Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Applied Energy 285 (2021) 116437

Contents lists available at ScienceDirect

Applied Energy
journal homepage: www.elsevier.com/locate/apenergy

Impact of emergency diesel generator reliability on microgrids and


building-tied systems
Jeffrey Marqusee , Sean Ericson , Don Jenket *
National Renewable Energy Laboratory, Golden, CO, United States

H I G H L I G H T S

• Finite reliability of diesel generators is crucial for backup energy planning.


• A model comparison of building-tied and networked generator systems is presented.
• An N + 1 network has a ≥93% probability of powering all buildings for a 2-week outage.
• A single generator design is not likely to power all buildings for a 2-week outage.

A R T I C L E I N F O A B S T R A C T

Keywords: Microgrids are an emerging alternative as an energy backup system for critical electric loads and have improved
Emergency diesel generators performance compared to the traditional architecture where a single emergency diesel generator is tied to an
Microgrids individual building. Both architectures are dependent on the reliability of their individual generators and a
Reliability
quantitative and realistic comparison of the overall system reliability of the two architectures is lacking. Using
Energy resilience
Microgrid reliability
recently published work on emergency diesel generator finite reliability, a quantitative methodology is presented
Generator reliability to compare the reliability of a microgrid architecture based on centralized emergency diesel generators to the
traditional approach of generators tied to individual buildings. Three system reliability performance metrics are
calculated as a function of outage duration: (1) probability to meet 100% of the critical load; (2) expected
fraction of lost load; and (3) probability to meet the highest priority critical loads. It is shown that stand-alone
building-tied emergency diesel generators systems, even when two emergency diesel generators are used per
building, cannot provide the reliability required to sustain critical loads for a grid outage lasting multiple days.
Due to their network configuration and ability to share load, diesel generator-based microgrid configurations are
estimated to have ≥ 93% probability of powering all buildings for a 2-week outage there the individual building-
tied emergency diesel generator architecture has a ≤20% probability. Microgrids do present other susceptibilities
that are site specific and should be considered including vulnerabilities associated with the on-campus distri­
bution system and cybersecurity.

1. Background Customers with critical backup power requirements have historically


relied on building-tied generators with short-term fuel stockpiles to
Microgrids have emerged in the last decade [1] as a solution for end provide emergency backup power during a grid outage. The Department
users’ need for energy security and higher energy reliability. They are an of Homeland Security’s Enhanced Critical Infrastructure Program
alternative to traditional standby power system comprised of building- Initiative reports that 85% of backup power for the U.S. critical infra­
tied emergency generators. Although the primary driver for deploying structure is provided by emergency or standby diesel generators [3]. The
a microgrid is to support critical loads during a grid outage, the litera­ role and size of the backup power capacity varies among critical facil­
tures’ focus has primarily been on their multiple revenue streams [2] ities: 28% of facilities have backup power for all functions, 38% for their
and few comparisons have been conducted on their performance relative core or critical functions, 27% only for life and safety systems, and 6% to
to traditional approaches to provide power during a grid outage. allow for a graceful shutdown [3]. In the case of a stand-alone backup

* Corresponding author.
E-mail address: donald.jenket@nrel.gov (D. Jenket).

https://doi.org/10.1016/j.apenergy.2021.116437
Received 15 June 2020; Received in revised form 13 November 2020; Accepted 3 January 2021
Available online 16 January 2021
0306-2619/© 2021 Elsevier Ltd. All rights reserved.
J. Marqusee et al. Applied Energy 285 (2021) 116437

power system, every building requiring power during a grid outage has a Model for Multiple Energy Resources (HOMER) [17], and Distributed
single (building-tied) backup generator that is hardwired directly to the Energy Resource, Customer Adoption Model (DER-CAM) [18 19],
building. Two individual backup generators can also be utilized for developed by Lawrence Berkeley National Laboratory, do not take into
buildings with high priority building loads. This configuration offers a account the nonperfect reliability of the DERs that make up the micro­
backup to the backup and provides a higher degree of reliability. grid. Although they discuss reliability and resilience, none consider DER
Building-tied emergency diesel generators (EDGs) typically range in size reliability in determining the microgrid’s performance. For example,
from 10 kW to a few hundred kWs. recent analysis using REopt has assessed resilience by considering finite
A microgrid offers a different approach to provide backup power for fuel supplies [20] but always assumes that if fuel is available the gen­
critical facilities and today is often viewed as a potential solution for erators will operate. The Microgrid Design Toolkit (MDT) [21 22],
campuses, military installations, and communities in light of the developed by Sandia National Laboratory, calculates microgrid perfor­
growing concerns of multiday grid outages. A microgrid is a local system mance in an islanded mode using a Monte Carlo simulation to account
of distributed energy resources (DERs) and energy demands that can for DER reliability. But they provide no recommendations on how to
operate as one entity both in conjunction with to the commercial grid or model the individual DER reliability. Direct Monte Carlo simulations for
separately during a grid outage (“island” mode). When connected to the rare events are slow to converge and thus difficult to use to assess overall
grid, it can offer revenue generation and cost savings. During a com­ microgrid reliability. To date, Sandia’s tool has not been used to assess
mercial grid outage, it can provide emergency backup power. DERs that the impact of DER reliability on a microgrid’s reliability.
comprise a microgrid can include any energy generation and storage In this paper, a quantitative methodology is presented to compare
technologies, including emergency generators, prime generators, com­ the reliability of a common microgrid architecture based on centralized
bined heat and power plants, renewables, batteries, as well as many EDGs and the traditional approach of stand-alone EDGs tied to indi­
other energy technologies. This work is focused on microgrids powered vidual buildings. Using recently published work on EDG reliability [11],
by a modest number of larger EDGs that are often placed in a single the large difference in energy reliability for these two systems is illus­
location on the campus. Centrally locating EDGs is a common microgrid trated and its sensitivity to key energy consumption and generation
configuration for ease of maintenance, refueling, and integration with characteristics.
both the on-campus distribution and the grid. Microgrid reliability is In the next section, two model campuses are presented that are
dependent on the vulnerability of the on-campus distribution system, representative of the many different type of sites who consider deploy­
while building tied systems are not. Many campuses that have experi­ ing a microgrid as an alternative to building-tied EDGs. These will be
enced long duration outages due to grid failures see no impact to their used to highlight the reliability comparison between microgrids and
on-campus distribution system either because it is not located where the building-tied architectures. In Section 3, the reliability of an individual
greatest damage to the grid occurred or because its distribution system is EDG is reviewed. In Section 4, the methodology for calculating the
hardened or protected. The probability that the on-campus distribution system reliability of a microgrid and traditional building-tied backup
system is disrupted during a long duration grid outage is very site spe­ power systems is described. In Section 5, results are provided for the two
cific and should be considered as an additional factor to those consid­ example campuses and a characterization of the sensitivity of a system’s
ered in this paper. reliability to key energy consumption and generation characteristics.
The availability of electric power and its reliability from microgrids Lastly, a brief discussion is provided on the importance of considering
versus the traditional energy backup system of building-tied EDGs is finite reliability when considering a microgrid and discuss future
dependent on the reliability of the individual EDGs, the most commonly directions.
used DER for providing backup power. Although it is recognized that
DER selection determines the reliability of a microgrid system as high­ 2. Backup power architectures: stand-alone and microgrid
lighted in recent reviews [4] and surveys [5], quantitative and realistic
assessments on the impact of DER reliability on microgrid reliability and To illustrate the impact of EDG reliability, two realistic cases were
a comparison to existing common alternatives is absent from the created for a campus or group of buildings that require backup power: a
literature. small campus with a peak annual critical hourly load of 1 MW and a
Studies that have examined microgrid reliability have used generator large campus with a peak annual critical hourly load of 10 MW. The
performance metrics that are almost two times too high [6] or use a small campus represents a typical critical load seen in colleges [23],
probabilistic capacity table to estimate system performance [7]. national guard bases [24], regional airports [25], and community hos­
Techniques to select the optimum mix of DERs do not consider the pitals. The second larger example is typical of critical loads seen in large
reliability differences of the DERs being considered [8]. Recent reviews universities [26], large active military installations [24], midsize air­
of the role of microgrids to provide resilience have highlighted the ports [25], and research hospital complexes. For each campus, three
importance of a microgrid but ignores its vulnerabilities to DER reli­ EDG-based architectures are modeled.
ability [9]. Ignoring the reliability of the DER is an incorrect approach in In the first architecture, each building with a critical load is con­
general [10] and when applied to power systems [11]. A few recent nected to a single EDG. In the second architecture, each building with
studies have attempted to assess the impact of DER reliability on a high-priority critical loads is connected to two EDGs. Using two EDGs for
microgrid’s reliability using cross-entropy [12] and sequential [13] a single building is a common approach to provide higher reliability but
Monte Carlo simulation but neither use realistic estimates for DER is rarely done for all critical loads on a campus due to costs. In the third
reliability.1 Industry has recognized this issue and has highlighted this architecture, centralized EDGs are utilized to create a microgrid.
gap in the ability to assess microgrid performance [14]. The microgrid was designed to model the commonly used N + 1
Multiple software tools have been developed to design and optimize configuration. The annual peak critical load for each campus size and
microgrid configurations [1]. Most do not account for DER reliability at the size of the EDG defined N for each scenario and an additional EDG of
all. A few treat it using Monte Carlo approaches, which have short­ the same size is added. Engineering trade-offs were used to determine
comings associated with the root assumptions and have not been used to the size of the EDG for each scenario. Choosing many small EDGs would
assess the impact using realistic reliabilities for the key DERs. Three result in high maintenance costs where choosing a few large EDGs would
commonly used modeling tools: REopt [15 16], developed by the Na­ make it difficult to meet future load growth in a cost-effective manner
tional Renewable Energy Laboratory (NREL), Hybrid Optimization while maintaining a common fleet of EDGs. The centralized EDGs were
constrained to be in multiples of 250 kW. The campus’ and the micro­
grid’s EDGs characteristics are listed in Table 1.
1
Unrealistically high failure rates have been used. Due to the networked architecture, each generator in the microgrid

2
J. Marqusee et al. Applied Energy 285 (2021) 116437

Table 1 tures the likelihood the EDG is available at the start of a grid outage and
Characteristics of small and large campuses used for modeling. is calculated by:
Campus Size Small Large l − tol
OA = (3)
Peak Critical Load 1 MW 10 MW l
Number of Buildings with Critical Loads 8 80
Size of Centralized EDGs 250 kW 750 kW where l is the lifetime and tol is time offline due to repairs and mainte­
Number of Centralized EDGs (N + 1) 5 15 nance. The OA metric can change based on maintenance schedules,
repair times, and annual failure rates.
can provide power to every building in the campus. Therefore, the For this model, the EDG is assumed to be in its “useful life period”
critical load profile must be known to assess the microgrid’s perfor­ and the run-time failure rate is constant. This rate can be calculated as
mance because the effective redundancy of the networked EDGs will the inverse of the MTTF. Thus, the reliability of an EDG at time t is given
vary as the load demand changes. For the first two building-tied EDG by:
architectures, information about the overall critical load demand is not R(t) = OA × (1 − FTS) × e− t/MTTF
(4)
needed because each EDG can only support the building it is tied to, even
if it has excess capacity. Hourly load profiles from six military bases, two A recent report [11] reviews the current EDG reliability literature
universities, and one hospital were gathered and reviewed. Based on and demonstrates that commonly reported values in the literature are
critical loads found on similarly sized campuses, load profiles were inappropriate for assessing an EDG’s reliability. The results presented
created for the small and large campuses, so their annual peak critical differ significantly from the reliability data in the Institute of Electrical
loads are 1 MW and 10 MW, respectively. Fig. 1 shows the hourly load and Electronics Engineers (IEEE) 3006.8 Recommended Practice for
profiles used in this study in hourly kW and the number of EDGs. Analyzing Reliability Data for Equipment Used in Industrial and Com­
Critical load during peak summer months is typically higher than the mercial Power Systems [10].
rest of the year, and peak load hours at that time drive the number of The IEEE reliability data is often incorrectly used to estimate the
centralized EDGs required. During the winter months and off-peak pe­ reliability of continuously running EDGs during a grid outage. Based on
riods, multiple generators would have to fail for load to be dropped by a detailed analysis [11] of data on thousands of EDG years of fielded
the microgrid. No such redundancy is possible with a building-tied commercial EDGs collected by the U.S. Army [27] and Navy (28) (see
system. Table 2), modern2 well-maintained EDGs in the power range of
10–2000 kW can be characterized by the values in Table 3.
3. Single EDG reliability When calculating the lower bound for reliability, the low MTTF with
a high FTS is used and vice versa for the upper bound. These reliability
In this section, recently published work on the reliability of a single metrics are more than an order of magnitude better than seen in poorly
EDG is reviewed, a short introduction to reliability theory is presented, maintained EDGs [29] and also better3 than the values reported for the
the relevant reliability metrics to quantitively represent an EDG are much larger EDGs used to support nuclear power plants in the United
illustrated, and the empirical data on EDG performance [11] is States [30].
reviewed. Summarizing [11] mean operational availability of a well-
Most energy systems or components are designed to operate maintained EDG is 99.98%. This high availability reflects the small
continuously, and their reliability assessments are conducted appropri­ number of EDG runs per year, and thus the small number of potential
ately. However, EDGs only run during testing or during an outage and failures per year. A single well-maintained EDG has a reliability between
therefore rest in an unused state for most of the year. 92% and 96% for providing backup power for four days (96 h) into an
Additionally, their yearly operation was limited to 200 h (for non- outage (the current requirements for critical loads at hospitals [31]),
emergency use) by the Clean Air Act regulations, and most run for less between 90% and 95% for a one week outage, and between 75% and
than that. Understanding the intended use for backup devices and the 87% for a two-week outage (requirements for critical loads at military
corresponding time intervals becomes important when defining EDG facilities).
reliability metrics for backup power.
To address the irregular use of EDGs, the EDG is assumed to suc­ 4. System reliability
cessfully start, can carry the load, and then a mean time to failure
(MTTF) is defined that captures failures while the EDG is running. This In this section, the system-level reliability is derived for a system of
MTTF can be determined by: building-tied EDGs and a microgrid based on centralized EDGs [32]. The
mean time to repair an EDG is 37 h [11] and the model assumes that
tr
MTTF = (1) failed EDGs will not be repaired during the outage for both systems.
nrtf

where tr is the total runtime and nrtf is the number of failures while 4.1. Building-tied
running or run-time failures. This MTTF is not dependent on the reli­
ability of the grid or how often the EDG is tested. This metric is defined In the first modeled architecture, each building with a critical load
by total runtime and the number of failures that occur while running. has one EDG connected to it. If the generator fails, the building will lose
To capture the likelihood that the EDG fails to start and carry the power. In the second modeled architecture, both EDGs have to fail for
load, another reliability metric, the failure to start probability (FTS), is the building to lose power. A generator can fail in three ways: (1) not
introduced and is calculated as: being at the start of an outage due to maintenance or repairs, (2) failing
nfts to start, or (3) failing to continuously run for the duration of the outage.
Failure to Start Probability (FTS) = (2)
nats The likelihood that an EDG survives an outage of duration d, R1 (d), is
calculated using the three reliability metrics presented in the previous
where nfts is the number of failures to start and nats is the number of
attempts to start. These two metrics characterize the intrinsic reliability
of an EDG (i.e., detached from the reliability of the grid and the testing 2
By modern, the meaning is that typical of EDGs deployed today.
rate). 3
Commercial well-maintained EDGs used on campuses are two to three times
An additional metric, the operational availability (OA), which cap­ more reliable than those used in nuclear power plants.

3
J. Marqusee et al. Applied Energy 285 (2021) 116437

Fig. 1. Modeled campus critical load profiles with generator step sizes for small (left) and large (right) campus.

()
b
Table 2 where k denotes the number of combinations of selecting k buildings
Summary of the datasets used in (11) to obtain MTTF and FTS parameters in
from the set of b possible buildings. The average number of buildings
Table 3.
that still have power at time d can be calculated using the mean value of
Source # EDG Years of Comments
k at time d:
(Ref) EDGs Observation

Army 304 2298 • Representative size EDG Mean(k) = b × Ri (d) (9)


[27] (≤1500 kW)
• Mixed maintenance
The remainder is the number of buildings without power or simply b
Navy [28] 239 1281 • Representative size EDGS minus k. Lastly, the fraction of expected loss of power (ELP) can
(10–2000 kW) equivalently represent this data and can be approximated as:
• Well-maintained
ELPi (d) = 1 − Ri (d) (10)
This model assumes all the EDGs have the same reliability metrics
Table 3 and each building (with the same architecture) is equally reliable.
Mean reliability metrics and 90% confidence intervals (11) used in this model. Therefore, the total number of buildings do not affect the ELP as this
Metric Low (90% confidence) Mean High (90% confidence) reflects the average fraction of buildings without power for any campus
size.
MTTF 1180 h 1662 h 2410 h
FTS 0.10% 0.13% 0.17%

4.2. Microgrid
section:
Due to the network configuration of a microgrid, the reliability cal­
R1 (d) = OA × (1 − FTS) × e− d/MTTF
(5) culations require a different approach than the building-tied architec­
tures. The critical load demand varies with season, day of week, and
If two generators are connected to a building, then the system sur­
time of day. A backup system that has an N + 1 configuration for the
vives if at least one of the generators survives. The survival probability
peak critical load may have significant additional redundancy for much
of the building having power for the duration of the outage is deter­
of the year.
mined by the probability of either generator surviving, which is given
Fig. 2 displays the annual percentage of critical load for the large
by:
campus scenario ordered by load size. A microgrid system with N + 1
R2 (d) = 2*R1 (d) − R1 (d)*R1 (d) (6) generators, with each generator sized at 750 kW, has a redundancy of N
+ 5 or more for more than 80% of the year. The irregularity of the
In a campus-like environment, such as a hospital complex, military
bases, airports, and universities, critical loads occur in multiple build­
ings. To meet the critical functions and provide for health and safety, a
campus needs to have all or most of its critical loads supported. If there
are b independent buildings with critical loads of concern and i EDGs
tied to each building, the probability of all b buildings having power
(ABHP) at outage hour d during a grid outage is then:

ABHPi (b, d) = Ri (d)b (7)


Another way to present this data is to calculate the average number
of buildings that are likely to lose power during an outage. Out of b
buildings, the probability that k buildings have power at time d is given
by the binomial distribution:
( )
b
Ƥi (b, k, d) = Ri (d)k (1 − Ri (d))b− k (8)
k

Fig. 2. Percentage of annual critical load for large campus ordered by load size.

4
J. Marqusee et al. Applied Energy 285 (2021) 116437

critical load must be included when calculating the probability of sur­ {


vival and the expected critical load lost. 0 C(n, d, t) > 0
Sm (n, d, t) = (16)
P(n, d) C(n, d, t) = 0
The critical load profiles used in this analysis come at hourly in­
tervals, and a discrete representation of component reliability must be In other words, for each hour, the probability of having n working
used for the microgrid analysis compared to the continuous formulation generators is calculated and the probability of survival is set to zero for
used for the building-tied scenarios. The probability that n generators systems that cannot meet the critical load. The probability that all
can provide power at the start of an outage from a total of N generators is buildings have power in the microgrid at duration d is then calculated as:
given by P(n, 0): ( )∑
( ) 1 T ∑ N

N ABHPm (d) = Sm (n, d, t) (17)


P(n, 0) = (OA*(1 − FTS) )n *(1 − OA*(1 − FTS) )N− n (11) T t=1 n=0
n
Generators become increasingly likely to fail to run as the outage
which is simply the combinatorics formula for n generators being duration increases, and because the critical load profile varies with
available and not failing to start, and N − n generators being unavailable when the outage starts the probability of having sufficient generator
or failing to start. The model assumes all EDGs attempt to start at the capacity varies across the year. Figs. 3 and 4 display the probabilities
beginning of the grid outage even though all N + 1 might not be that the microgrid system at the large campus has a given number of
required. It is optimal to run EDGs at 50–80% of their maximum ca­ generators over a one-week outage for generators for well and poorly4
pacity [33]. For the scenarios, the average annual hourly critical load is maintained EDGs, respectively.
approximately 50–60% of the peak and the peak load is between 80% The probability of outage starting is assumed to be equally likely at
and 90% of the total N + 1 EDG capacity. Having the model start all the any time during the year. This allows for the annual, seasonal, and daily
EDGs and continually running them properly loads the EDGs. variability in the hourly critical load profile to be captured in the annual
Starting with n running generators, the likelihood that n’ generators average metrics discussed in the next section. This assumption can easily
are running in the next hour is given by p(n, n’ ): be relaxed if there is knowledge on when outages are likely to start. The
(n) chance that several generators have failed increases with outage dura­
(1 − FTR)n *FTRn− n (12)
’ ’
p(n, n’ ) = tion and is much higher for poorly maintained generators than for well-
n’
maintained generators. Reinforcing the need to do proper maintenance
where FTR is the discrete hourly version of exponential decay rate. A of EDGs. In all cases shown below only well-maintained EDGs are
Markov matrix is used to capture the likelihood of n generators still considered.
operating after d outage hours, designated as P(n, d):
⎡ ⎤ ⎡ ⎤d ⎡ ⎤ 5. Application of architecture reliability to scenarios
P(0, d) 1 p(n, 0) ⋯ p(N, 0) P(0, 0)
⎢ P(1, d) ⎥ ⎢ 0 p(n, n’ ) ⋯ p(N, n’ ) ⎥ ⎢ P(1, 0) ⎥

⎣ ⋮ ⎦ = ⎣⋮
⎥ ⎢ ⎥ ⎢
⎦ ⎣ ⋮ ⎦
⎥ (13) Illustrated below are three reliability system performance metrics
⋮ ⋱ ⋮
P(N, d) 0 ⋯ 0 p(N, N) P(N, 0) using well-maintained EDG parameters to compare the EDG system ar­
chitectures. The first metric is survivability, the likelihood that all
The amount of unserved load for each hour is dependent on the buildings have power as a function of outage duration. The survivability
critical load demand and number of generators running during that metric posed the most difficult conditions to meet where any load not
hour. The unserved load for an outage starting at time t, in outage hour served is considered a failure. The second metric is comparing the mean
d, given n currently working generators, each with a capacity of c, is fraction of lost load for the microgrid to the mean fraction of buildings
given by: without power for the single building-tied EDG architecture. The last
metric compares the reliability for the highest priority critical loads,
C(n, d, t) = max(0, L(t + d) − c*n) (14)
which is represented as a fraction of the total critical load and must be
where L(t +d) denotes the critical load in hour t +d and C denotes the sustained during a grid outage. For this scenario the microgrid system is
quantity of unserved load. The model assumes that outages are equally compared to the two building-tied EDGs per building architecture.
likely to occur throughout the year, and the microgrid’s expected per­ Finally, the sensitivity of these results to the load and generation char­
centage of load shed at outage duration d is: acteristics is examined.
( )
∑T ∑ N
EPLSm (d) = ∑T
1
P(n, d)*C(n, d, t) (15) 5.1. Survivability: probability to support 100% of critical load
t=1 L(t) t=1 n=0
The survivability results are shown below in Fig. 5. The single
where T denotes the number of hours in the year. The above equation building-tied EDG architecture was compared to the centralized N + 1
says that the expected load shed in outage hour d is the sum of unserved EDG microgrid architecture for both the small and large campus sizes.
load across the possible number of working generators weighted by the The mean values for well-maintained EDGs are presented along with the
probability that number of generators are working in outage hour d. 90% confidence intervals based on the data in Table 2. This is the most
Next, the probability of survival is calculated. This is equivalent to rigid metric and it demonstrates the vast differences in reliability be­
the likelihood that all load is served (i.e. all buildings have power). tween the two architectures. As the campus size increases the number of
The system survives if it has sufficient generation to meet the critical buildings, the probability that one or more building-tied generators will
load and fails if the critical load exceeds available generation. P(n, d) fail also increases as shown in Eq. (8).
denotes the probability of n generators being available at duration d, as
defined in eq. (11), and C(n, d, t) denotes the amount of unserved load in 5.2. Fraction of expected lost critical load or fraction of unserved
outage hour d for an outage beginning at time t with n working gener­ buildings
ators, as defined in eq. (14). The probability of the microgrid surviving
outage duration d with n working generators given the outage starts at Fig. 6 shows the average expected fraction of lost load for the single
time t is denoted Sm (n, d, t). Sm (n, d, t) equals P(n, d) when unserved
critical load is zero and equals 0 when unserved critical load is positive.
4
Based on empirical data (29), a poorly maintained EDG is assumed to have a
MTTF of 61 h, an FTS of 1.65%, and an OA of 99.84%.

5
J. Marqusee et al. Applied Energy 285 (2021) 116437

Fig. 3. Probability distribution that well-maintained generators will continue to provide power as a function of run time.

Fig. 4. Probability distribution that poorly maintained generators will continue to provide power as a function of run time.

Small Campus Large campus


100% 100%

80% 80%
Probability
Probability

60% 60%

40% 40%

20% 20%

0% 0%
120
144
168
192
216
240
264
288
312
336

120
144
168
192
216
240
264
288
312
336
0
24
48
72
96

0
24
48
72
96

Outage duration (hours) Outage duration (hours)

Microgrid 90% CI Microgrid 90% CI


Building-tied EDG 90% CI Building-tied EDG 90% CI

Fig. 5. Survivability or the probability of meeting 100% the critical load requirement for outages up to 14 days (336 h) for small (left) and large (right) campuses.
The results based on the 90% confidence intervals for EDG failure metrics (FTS and MTTF) are plotted with a dotted line.

building-tied EDG and microgrid architectures for the two campus sizes. for clarity. This highlights the reliability differences between the two
90% confidence intervals for the single building-tied EDG architecture EDG architectures and shows that a microgrid architecture is expected
are also shown in Fig. 6 but were omitted fir the microgrid architecture meet nearly 100% of the critical load during a two-week outage. For the

6
J. Marqusee et al. Applied Energy 285 (2021) 116437

25.0%

20.0%

Fraction of lost Load


15.0%

10.0%

5.0%

0.0%
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336
Outage duration (hours)

1 EDG per building 90% CI


Microgrid: Small Campus Microgrid: Large Campus

Fig. 6. Expected fraction lost load for a single EDG per building and N + 1 microgrids on a small and large campus. The results based on the 90% confidence intervals
for EDG failure metrics (FTS and MTTF) are plotted with a dash-dot line for building-tied EDGs. Confidence intervals for the microgrids were not included for clarity.

single building-tied EDG architecture, the small campus is expected to common to deploy two EDGs (a backup for the backup) on the highest
lose one or two buildings during a two-week outage, and a large campus priority loads. In this scenario, high priority critical load is 25% of the
is expected to lose 10–20 buildings. total critical load and the building-tied architecture uses two EDGs per
The fraction of buildings without power is the same for a stand-alone building. The probability of being able to meet the highest priority load
EDG system for each campus because it is independent of the number of is shown in Fig. 7 below.
buildings. While the microgrid at two weeks would need to shed only an Microgrids have nearly a 100% probability of having power gener­
average of 34 kW and 10 kW of critical load on a large and small campus, ation capacity sufficient to meet the highest priority critical load for
respectively. Confidence intervals are not shown for the microgrid cases both campuses. The probability of meeting the high priority critical load
because they would not be clearly visible on the scale plotted. This is a during a two-week outage is nearly 100% for the microgrid architecture.
minute fraction of the 10 MW and 1 MW annual peak critical load for For the building-tied architecture using two EDGs per building, the
these two campuses. Additionally, this metric underscores the ability for probability decreases to 50% at the end of a two-week outage with a
the networked EDG architecture to choose which low-priority loads to confidence interval of ±20% for the large campus and 93% with a
stop serving whereas the building-tied architectures cannot. This can be confidence interval of ±5% for the small campus which has 25% of the
of great value to critical infrastructure operators during long outages critical load is contained in only two buildings.
when power triage becomes necessary. The question then emerges if one could build a backup power system
that is affordable based on building-tied systems. Fig. 8 illustrates that at
least four EDGs per building are required for a large campus to have a
5.3. Probability to meet highest priority critical loads
greater than 98% probability that power is available for the highest 25%
of priority critical loads. This would prove to be an extremely expensive
The ability to serve the highest priority critical loads is possibly the
system to procure, operate, and maintain.
most significant metric. These are loads that must be sustained to meet
Each of the three metrics clearly demonstrate for these two model
critical missions or protect health and safety.
campuses that building-tied EDG architectures cannot provide the en­
In this metric, the networking ability of the microgrid allows loads to
ergy assurance that most campuses require if they are concerned with
be shifted in real-time and high priority critical loads can be positioned
multiple-day outages. Due to their network configuration, microgrids
to be the last loads in the network to lose power. Building-tied EDG
provide a robust source of power for critical loads. However, microgrids
systems do not have this ability and power from each DER cannot be
present other susceptibilities that must be managed. Including cyber
shifted during an outage. Their only option to increase reliability is to
vulnerabilities and weaknesses of the on-campus distribution system.
increase the number of EDGs connected to an individual building. It is

100%
90%
Probability

80%
70%
60%
50%
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336
Outage duration (hours)

Microgrid Small Base Large Base


2 EDG per Building 2 EDG per Building
Fig. 7. Probability of meeting the highest priority critical load for a microgrid and with two building-tied EDGs on a small and large campus. The high priority
critical load is assumed to be 25% of the critical load.

7
J. Marqusee et al. Applied Energy 285 (2021) 116437

100%
90%

Probability
80%
70%
60%
50%
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336
Outage duration (hours)

Microgrid 1 EDG per Building 2 EDG per Building


3 EDG per Building 4 EDG per Building
Fig. 8. Probability of meeting 25% of highest priority critical load for a large campus as a function of the number of stand-alone EDGs per building as compared to
a microgrid.

5.4. Sensitivity analyses system. Similar results are found for fraction of lost load. This is due to
the load being less than the annual peak load almost the entire year.
5.4.1. Date and time of outage These results are sensitive to the assumption that an outage occurs with
These results represent the performance of a microgrid assuming an equal probability any time during the year.
outage can start with equal probability at any time during the year. The
performance of the microgrid will vary as a function of the date and time 5.4.3. Annual load profile
the outage begins. The building-tied systems are independent of load The impact of the load profile on the microgrid’s performance is
variations and thus those results are independent of seasonal load var­ illustrated below. The key load characteristic is how often the load is
iations. Fig. 9 shows the large campus variation in the probability that near the annual peak value. Multiple load profiles were explored, which
100% of the critical load can be supported for a two-week outage as a can be characterized by the distribution of the peak critical loads. In
function of the time during the year at which the outage starts. addition to the load profile used above, two other real load profiles were
This campus is located in the mid-Atlantic region and shows the used scaled to a 10-MW annual peak load and compared to the large
typical summertime peak loads due to air conditioning. The variation for campus load profile as a baseline. Fig. 11 compares their annual hourly
shorter outrage durations is smaller because the likelihood of an EDG load distributions.
failing is less and thus the impact of variable loads is smaller. The The more infrequent high-power demand hours are the more likely
variation in microgrid performance is much larger than the 90% confi­ all load will be met. Similar results are seen for fraction of load lost. The
dence intervals illustrated in Fig. 5 due to uncertainties in the EDG differences again are modest and less than the variation due to uncer­
reliability metrics. At the end of a two-week outage the average sum­ tainty in the reliability metrics of an EDG. This implies that modest
mertime probability is 90.2% as compared to an average wintertime uncertainty in the hourly load profile will not have a major impact on
performance of 98.2%. A significant difference but both are still much the predictions or reliability. These three load profiles are not dramat­
higher than a single building-tied architecture of EDGs. ically different and a highly unusual load profile that is either nearly
constant or has rare but high-power moments will show different
5.4.2. Number of EDGs in the microgrid behavior.
The results presented above are for a specific number of microgrid Fig. 12 shows the probability of meeting a 100% of critical load
EDGs. Fig. 10 shows the results for the large campus microgrid as a assuming mean reliability metrics for well-maintained EDGs.
function of number of redundant EDGs assuming mean reliability values
for well-maintained EDGs.
As expected, an increase in EDG redundancy leads to a more reliable

Fig. 9. The probability that 100% of the critical load for a large campus can be supported at two weeks into an outage as a function of the outage start time as
compared to the annualized probability.

8
J. Marqusee et al. Applied Energy 285 (2021) 116437

Fig. 10. The probability of a microgrid meeting 100% of the critical load requirement for a large campus for outages up to 14 days as function of the redundancy (N
+ x) of centralized EDGs.

10000.0
9000.0
Hourly Critical Load (kWh)

8000.0
7000.0
6000.0
5000.0
4000.0
3000.0
2000.0
0 1000 2000 3000 4000 5000 6000 7000 8000
Hours of the Year
Baseline Alternative 2 Alternative 1
Fig. 11. Critical load distribution for three load profiles for large campuses ordered by load size.

6. Conclusion power all buildings with critical loads during a two-week outage. The
expected lost load for the microgrid is trivial and this loss can be
Building with critical loads. Alternatively, diesel generators can be managed by shedding lower priority loads. Often, the greatest concern is
networked together to provide power for a microgrid. This approach is ensuring the highest priority critical loads are served. This is managed in
less common but is starting to rise in popularity. During a grid outage, stand-alone building-tied emergency diesel generator systems by con­
emergency diesel generators can fail to provide power because they are necting two emergency diesel generators per building (a backup to the
unavailable due to maintenance, fail to start and carry the load, or fail to backup). While this increases the probability of having power, it does
continuously run. When assessing the trade-offs of different campus not meet the requirements needed to support critical missions or protect
backup energy systems, one crucial criterion is the system-level reli­ health and safety. Over a two-week outage, these stand-alone emergency
ability that is dependent on outage duration. This model has examined diesel generator systems are expected to have less than a 50% proba­
the impact of finite emergency diesel generator reliability for microgrids bility of providing power to the highest priority critical loads on a large
and building-tied systems. campus. Microgrids can shed lower priority loads in real time and have a
The impact of emergency diesel generator reliability is significant for close to 100% probability to provide power to the highest priority
multiple-day grid outages, where multiple buildings house critical loads. critical loads.
It is unlikely that campuses which rely on a single stand-alone emer­ Stand-alone building-tied emergency diesel generators should not be
gency diesel generators tied to individual buildings with critical loads relied on as the sole provider for critical load backup power if multiple
will have power for all these buildings during a two-week outage. Small day outages are a concern. Emergency diesel generator microgrids
campuses are likely to lose power to 1–2 buildings and large campuses provide a robust source of power for critical loads due to their network
are likely to lose power to tens of buildings. A centralized N + 1 emer­ configuration. However, microgrids do present other susceptibilities
gency diesel generator microgrid has a high likelihood of being able to that must be addressed. These include cyber vulnerabilities and

9
J. Marqusee et al. Applied Energy 285 (2021) 116437

100%
99%
98%
97%

Probability
96%
95%
94%
93%
92%
91%
90%
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336
Outage duration (hours)
Baseline Alternative 1 Alternative 2
Fig. 12. The probability of microgrid meeting 100% the critical load requirement for outages up to 14 days for three different load profiles for large campuses.

weaknesses associated with the on-campus distribution system. Cyber reproduce the published form of this work, or allow others to do so, for
vulnerabilities can be alleviated by suitable cyber defense systems and U.S. Government purposes.
procedures. On-campus distribution system reliability varies consider­
ably with ranges from being the primary cause to rarely being the cause References
of outages. To decrease the probability of outages associated with the
on-campus distribution system, appropriate maintenance practices and [1] Fenga Wei, Jina Ming, Jina Liua, Xu Baoa, Yi Marnaya, Chris Yao, Cheng Yu,
Jiancheng. A review of microgrid development in the United States – A decade of
commonly used mitigations to certain threats can be employed. Lastly, progress on policies, demonstrations, controls, and software tools. Appl Energy
this analysis does not consider hybrid microgrid systems that combine 2018;228:1656–68.
emergency diesel generators with recurrent renewable energy genera­ [2] Stadler Michael, et al. Value streams in microgrids: a literature review. Appl Energy
2016;162:980–9.
tion and electrical storage systems. The impacts on microgrid reliability [3] Phillips Julia, et al. Onsite and Electric Power Backup Capabilites at Critcal
from renewable energy generation and electrical storage technologies Infrastructure Facilites in the United States. s.l.: Argonne; 2016. ANL/GSS-16/1.
will be covered in a future paper. [4] Gamarra Carlos, Guerrero Joseph M. Computational optimization techniques
applied to microgrids planning: a review. Renew Sustain Energy Rev 2015;48:
413–25.
CRediT authorship contribution statement [5] Hare James, et al. Fault diagnostics in smart micro-grids: a survey. Renew Sustain
Energy Rev 2016;60:1114–24.
[6] Wang Shouxiang, Li Zhixin, Lei Wu, Shahidehpour Mohammad, Li Zuyi. New
Jeffrey Marqusee: Conceptualization, Methodology, Formal anal­
metrics for assessing the reliability and economics of microgrids in distribution
ysis, Investigation, Data curation, Writing - original draft, Visualization, system. IEEE Trans Power Syst 2013;28:3.
Supervision, Funding acquisition. Sean Ericson: Conceptualization, [7] Zhoua Yutian, et al. System-level assessment of reliability and resilience provision
from microgrids. Appl Energy 2018;230:374–92.
Methodology, Software, Validation, Formal analysis, Resources, Data
[8] Mashayekh Salman, et al. A mixed integer linear programming approach for
curation, Writing - review & editing, Visualization. Don Jenket: optimal DER portfolio, sizing, and placement in multi-energy microgrids. Appl
Conceptualization, Validation, Writing - review & editing, Visualization, Energy 2017;187:154–66.
Project administration. [9] Bajwa Abdullah Akram, et al. Enhancing power system resilience leveraging
microgrids: a review. J Renewable Sustainable Energy 2019;11.
[10] 3006.8, IEEE Standard. Recommended practice for anayzing reliability data for
Declaration of Competing Interest equipment used in industrial and commercial power systems; 2018.
[11] Marqusee Jeffrey, Jenket Donald. Reliability of emergency and standby diesel
generators: impact on energy resiliency solutions. Appl Energy 2020;286.
The authors declare the following financial interests/personal re­ [12] Hanna R, Disfani VR, Kleiss Jl. Reliability evaluation for microgrids using cross-
lationships which may be considered as potential competing interests: entropy monte carlo simulation. In: IEEE international conference on probabilistic
Jeff Marqusee previously served as the Director of ESTCP, the funding methods applied to power systems (PMAPS). Boise: s.n.; 2018. p. 1–6.
[13] Hanna Ryan, et al. Improving estimates for reliability and cost in microgrid
source for this work. investment planning models. J Renewable Sustainable Energy 2019;11.
[14] Jones Richard B. How reliable is your microgrid? An insurer’s perspective on risk
Acknowledgments drivers for distributed resources. Public Utilities Fortnightly; July 2015.
[15] National Renewable Energy Laboratory. REopt: Renewable Energy Integration &
Optimization. [Online] [Cited: March 3, 2020.] https://reopt.nrel.gov/.
We wish to thank to than Dr. Brian Bush of NREL for his suggestions [16] Cutler Dylan, et al. REopt: A platform for energy system integration and
on how to treat the reliability of a system of generators. optimization. s.l.: NREL; 2017. TP-7A40-70022.
[17] HOMER LLC. HOMER Energy. [Online] [Cited: March 3, 2020.] https://www.
This work was authored by the National Renewable Energy Labo­ homerenergy.com/.
ratory, operated by Alliance for Sustainable Energy, LLC, for the U.S. [18] Lawrence Berkeley National Laboratory. Distributed Energy Resources - Customer
Department of Energy (DOE) under Contract No. DE-AC36-08GO28308. Adoption Model (DER-CAM). [Online] [Cited: March 3, 2020.] https://building
-microgrid.lbl.gov/projects/der-cam.
Support for the work was also provided by the Department of Defense’s
[19] Marnay Chris, et al. Optimal technology selection and operation of commercial
Environmental Security Technology Certification Program (ESTCP) building microgrids. IEEE Trans Power Syst 2008;23.
under [Agreement IAG-18-02080]. The views expressed in the article do [20] Anderson Kate, et al. Quantifying and monetizing renewable energy resiliency.
Sustainability 2018;10.
not necessarily represent the views of the DOE or the U.S. Government.
[21] Sandia National Laboratory. Microgrid Design Toolkit. [Online] [Cited: March 3,
The U.S. Government retains and the publisher, by accepting the article 2020.] https://www.sandia.gov/CSR/tools/mdt.html.
for publication, acknowledges that the U.S. Government retains a [22] Eddy John, Miner Nadine, Stamp Jason. Sandia’s microgrid design toolkit.
nonexclusive, paid-up, irrevocable, worldwide license to publish or Electricity J. 2017;30:62–7.

10
J. Marqusee et al. Applied Energy 285 (2021) 116437

[23] 2017 – 2018 campus Annual Energy Report. [Online] March 17, 2020. https:// [28] Fehr Stephen John. Emergency diesel-electric generator set maintenance and test
www.macalester.edu/facilities/wp-content/uploads/sites/74/2018/08/2017_20 periodicity. s.l.: Doctor of Philosophy (PhD), dissertation, Engineering
18_Campus_Energy_Rpt.pdf. Management, Old Dominion University, doi: 10.25777/q2nk-n411 https://d
[24] Department of Defense. Annual Energy Management and Resilience Report igitalcommons.odu.edu/emse_et; 2017.
(AEMRR) Fiscal Year 2018. s.l.: Department of Defense; 2019. [29] Du Y, Burnett J, Chan SM. Reliability of standby generators in Hong Kong
[25] Alba Manana, Ortega Sergio, Mario Manana. Characterization and analysis of buildings. IEEE Trans Ind Appl 2003;39.
energy demand in airports. Energies. 2017;10:119. [30] Schroeder John A. Enhanced component performance study: emergency diesel
[26] Xinda Ke, Anjie Jiang, Ning Lu. Load profile analysis and short-term building load generators 1998–2016. s.l.: INL/LTD 17-44204; April 2018.
forecast for a university campus. In: IEEE power and energy society general [31] National Fire Protection Association. NFPA 101 Life Safety Code; 2018.
meeting (PESGM). Boston: IEEE; 2016. [32] Marqusee Jeffey, Ericson Sean, Jenket Don. Emergency diesel generator reliability
[27] Thompson Christopher, Hale Peyton Jr, Arno Robert. Decanting the data: the gold and installation energy security. s.l.: National REnewable Energy Laboratory; 2020.
book presents equipment reliability refreshment. IEEE Trans Industry Appl 2012; [33] Understanding Generator Set Ratings. [Online] Caterpillar Inc. [Cited: April 7,
482. 2020.] https://www.cat.com/en_US/by-industry/electric-power-generation/Artic
les/White-papers/understanding-generator-set-ratings.html.

11

You might also like