEX - Capital Expenditure)

2 Operations & Maintenance 28,40,48,546


(OPEX – Operational Expenditure)

Total Cost 94,89,23,426

10
Implementation Timelines

Phase 1 completion Phase 2 completion Phase 3 completion


Global
OEM
OEM
90 days 180 days 270 days
Supply
Domestic
OEM

CCC with GIS & ERP


Survey

O&M – 5 Years
CCC & DC DR & NOC
(Needed active
CCC & DC interior readiness for Ph 1) installation

Complete
Fiber connectivity to
Fiber Laying aggregate and 3 100% connectivity
DC/DR
access rings

Field Elements Site Readiness


Smart VMD, Waste Video feed,
Light Sensors, mgmt Disaster
Parking mgmt
SIM based and other elements 30% of Wi-Fi & CCTV ANPR, RLVD, FRS & Rest of
installation & integration elements integration 11
installation & integration
Project Progress Status
Solutions Material @ WH Route/Location Design approval
Fibre (Core/Agre) NA
(32 Kms)

Smart Light (617/640) NA


(392)
Env. Sensors
P1
Disaster mgmt. NA NA
VMD
(3 in progress)
Control Centre (In progress)
SWM NA
Smart Parking NA
Wi-Fi NA
P2
CCTV 15th Oct 2017 NA
DR-NOC

Other elements: ANPR,


RLVD, ATCS, PA, ECB
30th Dec 2017 NA
P3
GIS Integration APIs NA NA
ERP Integration NA NA
Done Partially done Pending
12
CCC Elevation
Birds View
Front View

13
Work in progress at CCC building

14
Optical Fibre Cable laying & Smart Light Installation
Optical fibre cable laying Smart street light installation

15
VMD construction, Smart Traffic and Parking
VMD Sub structure construction is in progress Joint site survey with Police Department for locations of Smart Traffic
elements & Smart parking

16
17