1) 1 BLOK 6 TINGKAT PUSAT PERUBATAN & 1 TINGKAT TEMPAT LETAK KENDERAAN BAWAH TANAH
2) PONDOK PENGAWAL , RUMAH PAM AIR & KEBUK SAMPAH
DI ATAS LOT 443, SEKSYEN 43 DAERAH KULIM, BANDAR KULIM, KEDAH DARUL AMAN.
DESIGN RAINFALL
In accordance with Urban Stormwater Management Manual for Malaysia (MSMA Second edition 2012)
Peak rainfall intensity; I = λ × (T/1yr)κ / (t/1hr + θ)η × 1mm/hr I = λ × (T/1yr)κ / (t/1hr + θ)η × 1mm/hr
I = 206.81 mm/hr I = 185.86 mm/hr
Design runoff
time, t = 5 minute
period = 10 years
Catchment area; A= = 4179 m2
Runoff coefficient (Table 2.5); C= = 0.9
I = 206.81
Design runoff (rational method); Q=C×I×A = 0.2160647475 m3/s