PEMBINAAN PINTU GERBANG KAWASAN LITTLE INDIA,

LEBUH PASAR, BANDARAYA GEORGE TOWN, DAERAH


TIMUR LAUT

LAPORAN PEMANTAUAN
KERJA
SEHINGGA
16 NOVEMBER 2022

DISEDIAKAN OLEH:
SRI & SRI’S ASSOCIATES SDN. BHD. - Innovating Engineering Solutions
PROGRESS UNTIL 16th November 2022
AS PER CONTRACTOR'S SCHEDULE
Estimated
PERCENTAGE PERCENTAGE
No. Ahead
Start Date Finish Date OF WORKS PER OF WORKS
DAYS /(Delay) in
SCHEDULE (%) DONE (%)
Days
FOOTING
100 100 0
1A
FOOTING 1 100 100 0
COLUMN
14/9/2022 25/9/2022 12 100 90 -1.2
1A
Finishes 95
Column 1 27/09/2022 07/10/2022 12 100 90 -1.2
Finishes 95

DOME 3 08/10/2022 31/10/2022 24 100 63.33 -9.4


Fabrication 08/10/2022 18/10/2022 11 100 0
Installation 19/10/2022 25/10/2022 7 0 -7
Finishes 25/10/2022 31/10/2022 6 60 -2.4

DOME 2 23/10/2022 02/11/2022 11 100 74.18 -1.9


Fabrication 23/10/2022 26/10/2022 4 90 -0.4
Installation 27/10/2022 30/10/2022 4 0 0
Finishes 31/10/2022 02/11/2022 3 50 -1.5

DOME 2A 03/11/2022 13/11/2022 11 100 43.64 -6.2


Fabrication 03/11/2022 06/11/2022 4 90 -0.4
Installation 07/11/2022 09/11/2022 3 0 -3
Finishes 10/11/2022 13/11/2022 4 30 -2.8

DOME 1 14/11/2022 29/11/2022 13.6 22 64.56 4.8


Fabrication 14/11/2022 20/11/2022 6 50 3.0
Installation 21/11/2022 25/11/2022 5 0 0.0
Finishes 27/11/2022 29/11/2022 2.6 30 1.8

LETTERING 14/11/2022 25/11/2022 11 27 50 0


Fabrication 14/11/2022 19/11/2022 5 50 0
Installation 20/11/2022 22/11/2022 3 50 0
Finishes 23/11/2022 25/11/2022 3 50 0

Electrical 31/10/2022 26/11/2022 25 68 48 -13

BALANCE DAY (TOTAL 153 DAYS) 14 Days


OVERALL ESTIMATED
-28 Days
DELAY
Overall Work done 72 %
Actual percent to Obtained 90 %