Professional Documents
Culture Documents
Laporan Kemajuan Oleh Sri 16.11.22
Laporan Kemajuan Oleh Sri 16.11.22
LAPORAN PEMANTAUAN
KERJA
SEHINGGA
16 NOVEMBER 2022
DISEDIAKAN OLEH:
SRI & SRI’S ASSOCIATES SDN. BHD. - Innovating Engineering Solutions
PROGRESS UNTIL 16th November 2022
AS PER CONTRACTOR'S SCHEDULE
Estimated
PERCENTAGE PERCENTAGE
No. Ahead
Start Date Finish Date OF WORKS PER OF WORKS
DAYS /(Delay) in
SCHEDULE (%) DONE (%)
Days
FOOTING
100 100 0
1A
FOOTING 1 100 100 0
COLUMN
14/9/2022 25/9/2022 12 100 90 -1.2
1A
Finishes 95
Column 1 27/09/2022 07/10/2022 12 100 90 -1.2
Finishes 95