Pic Pintu Gerbang 11.11.22
Pic Pintu Gerbang 11.11.22
% Work Per Schedule = 87% ; % Work Done = 71% ; Delay/ Ahead (days) = -24 days
Dome 2A
% Work Per Schedule = 100%
% Work Done = 43.33%
Delay/ Ahead = 0.2 days
Column 1 Column 1A
% Work Per Schedule = 100% Dome 3 % Work Per Schedule = 100%
% Work Done = 85% % Work Per Schedule = 100% % Work Done = 85 %
Delay/ Ahead = -1.8 days % Work Done = 53.75% Delay/ Ahead = -1.8 days
Delay/ Ahead = -12.2 days
Footing 1 Footing 1A
% Work Per Schedule = 100% % Work Per Schedule = 100%
% Work Done = 100% % Work Done = 100%
Delay/ Ahead = 0 days Delay/ Ahead = 0 days