REINFORCING BAR BENDING SCHEDULE

Project : Sewage Treatment Plant


Client : Chittagong Water Supply and Sewerage Authority RFI No : TY-WTP
Consultant : ERINCO-BETS-DEVCON-IWM-JV
Structure Name : U Drain
Contractor : Taeyoung E & C Company Limited
Bill No :
Item No. :
Item Description : 1000x1000 U drain
Rebar Installation Date :

Net Rebar Auxiliaries(Chair, Lap & Separator)

Bar Unit Bar Unit Total


Re bar No of Total Bar Total Weight No of Total Bar
SL No Description/Location Bar Shape Length Weight Length Weight Weight Remarks
Size Rebar Length (M) (Ton) Rebar Length (M)
(M) (KG/M) (M) (KG/M) (Ton)

A B C D E F G=E*F H I=G*H J K L=J*K M N=L*M

1310
Top-bottom bar at short direction of
01 D10 Foundation 12 1.310 15.720 0.616 0.010

1000
Top-bottom bar at Long direction of
02 D10 Foundation 18 1.000 18.000 0.616 0.011

1300
Vertical bar with development of
03 D10 walls 12 1.778 21.336 0.616 0.013
478

1100
04 D10 Vertical bar of walls 12 1.100 13.200 0.616 0.008

1000
05 D10 Horizontal bar of walls 22 1.000 22.000 0.616 0.014

1010
Top bar Short direction of Precast 110 110
06 D12 12 1.230 14.760 0.888 0.013
Slab

Bottom bar Short direction of 110 110


07 D12 12 1.230 14.760 0.888 0.013
Precast Slab 1010

Top-bottom bar Horizontal 1000


08 D10 12 1.000 12.000 0.616 0.007
direction of Precast Slab

114

9 D10 Bottom hunge bar 12 0.774 9.288 0.616 0.006


560

100

Sub Total D10mm Rebar for 1 Meter 0.069


Sub Total D12mm Rebar for 1 Meter 0.026
Sub Total for 1 Meter 0.095
Total D10mm Rebar for 2500 Meter 171.778
Total D12mm Rebar for 2500 Meter 65.534
Total rebar (D10 & D12) for 2500 Meter 237.312
Total D10mm Rebar for 2500 Meter with 3% Lapping & Wastage 176.931
Total D12mm Rebar for 2500 Meter with 3% Lapping & Wastage 67.500
Total rebar (D10 & D12) for 2500 Meter with 3% Lapping & Wastage 244.432

Requested By : Contractor Checked and Approved by : Consultant