Professional Documents
Culture Documents
Aqpaxi Phase 3
Aqpaxi Phase 3
Approved By:
INTRODUCTION
The third phase in a project is Process Development. This phase is designed to ensure the
comprehensive development of an effective manufacturing system and corresponding controls to
achieve customer satisfaction. During this period of time, process methods and flow, and product
features and characteristics, are developed into a feasible and final form. A "feasible" design and
manufacturing process must satisfy production volumes and schedules including fluctuations in
demand, and be consistent with engineering standards and specifications, as well as quality,
reliability, durability, and other external and internal objectives.
The inputs and outputs relevant to this phase may vary depending on the situation, needs and
wants of both the customer and the company.
The team consisting of the Program Manager, Manufacturing Engineer, and Quality Engineer
shall complete the Process Failure Mode and Effects Analysis (PFMEA). Completing the
PFMEA is the first major step in identifying and/or qualifying characteristics to control in the
manufacturing process.
The PFMEA is a living document and as such, it should continue to be updated throughout the
program, particularly as manufacturing inputs become available. PFMEA document will reflect
all changes identified in an ECN or customer deviation.
Axiom Group Inc.’s policy is to demonstrate RPN reductions in the PFMEA development. The
following criteria have been established to determine the need for action:
As per the above criteria, the team must demonstrate reductions in the overall RPN total by
completion of the PFMEA by the end of Phase 3 of the program.
The process flow is a representation of the total process from receiving inspection through
shipping of the final product. The process flow diagram illustrates how the parts will flow
through the anticipated manufacturing process.
No specific format is required for this diagram since customer requirement vary widely. Check
with the Quality Assurance Manager for the diagram and details of the required format.
The Floor Plan Layout should be developed and reviewed to determine the acceptability of
machine layout, product flow efficiency, inspection points, control chart location, visual aids
location, interim repair stations, and storage areas to quarantine defective material.
No specific format is required for this diagram since plant and customer requirements vary
widely. Check with Senior Management for the floor plan layout.
A list of all equipment, tooling and facilities needed to successfully produce production parts
must be completed (QAR-8.3.8).
If possible and where appropriate, identify preliminary calibration and preventive maintenance
requirements; otherwise, provide this information at a future date.
The purpose of Production Release Review is to familiarize the team with the product, as it will
be released for production.
During the design review, tooling (design for manufacturing) considerations must be taken into
account and addressed.
Typical inputs to the Production Level Review include but are not limited to:
As per customer requirements Quality Assurance Manager or designate must schedule supplier
PPAP (QAR-8.3.37) to coincide with the needs of the plant and customer to ensure timing and
requirements are met for our PPAP submission.
The team must ensure that pre-launch control plans (QAR-8.5.0) are prepared. These plans are
intended to provide a description of the process controls, dimensional measurements, material
and functional tests that will occur during pre-production builds.
The date the documented instructions and illustrations for manufacturing and inspecting the
specified product are complete.
The required format and content of these documents may vary depending on the manufacturing
location and customer involved. Check with the quality department for the instructions and/or
the customer-required format.
This is the date that Senior Management or designate completes the Preventative Maintenance
Plans for all equipment and tooling associated with the product. A preventative maintenance
plan should exist for machine, tooling, assembly equipment and gages.
The team must determine special training needs and develop a training plan. Training plans
should, at a minimum include the following elements:
Training schedule
Qualified trainers/instructors (may include members of AQP team)
Training materials
Training facilities (if other than on the job)
This is the date that packaging specifications are approved. The purpose is to document the
packaging method and materials agreed upon with the customer. The packaging must provide
sufficient damage protection during shipping and handling from the end of our line to the
customer assembly line. Packaging and label requirements shall be as per customer requirements.
If applicable, Program Manager will record the date for safe launch plan completion. Where Safe
Launch Plan is utilized start dates, exit criteria and completion dates to be recorded on the Safe
Launch Plan Log (QAR-8.3.26) and data recorded on I Charts. Once exit criteria is satisfied
change to Production Control Plan. (QAR-8.5.0)
When all the phase 3 items are closed, management must review the outputs of the team and
approve the completion of the phase or recommend further actions required achieving
completion (QAR-5.0.1). This review must be completed by the end of Phase 3 for any direct
programs with Daimler Chrysler, Ford or General Motors.