OVERALL

% Work Per Schedule = 87% ; % Work Done = 71% ; Delay/ Ahead (days) = -24 days

Dome 2 % Work Done = 74.18% Dome 1


Delay/ Ahead
% Work Per Schedule = -0.88 days
= 100% % Work Per Schedule = 0 %
% Work Done = 57.27% % Work Done = 44.85%
Delay/ Ahead = -6.3 days Delay/ Ahead = 6.1 days

Dome 2A
% Work Per Schedule = 100%
% Work Done = 43.33%
Delay/ Ahead = 0.2 days

Column 1 Column 1A
% Work Per Schedule = 100% Dome 3 % Work Per Schedule = 100%
% Work Done = 85% % Work Per Schedule = 100% % Work Done = 85 %
Delay/ Ahead = -1.8 days % Work Done = 53.75% Delay/ Ahead = -1.8 days
Delay/ Ahead = -12.2 days

Footing 1 Footing 1A
% Work Per Schedule = 100% % Work Per Schedule = 100%
% Work Done = 100% % Work Done = 100%
Delay/ Ahead = 0 days Delay/ Ahead = 0 days