CG 200706 DWR 056
CG 200706 DWR 056
Work Performed:
1. Project Handover.
2. Changing of user automatic logout time from HMI from 10 minutes to 12 hours as per directed by CSS.
Issues:
Please refer to punch list for details.
Lifua Progress:
No. Task Progress
1. SIS Loop Testing 191/241
2. FGS Loop Testing 147/147
3. PCS Loop Testing 173/196
Future Tasks:
1. Closing of punch items.
2. QAY1200 remaining loops check.