Professional Documents
Culture Documents
Spill Prevention and Emergency Response Plan
Spill Prevention and Emergency Response Plan
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 1 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 2 OF 102
Revision Log
Date Revised Detail
Rev. (dd/mm/yyy
y) Item Page Article Description
7 Section Paragraph
11/03/2021 8&9 Hydropower Facility details updated
1.2.1
7 Section Paragraph
11/03/2021 10 Ancillary Facilities Details Updated
1.2.3
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 3 OF 102
CONTENTS
1 INTRODUCTION 7
2.1 INTRODUCTION 17
2.2 ADDITIONAL RESOURCES 21
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 4 OF 102
5 RISK ASSESSMENT 69
6 MONITORING 86
7.1 AUDITING 93
7.2 REPORTING 94
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 5 OF 102
ACRONYMS
Name Description
ADB Asian Development Bank
BOOT Build, own, operate, transfer
CECT Central Emergency Co-ordination Team
CESMP Construction Environmental and Social Management Plan
COVID-19 Coronavirus disease (caused by novel coronavirus SARS-CoV-2)
CPR Cardio-Pulmonary Resuscitation
CSR Corporate Social Responsibility
DIA Direct Impact Area
E&S Environmental & Social
EDCF Economic Development Cooperation Fund
EHS Environment, Health, and Safety
EPC Engineering, Procurement and Construction
ERT Emergency Response Team
ESIA Environmental and Social Impact Assessment
ESMP Environmental and Social Management Plan
ESS Environmental and Social safeguards
GPHEOC Guadalcanal Provincial Health Emergency Operations Centre
GRM Grievance Redress Mechanism
HEC Hyundai Engineering Corporation Limited
HSE Health, Safety, and Environmental
IA Implementation Agreement
IC Incident Commander
ICC Incident Control Centre
K-water Korea Water Resources Corporation
IFC International Finance Corporation
IMC Incident Management Centre
IMT Incident Management Team
MASL Meters above sea level
MECCDM Ministry of Environment, Climate Change and Disaster Management
MHMS Ministry of Health and Medical Services
MSDS Material Safety Data Sheet
MW Mega Watt
MMERE Ministry of Mines, Energy and Rural Electrification
NFPA National Fire Protection Association
OCG Office Command Group
OE Owner’s Engineer (Stantec New Zealand)
OSC On-Scene Commander
OSHA Occupational Safety and Health Standard
PASS Personal Alerting Safety System
PC Personal Computer
PO Project Office
POP Persistent Organic Pollutants
PPA Power Purchase Agreement
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 6 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 7 OF 102
1 INTRODUCTION
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 8 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 9 OF 102
according to Technical Proposal. The reservoir formed by the dam will extend
upstream approximately 2.6 km and will have a surface area of about 0.31 km2 at an
elevation of 175 masl. The powerhouse will be located 5.4 km downstream from the
dam on the left bank of the Tina River, and water will be diverted to the powerhouse
from the reservoir through the underground tunnel. Initially, the powerhouse will have
3 turbine/generator units, each with a capacity of 5 MW, allowing a maximum
discharge of about 18 m3/s and a minimum discharge of 2.4 m3/s. An environmental
flow of 1 m3/s will be maintained between the dam and the powerhouse tailrace, a
distance of 5.7 km
1.2.2 Access Road: Existing Road Upgrades and New Road Construction
The existing Black Post Road to Managikiki village will require upgrade/refurbishment
to accommodate the passage of construction traffic in both directions. This will involve
road widening and construction of road subgrade, road base, and roadside drainage
(including installation of culverts). Along the existing Black Post Road (up to
Managikiki), the access road will not require any forest clearing. Beyond Managikiki
Village, new permanent access roads to the powerhouse, dam and dam base, and
reservoir will be constructed.
The expected new construction or improvement of access roads for the Project is as
follows:
• Permanent existing Black Post Road (Lot 1: this is the main access road,
starting at the junction between Kukum highway and the existing Black Post gravel
road. Black Post Road is a public road and will provide access to the Project site on
most of its current alignment (approximately 13.4 km);
• Permanent access road to dam (new extension of Black Post road): the new
section of access road will follow an old timber harvesting road for about 5.6 km, and
will be extended to the South through an area of secondary and primary forests to
access the dam site on the left bank of the river (Lot 2-1 and 2-2); and
• New permanent road to dam base (approximately 0.6 km, Lot 2-3).
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 10 OF 102
Figure 1.1 – Overview of access roads leading to the powerhouse and dam site from
Kukum Highway
The Project construction activities will be supported through two main sites housing
ancillary facilities, one at the Workers Camp site just off Lot 1 Access Road at
Verakapicha, and another one located at the Project Office within the Core Land Area
and near the commencement of Lot 3-1 (Figure 1.2).
For Access Road construction, the ancillary facilities at the Workers Camp will be used.
The facilities include the following:
- Parking area
- Fuel storage
- Waste management area
- Vehicle service area
- Security
The ancillary facilities located at the Project Office near the dam site in the Core Land
Area includes similar facilities, as well as a concrete batching plant. A second concrete
batching plant will be based at the dam site itself. These facilities will service
construction of the Hydropower Facility mainly.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 11 OF 102
Figure 1 2: overview of access road and ancillary facilities servicing Tina River Hydropower Facility construction activities
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
CONSTRUCTION
ESMP FRAMEWORK SUBCONTRACTOR’S CI
(C-ESMP)
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-001 12 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 13 OF 102
PROJECT
Figure 1-3 presents a high-level master plan of the construction work schedule as of
September 2020.
This Framework will apply to all construction activities depicted in Figure 1-3. In
addition, the relevant management plans for every Project construction activity are
illustrated in Section 3 of P1 CESMP. All management plans will be prepared prior to
the start of the access road construction, and these must be approved by Lenders
before construction can commence.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 14 OF 102
PROJECT
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 15 OF 102
PROJECT
Worker’s Health and Safety Plan Refer to this plan for management of workers’
(WHSP; P8) health and safety, and HSE incident reporting
protocol.
Security Management Plan (SMP; Refer to this plan for management of security across
P7) the Project DIA and Infrastructure Area.
Traffic Management Plan (TMP; Refer to this plan for measures to follow when
P11) driving vehicles on site.
Community Health and Disease Refer to this plan for management of community
Vector Management Plan health and disease vectors , and for further details
(CHDVMP; P10) of the Project-specific COVID-19 risk assessment and
management policy (pandemic response).
Waste Management and Point Refer to this plan for management of all waste
Source Pollution Plan (WMPSPP; generated by the Project.
P12)
Air Quality Management and Dust Refer to this plan for management of air quality and
Control Plan (AQMDCP; P15) dust control during construction.
Post Construction Rehabilitation Refer to this plan for mitigation measures related to
and Replanting Plan (PCRRP; C4) cleared areas.
Construction Works Monitoring Refer to this plan for a summary of all monitoring
Plan (CWMP; M6) conducted during the construction phase.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 16 OF 102
PROJECT
Water quality monitoring plan Refer to this plan for the monitoring activities
(WQMP; M2) related to water quality.
Construction and Quality Assurance Refer to this plan for the management of
Plan (DS1) construction activities and quality assurance.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 17 OF 102
PROJECT
2.1 INTRODUCTION
Having an appropriate organizational structure in place, with all staff having defined
roles and responsibilities, is essential to ensuring the overall success of this SPERP. This
section provides details of HEC’s organizational structure with regards to onsite
delivery of the SPERP, and the various positions and responsibilities of those people in
relation to meeting its requirements, including the contractor and their sub-
contractors. All on-site managers and supervisors will be trained as medical first
responders.
Positions Responsibilities
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 18 OF 102
PROJECT
Positions Responsibilities
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 19 OF 102
PROJECT
Positions Responsibilities
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 20 OF 102
PROJECT
Positions Responsibilities
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 21 OF 102
PROJECT
Positions Responsibilities
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
TINA RIVER
PAGE
HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT 22 OF 102
PROJECT
In addition, HEC will maintain an up to date list of the support agencies and specialist
and their contact details. A copy of the most recent list will be provided to HEC’s HSE
Manager.
As part of the ongoing development and continual improvement of this SPERP, HEC
will review and update the list of Emergency Services, every six months, to ensure that
it is up to date and adequate for the construction and operation of the facility.
The RISPF Fire department will be given a site tour of the site to familiarize them with
the site layout, access points, and location of specific hazards, such as hazardous
chemical storage; additionally, the SPERP will also be provided to fire services, and
medical first responders.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 23 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 24 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 25 OF 102
The communication structure presented in Figure 3-2 is indicative at this early stage of
the project and will be updated with names and designations as positions get filled.
As per the approach applied for responding to major / urgent grievances in the
Grievance Redress Mechanism (GRM), a similarly clear pathway to escalate reporting
and communications is required for responding to crisis events (as per Section 3.1.1
below).
Keeping in view the preliminary stage prior to main construction activities, Figure-2
presents quick protocol to cater any imminent accident situation until a clearer
strategy for emergency communications is developed within the first two months of
construction. The workforce shall be required to follow protocol in case they
encounter any accident/incident scenario. Key emergency contacts as per protocol will
be provided to the workforce on the back of their identity card (printed).
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 26 OF 102
2. The first senior staff member to become aware of the event (from
either HEC or THL) is to then immediately contact the Deputy
Project Manager of the Project Office, Fred Conning.
3. Fred will then notify authorities and coordinate with the notifying
senior staff, Mr Park (Chief Technical Officer, THL) and Mr DY Kim
(HEC HSE Manager) in the first instance.
HEC will communicate with the THL project representative the details of any accident
as soon as practicable after its occurrence. THL will maintain records and make reports
concerning health, safety and welfare of persons, and damage to property, as THL
required
Refer to Annex A for List of Regulatory Authorities and Emergency Support Services.
Level 1 - Incident
The HEC HSE Manager, performing the function of the OSC, will judge and announce
whether a situation is deemed to be a Level 1 - Incident.
Level 1 incidents are singular occurrences that require an immediate response and
dedicated resources to mitigate the effects of the event. These incidents will generally
be confined to the construction site and can be managed solely by HEC’s Emergency
Response Team (ERT) led by HEC’s OSC. These events will be recorded in an Incident
Report (as shown in Annex B).
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 27 OF 102
Level 2 - Emergency
The OSC will determine whether a situation is deemed a Level 2 – Emergency, and
notify relevant parties, accordingly.
If the incident (Level 1) escalates to an emergency situation (Level 2) or some incidents
are immediately deemed to be Level 2, the OSC will mobilise the Level 2 Central
Emergency Coordination Team (CECT) which Led by the IC, will then mobilise to an off-
site Control Room.
A Level 2 Emergency is defined as any occurrence that disrupts the normal working of
HEC or affects the local population. Such emergencies will involve:
Incidents that escalate beyond the site boundary;
Incidents initiated outside the site boundary but impact on site activities
related to construction; and
Incidents occurring away from the site but involving site personnel (e.g. road
traffic accidents).
Such emergencies may require assistance from sources external to the site, including
assistance from local police or fire department as required.
Level 3 - Crisis
Level 3 (Crisis) incidents include any situation that is significant in impact and
consequences that they require strategic management support at a senior corporate
level. Typically, incidents that will impact on reputation and/or share price would be
regarded as crisis incident and would result in the mobilisation of the HEC Office
Command Group (OCG). Assistance from third parties external to HEC such as specialist
contractors and Government Agencies will be required to contain and manage the
situation.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
28 OF 102
Spillage of a large volume of hazardous Spillage of large volume of highly toxic hazardous substance
Localised spillage of a small
substance inside the project boundary, that goes beyond the project boundary and causes widespread
volume of less toxic hazardous
causing localised groundwater and surface contamination of groundwater and surface water.
ENVIRONMENT substance
water contamination Spillage of hazardous material that impacts neighbouring
Spillage of non-hazardous
Natural event impacting on Project – communities
substances inside or outside
moderate Typhoon (Category 3 or less1)
1 On the Australian Tropical Cycle Intensity Scale (very destructive winds gusting to 165-224 km/h. Some roof and structural damage, power failures likely)
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
29 OF 102
2 5.0 to 5.9 on Richter Scale - Can cause major damage to poorly constructed buildings over small regions. At most slight damage to well-designed buildings
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 30 OF 102
The above table will be updated during the Dam Detailed Design stage of the Project
following a risk assessment of potential emergency activities. Additional details on
potential examples of incidents will be added as appropriate.
Response Levels
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 31 OF 102
Level 3 – Central Emergency Coordination Team (CECT) and Office Command Group
(OCG)
The OSC (HEC HSE Manager) will judge and announce as Level 3 - Crisis.
CECT still leads Level 3 - Crisis response at the site.
The primary function of the OCG is to ensure that all resources needed to manage the
emergency are provided and to maintain communications with the CECT. It supports
CECT for liaising with external agencies, Government, stakeholders and the Media
throughout the emergency situation.
The Level 3 OCG is led by IC and will typically comprise HSE Managers, Administration
Manager, and other members as required. The OCG is supported by:
HSE Teams; and
HEC Construction Team.
The Level 3 OCG team will communicate directly with the CECT and initially the Incident
Commander. The OSC will communicate and keep the wider HEC management team
apprised of the situation.
The IC reports to the CECT about the incident and related information initially and the
CECT has direct communication with OCG. The OSC fully supports the OCG in making
decisions for the emergency response.
The overall Organisation and deployment of the Emergency Response process to be
applied to each level of emergency is documented in Figure 3-4.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
32 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 33 OF 102
Additionally, HEC will appoint, at minimum, one H&S Staff for every 50 staff (including
subcontractors) at the Site, responsible for maintaining safety and protection against
accidents. This person shall be qualified for this responsibility (i.e. holding Bachelor’s
degree in H&S or equivalent; and having minimum five years of experience supervising
emergency response procedures on construction projects), and shall have the
authority to issue instructions and take protective measures to prevent accidents.
Throughout the execution of its services, HEC will provide whatever is required by this
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 34 OF 102
person to exercise this responsibility and authority. The responsibilities of this position
have been stated in Table 2-1.
In collaboration with local health authorities, HEC will ensure that medical staff/First
Aiders, first aid facility, and ambulance (i.e., remodelled vehicle compliance with
international standards for ambulance vehicle specifications) service are available at
all times at the Site, and the necessary arrangements will be in place to ensure the
welfare and hygiene requirements and for the prevention of epidemics.
Medical staff, approved by a Health Officer, will include two nurses covering day-time
shift and a Physician will be attending the project on a monthly basis. For more details
refer to Worker’s Health and Safety Plan (WHSP; P8). During night-time and weekends,
HEC will ensure experienced and certified first-aiders are at all-time on site.
The Project (THL and/or HEC) is not responsible for the provision of primary health
care services during the project lifecycle; the Solomon Islands Ministry of Health and
Medical Services is responsible for the provision of such primary health care services
including maternity and child primary health care services, family planning services,
school primary health care services, dental services, mental primary health care
services and vaccination and immunisation services.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 35 OF 102
Mobile Radio
Contact Title Name E-mail
Phone Channel
Construction
YOUJAE BONG 716 9559 - andapapa@hec.co.kr
Manager
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 36 OF 102
Mobile Radio
Contact Title Name E-mail
Phone Channel
H&S Emergency
Jonathanbenosi700@gm
Supervisor (IC Area Jonathan 7282076 -
ail.com
1)
H&S Emergency
Supervisor (IC Area TBD - - -
2)
H&S Emergency
Supervisor (IC Area TBD - - -
3)
PARK TAE
CTO 7648941 - Park4032@gmail.com
HOON
Dervinovita69@gmail.co
HSE Officer Derwin Ovita 7387498 -
m
25256
National Referral Emergency
- -
Hospital (Honiara) room
4400
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 37 OF 102
Mobile Radio
Contact Title Name E-mail
Phone Channel
(Ambulance)
999
Hotline
Royal Solomon
24421 - -
Islands Police Force Emergency
control room
Honiara
International Fletcher Kakai 847 2739 - -
Medical Centre
HEC will develop protocols for the safe use of emergency equipment and facilities that
its workforce have control over and are likely to use in the event of an emergency.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 38 OF 102
1. Immediately vacate the area and raise the alarm by any means possible, then
report the incident by phone, radio or verbally and speak slowly/clearly and
relay the following information:
a. Nature of the Fire
b. Location of Fire
c. Name and organization
d. Contact telephone number of person reporting the incident
e. Time of Incident
2. Notification will be activated by one of the available communications means:
a. Manual Fire Alarm Point
b. ERT telephone number
c. Mobile radio
d. Automatic fire / gas detection system
3. Verbal announcement
a. The person detecting the fire must then alert personnel in the
immediate area to the fire hazard.
4. Once the fire has been extinguished HSE Department and the affected Site
manager will investigate the incident and issue a detailed written report on
the incident.
5. In the event of a fire emergency the Site HSE and Security Manager (or his
Deputy) will proceed to the scene of incident. Thus he will take the following
actions:
a. Coordinating activities of the HEC HSE personnel
b. Liaise with subcontractor on the mobilization of any equipment that
might be needed during the fire emergency
c. Verifying the entire workforce has vacated the area and is at the
muster points
d. Request additional resources
e. After the incident, make a full report.
Explosions
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 39 OF 102
Whenever there is excavation collapse and someone is trapped, time is of the essence.
The onsite supervisor at the same time of notifying the site manager of the emergency;
should assess the situation to see if there is any further risk of a cave in. If the
assessment is positive then all personnel under the supervision of the team leader
should try to dig out the casualty by hand soil type permitting. Other means may be
warranted should the soil be compacted or solid state. The site manager will inform
the emergency response team and the medic of the situation. Should the excavation
collapse and it is not known if anyone was inside the trench at the time, the supervisor
must hold a head count in order to account for all personnel in his team.
Labor Strike/Rally
HEC shall immediately inform Client of any potential workforce strike upon receiving
such information.
An open dialogue with the party of the potential strike workforce to prevent further
development into actual workforce strike shall be conducted by the Project
Management Team Representatives.
If the subject party of the potential strike is subcontractors, HEC will support the
subcontractor’s senior management and executives to persuade and/or negotiate with
the subcontractor’s labor force to avoid strike or lockouts.
In the event of striking workforce, HEC will immediately notify the nearby police
station/law enforcement agency and Client, start a precautionary measure to protect
the site workforce and property.
HEC will proactively engage in resolving the problems or issues that striking workforce
demand regardless of the striking workforce being HEC’s direct labor or not.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 40 OF 102
All subcontractors shall inform such events to HEC immediately. All subcontractors’
managers shall follow the below mentioned steps and wait for further instruction for
HEC Site Manager:
1. Immediately instructed the security guards to close and lock the main gate and
sub gate.
2. Nobody will allow leaving or entering the camp till further instruction.
3. All employees should be evacuated to the emergency muster point.
4. To inform all employees the reason for evacuation.
5. To wait for the further instruction from HEC’s Site Manager.
Vehicle Accident
In the event of a major vehicle accident, the actions listed below should be followed:
1. Incident to be reported immediately to the HSE Manager providing details of
any injuries at the scene of the accident.
2. Site Manager to activate and brief the ERT.
3. The ERT to proceed to the scene of the accident. Administer first aid to injured
person and if necessary, send to the nearest Medical facilities for further
medical treatment.
4. As soon as possible record details of the accident.
5. Try to prevent other accidents from happening by warning other vehicles of
the vehicle accident by placing accident hazard warnings in the area. Stand
clear of vehicle or roadway if there is other traffic
If an accident or illness occurs, the designated first aider or other concerned persons
should:
1. Send for assistance and if required an ambulance or other form of emergency
transport.
2. Separate the cause and the victim if possible, e.g. switch off electricity
supplies; turn off power plant before assisting the casualty.
3. Move the casualty only to prevent further injury
4. Check for pulse and breathing; giving emergency CPR, as necessary.
5. Stop any bleeding; raise the injured part and apply pressure (care must be
taken regarding rising of the injured part and applying pressure in case of
fractures).
6. Keep the victim warm and reassured.
7. Do not remove evidence.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 41 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 42 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 43 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 44 OF 102
All Personnel
On hearing the site alarm all personnel will stop work, evacuate their worksite and
immediately proceed without running, to their designated Assembly Point. All alarms
will be treated as real unless confirmed otherwise. This applies to all personnel working
outdoors on site or indoors in buildings, workshops, offices etc. Personnel will present
themselves to the HEC’s OSC/HSE Manager to enable a headcount to be reconciled.
Personnel will remain at the assembly point and await further instructions from the
HEC’s OSC/HSE Manager. Personnel will not leave the Site until instructed to do so.
Refer to Figure 3-2 for the contact list.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 45 OF 102
On-Scene Commander
On being notified of an incident the OSC will proceed to the scene to evaluate the
situation and initiate the appropriate level of response.
In the event of a major incident he will advise the IC and will instruct the general site
alarm to be activated.
CECT Members
On hearing the site general alarm or when notified by the OSC, members of the CECT
will proceed to the IMC and await further information and instructions from the IC.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 46 OF 102
A Project-specific risk assessment and policy for the management of any COVID-19
related risks to (and from) the Project, and related response, has been developed by
the Project Office and THL. This policy is attached as Annex C to the Community Health
and Disease Vector Management Plan (CHDVMP; P10) and incorporates the
requirements of SIG (including those from the Consolidated National Preparedness
and Response Plan for COVID-19, issued 12 March 2020). The policy includes an
emergency response protocol in the event of a major COVID-19 outbreak (particularly
if this occurs within the Project workforce), which is summarised here. This protocol
should be reviewed in conjunction with the Project-specific COVID-19 policy, and other
ESMPs which manage the risks associated with COVID-19 (such as the HRLMP, IMP,
SMP, and WHSP).
1 Information on COVID-19 presented in this section has been sourced from the official World Health
Organisation Health Topic online resource available at https://www.who.int/health-
topics/coronavirus#tab=tab_1 , current as of 11 September 2020.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 47 OF 102
Figure 3-5: COVID-19 Lockdown Zone previously trialled by SIG in Honiara (May
2020; yellow markers) and key Project locations (red markers)
A lockdown plan specifically to be applied to the Project DIA and camp only (i.e.
initiated by the TRHDP COVID-19 Working Party; formed with representatives from
the PO, THL, HEC, SIEA and SIG agencies) is still in development and will be finalised
by the working party. The working party will also develop the following scenario-
based response plans (which will be included here once finalised) to:
Respond to a worker being notified they are a positive case while at work,
noting workers who show symptoms or have been in close contact should
NOT attend the workplace until they receive their test results.
Identify and notify close contacts in the event of a positive case attending the
workplace during their infectious period.
Clean the workplace (or a designated area) in the event of a positive case
being identified.
Notify health officials in the event of a positive case being identified in the
workforce or workplace. Provide details of the actions taken, including a risk
assessment, and contact details of any persons who may have been in
contact (including friends, etc.).
More details regarding the working party functions are provided in the CHDVMP.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 48 OF 102
Figure 3-6.
In the event that a Project employee or community member (if identified during a
Project activity in the community) has a suspected case of COVID-19, health
authorities will be contacted. Emergency contacts relating to the COVID-19 pandemic
are provided in Table 3-3 (in addition to those already provided in Table 3-2 above).
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
49 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 50 OF 102
3.4 EVACUATION
The Emergency Response Procedure in the Annex E Emergency Reponses Plan will be
updated at the Detailed Design stage and will clearly identify the events that will lead
to an evacuation alarm.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 51 OF 102
The Emergency Response Procedure includes evacuation plans and procedures for
implementation based on local needs; and may include:
Early warning systems to ensure that adequate time is available to ensure full
and complete evacuation of areas and the complete shutdown/ securing of all
plant and equipment if the need arises during a flooding event.
Demarcation/prioritization of areas to be evacuated;
Notification procedures and evacuation instructions;
Safe routes, transport and traffic control;
Safe areas/shelters (Annex D); and
Functions and responsibilities of members of evacuation team.
3.4.1 Floods
Any precarious situation during floods will be communicated either by an alert
situation or by an alert situation followed by a warning situation. An alert situation
would indicate that although failure of flooding is not imminent, a more serious
situation could occur unless conditions improve. A warning situation would indicate
that flooding is imminent as a result of an impending failure of the dam, or also due to
a prolonged inundation event. It would normally include an order for evacuation of
delineated inundation areas. The most vulnerable/submergence area in the
downstream will be demarcated with the help of flood wave travel time analysis and
accordingly help formulate the evacuation plan for the inundation areas.
3.4.2 Earthquake
In the event of an earthquake or other natural disaster, immediate information needs
to be passed on to the local Administration Office, security forces, warning stations,
representatives of municipalities and people living near High Flood Level (HFL) mark
asked to be ready for evacuation. Necessary action also needs to be taken to shift field
staff to safer places. Thereafter, structural inspections, especially over-ground
structures such as portals and bridges need to be carried out for the assessment of any
damage and make immediate decisions for remedial measures.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 52 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 53 OF 102
3.5.1 Training
All persons visiting or working on site will receive training in the actions to be
undertaken in the event of an emergency. This training will be provided as part of the
site induction programme and will include the HEC Construction’s employees,
subcontractors, occasional visitors and persons involved in making deliveries (i.e.,
suppliers). The training content and regularity will change as work activities evolve.
The evacuation route and Assembly Point will be developed at each stage, and training
of all workforces will be undertaken as shown in Error! Reference source not found..
This training will be re-enforced by the undertaking of evacuations drills which will be
organised by the HEC HSE Manager in conjunction with the HEC Construction Manager.
All personnel with specific emergency duties will receive induction and training in the
HEC incident management and emergency response procedures. A matrix of required
training is given in Table 3-4. In addition to the training specified in Table 3-4, the IC,
all other persons designated to stand-in as IC, and members of the OCG who will have
direct contact with the media, are required to undergo media awareness training prior
to taking up any CECT duties.
Local communities will also receive brief training in respect of emergencies by May
2020. The training will include certain actions that will be taken, given the type of
emergency that arises, such as a chemical spill that covers over the community area.
All personnel will be required to complete both evacuation and other emergency
exercises and drills.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 54 OF 102
3.5.2 Communication
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 55 OF 102
structure. Documents listed in this section will be available to internal and external
auditors, including PO and Lenders, on request.
Internal Communication
Internal communication guidelines are shown in Table 3-5 and Table 3-6, respectively.
Participant
No. List Sub-
HEC
Contractor
1. Daily monitoring/inspection x x
2. Weekly monitoring/inspection x x
3. Monthly monitoring/inspection
x x
Monthly meeting
4. Biannual Internal audit x x
5. Ad-hoc meeting (per case) x x
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 56 OF 102
External Communication
External communication is defined as a communication between the Project (HEC) and
third parties such as Lenders, relevant authorities, local communities on emergency
preparedness and response issues. External communication will include, but not
limited to:
Routine communication and joint monitoring and inspection programs upon
request from Lenders and local authorities;
Urgent communication when needed to address issues of immediate threat to
the people, environment, assets and security;
Public Disclosure (refer to Grievance Redress Mechanism (GRM; P6)); and
External audits.
External communication guidelines are shown in Table 3-7 and Table 3-8, respectively.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 57 OF 102
Participant
No. List Government Sub-
HEC
/ Lenders Contractor
Monitoring/inspection upon x
1. x x
request
2. Ad-hoc meeting (per case) x x x
Quarterly external audit and x
3. x x
report
A monthly joint monitoring and inspection meeting, conducted in local languages, will
be undertaken with participants from Government and HEC to observe Project
implementation against the SPERP (Construction Phase).
Likewise, communications will also include routine daily and weekly communication to
address a particular issue or problem, or to exchange information by telephone, fax,
email, or formal letter. This also includes urgent communications when needed (e.g.
emergency response and incidents) to address issues that present an immediate threat
to people, environment, assets and security.
In addition, external communication includes communication established for practical
reasons between HEC and local authorities for site specific issues to be discussed. Any
communication of this type will immediately be reported to the HEC with date, name
of persons concerned and subject of discussion. Any external communication (via
meeting, letter, site visit, etc.) will be recorded by HEC.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 58 OF 102
regular contact with the local authorities will help to ensure that the information is
disseminated to the local population. During the construction phase, information will
be disclosed on the following subjects;
Construction activities;
Proposed Emergency Preparedness and Response Plans; and
Complaints and grievances process.
HEC HSE Manager with HEC Construction Corporate Social Responsibility (CSR) Team
will be responsible for maintaining a comprehensive database of disclosure materials
prepared and disseminated by the Project. THL will be responsible for local community
engagement.
Level 2 (Emergency)
If the situation escalates to Level 2 (Emergency), the IC under the supervision of HEC
Construction HSE Manager will contact the local emergency services as follows;
Fire: Dial 988;
Police: Dial 999; and
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 59 OF 102
Level 3 (Crisis)
If the situation escalates to Level 3 (Crisis), the OCG is responsible for communicating
with the external stakeholders. Each section of the OCG will target different
communication groups as follows;
Security Manager will contact the provincial level emergency services (Police,
Fire, Ambulance and/or the relevant national level organization (National
Disaster Management Office) to provide notification regarding the current
situation and seek responses on how each will proceed;
HEC’s Environmental and Social Supervisor will contact the environmental
regulatory agencies (Ministry of Environment, Climate Change and Disaster
Management - MECCDM) in case of any wider issues (e.g., flooding, typhoon/
tropical storm), and to provide notification regarding the current situation.
HEC will submit the incident report (once per incident) upon the request of
these agencies;
HEC’s Admin Team will contact the affected communities as applicable (i.e.
Habusi, Pachuki, Namopila, Antioch, Tina, Vuramali, Horohutu, Verakuji,
Marava, Vera’ande, Verakabikabi) to notify them and/or co-ordinate the
evacuation procedure. HEC will communicate the event to affected
communities via two-way radio, phone, walkie-talkie, hand-held transceiver,
and cell phone (if there is reception), and direct contact. HEC will submit the
incident report (per case) upon the request of these communities;
HEC Admin Team will also act as the focal point for information dissemination
to the Lenders and media. All information about the current situation will be
approved by HEC before the dissemination process; and
In all cases of Level 3 (Crisis), HEC will inform THL and the Project Office and
coordinate with MMERE and other relevant Government Ministries.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 60 OF 102
Grievance Procedure
An effective stakeholder engagement process, which includes providing access to
information on a regular basis and conducting consultation with stakeholder’s to
understand and mitigate their concerns and provide timely feedback, can substantially
help to mitigate or even prevent grievances from arising. However to provide an
opportunity to the local community and stakeholders a grievance procedure will be
developed and implemented to ensure that project related grievances can be
identified, documented, adequately resolved and monitored.
It is important that a document control system is in place to ensure that the most up-
to-date reporting is readily available, where and when required, and that copies of
previous reports are kept for future reference, throughout the life of the Project.
HEC will therefore establish a process to document and track all incident reports,
communications, and documents. HEC will use a computer database to store, track
and allow analysis of this information. All documents regarding emergency
preparedness and responses of HEC’s construction activities and derived from the
procedures described in this HEC’s SPERP (Construction Phase) will be listed, created,
and stored in appropriate files and registered. The list of documents to be filed includes
(but not limited to);
HEC’s SPERP (Construction Phase) and, where relevant, subcontractors’ site-
specific SPERP (Construction Phase) (including addendums and revised
versions);
Laws, regulations, and standards;
All documentation of communication and correspondence;
Quarterly and biannual reports including minutes of meetings;
Routine inspection reports;
Audit reports;
All documentation relevant to training materials;
Incident and accident report; and
Grievance records.
Control of Documents
A Health, Safety and Environment Document Control Register will be established and
maintained by HEC Construction’s HSE Team with the following key pieces of
information;
Document title and registration number;
Version number;
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 61 OF 102
Date of issue;
Date of review;
Responsible party; and
Location of Hard Copy (if justified).
The HEC’s SPERP (Construction Phase) and its addendum will be revised accordingly.
The reviewed date will be recorded on the document cover.
When documents are reviewed and revised, any changes will be tracked electronically
to enable readers to understand the changes.
A hard copy and electronic file of all supporting documents will be placed in the
Superseded HSE Documents File and listed on the Superseded HSE Documents
Register.
Information to be entered into the Superseded HSE Documents Register is:
Obsolete SPERP documents and file number;
Document title and registration number;
Issuance date; and
Withdrawal date.
Distribution of any documentation by electronic file will be done only using Adobe PDF
encrypted standard in order to avoid uncontrolled changes in the document.
Both on-site and off-site backup files will be kept for all documents.
It is also the responsibility of HEC and its subcontractors will also establish a
standardised documentation system and controls. All documents, maps, drawing,
procedures etc. in relation to the emergency preparedness and response aspects of
the construction of this Project will be created and filed in the construction site office
and related sites, and can be utilized any time as needed.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 62 OF 102
The spill prevention and response procedures documented in the following sections
need to be read and followed in conjunction with relevant and specific measures
additionally provided in the Waste Management and Point Source Pollution Plan
(WMPSPP; P12), Hazardous Materials Management Plan (HMMP; P13) and the Water
Supply Replacement Plan (WSRP; C7).
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 63 OF 102
b. If personnel are injured and can be removed from the area safely, do
so.
2. If it is safe to do so, stop the flow of leaking material.
a. Shut off the source of the leak if it is in a movable container/drum
reposition it to stop the flow.
b. Equipment filled with the material that is found leaking will be
removed from service as soon as possible.
c. Using a spill prevention kit, bund the area around the drum or
equipment where the leak occurs, (if safe to do so) in order to prevent
further contamination of the environment.
3. Assessment by Responsible Person
a. The foreman and/or supervisor to assess the situation quickly to
determine the need for external help.
4. Contain the spill
a. Bund and protect all open grates, sumps, manholes.
b. If the chemical has entered the drains, advise supervisor and E&S-
Supervisor immediately.
c. Dyke major spills with soil or other material.
d. Prevent spilled material entering drains, waterways or on to the
ground.
e. Where it is not possible to remove equipment from service
immediately, some means of collecting the leaking material should be
used, such as metal trays, buckets, polyethylene sheeting.
5. Protection of Personnel
a. Personnel entering the leak or spill area shall be provided with and use
appropriate protective equipment, as set out in the MSDS for that
chemical under consideration.
b. All non-essential personnel shall be kept out of the immediate leak or
spill area.
6. Report the spill.
a. Report the incident once the spill is contained or you must have a
fellow worker to report the incident to the foreman or supervisor.
b. In the event that a spill enters a watercourse (or could contaminate
groundwater) upstream or upgradient of a known water supply (as per
the WSRP; C7), an E&S Supervisor must be notified. They must then
contact the emergency contact person in the village or settlement
which uses the source, to advise them of the incident and not to
collect water. Villages should be contacted via Community Liaison
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 64 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 65 OF 102
Latex gloves;
Adequate closed footwear;
Overalls;
Safety glasses
Masks;
Disposal bags or containers; and
Hand wipes.
The hazardous substances that might require clean-up include:
Solvents;
Cement;
Glues;
Lead-Cadmium;
Plaster;
Weed killer;
Bitumen;
Epoxy resins;
Fillers;
Brick dust;
Silica dust;
Spent/Used oil or diesel;
Used/spent/expired solvents, resins and painting materials;
Medical Waste;
Wastewater from equipment/concrete washing bay;
Acid batteries;
Rubber tires;
Filters containing hazardous chemicals/oil;
Fluorescent light tubes and light bulbs;
Wastewater with inhibitors (if any) used for commissioning/hydro testing;
Bottles with refrigerant gas use for AC refilling;
Radioactive source used for welding inspection (if any); and
Batteries contain mercury/lead.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 66 OF 102
If a spill is too large to be cleaned-up using the available equipment or personnel, has
entered a storm sewer, run-off has flowed into surface waters or wetlands, or if
material is too hazardous to handle, then the ERT will be contacted immediately.
Used/contaminated spill response equipment will be sealed; the subcontractor
(approved waste vendor) in charge of the Waste Management will collect, transport
and disposed of the waste in accordance with Good International Industry Practices.
All clothing, equipment, or person(s) who have, or have potential, been exposed to
hazardous materials will be decontaminated. The decontamination area will be set-up
prior to the mitigation of the incident.
The decontamination procedures will be initiated by the OSC. To ensure that the staff
are properly trained in decontamination procedures, HEC will develop procedures and
training material based on likely scenarios detailing exposure under a reasonably
foreseeable emergency events. The following reference material will be used as a
guidance:
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 67 OF 102
MSDS;
The National Fire Protection Association (NFPA_ Hazardous Materials
Handbook (NFPA 400 series);
The chemical manufacturer; and
Other related reference materials.
Once the proper decontamination procedures are determined for the emergency
event, the OSC will designate an area to set up the decontamination process. The
equipment will consist of portable wash tubs, sprayers, heavy gauge plastic tarp and
disposable scrub brushes.
The following eight steps constitute the decontamination process for emergency
response personnel involved in the remediation of a contamination incident:
All personnel will exit the ’contaminated’ zone and will place monitoring
equipment, hand tools and other equipment in the decontamination zone. A
recovery drum and/or tarp will be set in place so all tools and equipment can
be put aside for further decontamination. All equipment and tools will be
decontaminated when work is complete. Personal protective clothing, self-
contained breathing apparatus and/or respirators worn by personnel are
excluded at this stage and will continue to be worn by personnel.
After placing equipment and tools in the recovery drum or on tarps, all persons
who have been within the ’contaminated’ zone will be washed down with the
appropriate solution, as determined by the appropriate MSDS, while wearing
all personal protective equipment. All water used in this step will be contained
in a recovery drum or decontamination pool while this process is carried out
and treated as hazardous waste at the completion of the decontamination
process.
After emergency response personnel are completely washed down, personnel
will remove their protective clothing. The protective clothing will be placed in
a recovery drum or approved bag and labelled with a tag as to their contents.
Support personnel will be required to assist personnel being decontaminated
with removing their protective clothing.
After removing protective clothing, personnel being decontaminated will
remove their self-contained breathing apparatus or respirators. The breathing
apparatus will be placed on a tarp for further decontamination.
Upon removing the personal protective equipment, the emergency response
personnel will remove any clothing that is likely to have been contaminated.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 68 OF 102
The clothing will be placed in recovery drums or approved bags and labelled
as to its contents. Separate changing rooms will be provided for both genders
during this process. Privacy screens will also be provided for individuals with
religious beliefs that prohibit nudity in public or in front of others.
Emergency response personnel will shower thoroughly if it has been
determined that their PPE has failed to protect the user.
Emergency response personnel and persons that were in the hot zone and
warm zone will receive a post-medical evaluation by a qualified individual if
overexposure or injury occurs.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 69 OF 102
5 RISK ASSESSMENT
During project execution, the principal objectives of risk management are to develop
and monitor the implementation and effectiveness of risk treatments and to identify
and evaluate changes in the risk profile of the project.
The following Four Step risk management approach will be implemented on the
project:
Identifying hazards in the workplace involves finding things and situations that could
potentially cause harm to people. Hazards generally arise from the following aspects
of work and their interaction:
Typical example for hazards the hazards associated with the project include electricity,
manual tasks, machinery and equipment, hazardous chemicals, extreme temperatures,
noise, radiation and biological (micro-organisms).
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 70 OF 102
what chemicals are around and what they are used for, what safe or unsafe work
practices exist as well as the general state of housekeeping.
Does the work environment enable workers to carry out work without risks to
health and safety (for example, space for unobstructed movement, adequate
ventilation, lighting)?
How is work performed, including the physical, mental and emotional demands
of the tasks and activities?
How suitable are the tools and equipment for the task and how well are they
maintained?
How do workers, managers, supervisors and others interact and how are
inappropriate behaviours or conflicts dealt with?
Have any changes occurred in the workplace which may affect health and
safety?
Hazards are not always obvious. Some hazards can affect health over a long period of
time or may result in stress (such as bullying) or fatigue (such as shiftwork). Also think
about hazards that you may bring into your workplace with new, used or hired goods
(for example, worn insulation on a hired welding set). As you walk around, you may
spot straightforward problems and action should be taken on these immediately, for
example cleaning up a spill. If you find a situation where there is immediate or
significant danger to people, move those persons to a safer location first and attend to
the hazard urgently. Follow up on why the situation occurred to identify
additional hazards and risks. Make a list of the hazards you find, including the ones you
know are already being dealt with, to ensure that nothing is missed. This list can be
kept and updated next time you do an inspection. You may use a checklist designed to
suit your workplace to help you find and make a note of hazards.
The best chance to find ways to eliminate hazards and minimise risks is during the
design phase. Effective design of ‘good work’ considers the work tasks, work systems,
the physical working environment, and the workers and others in the workplace. Safe
design of buildings, structures, equipment and vehicles accounts for
the hazards and risks present at all stages of the product’s lifecycle.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 71 OF 102
Ask your workers about any health and safety problems they have encountered in
doing their work and any near misses or incidents that have not been reported.
Worker surveys may also be undertaken to obtain information about matters such as
workplace bullying, as well as muscular aches and pains that can signal
potential hazards.
Talk with your suppliers or those commissioning your services to understand each
other’s needs and identify any hazards and risks. For example, hazards may relate to
frequent pressure to deliver services in very tight timeframes or to delay service
delivery for long periods which reduce workers’ opportunities to rest.
Other hazards may relate to packaging products in ways that increase workers’ risks of
musculoskeletal injury or exposure to hazardous chemicals. When people within a
supply chain act cooperatively they can exert greater influence on health and safety
than when acting alone.
Information and advice about hazards and risks relevant to particular industries and
types of work is available from regulators, industry associations, unions, technical
specialists and safety consultants. Manufacturers and suppliers can also provide
information about hazards and safety precautions for specific substances (safety data
sheets), plant or processes (instruction manuals). Analyse your records of health
monitoring, workplace incidents, near misses, worker complaints, sick leave and the
results of any inspections and investigations to identify hazards. If someone has been
harmed doing a task, then a hazard exists that could hurt someone else. These
incidents need to be investigated to find the hazard that caused the injury or illness.
A risk assessment was conducted to identify the project activities which might present
a hazard or risk relating to spill hazards and emergencies, and assess the potential
impacts which may arise. A range of mitigation measures and management
approaches were then identified, to achieve a reduction in the initial perceived risk.
The objective in implementing these measures and approaches is to reduce the level
of residual risk to a lower (and acceptable) level.
The following tasks were undertaken to analyse and evaluate risks and identify
potential impacts:
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 72 OF 102
The initial risks identified for each activity; associated impacts, and residual risks (after
implementation of mitigation measures) have been captured in a ‘live’ risk register,
which is maintained on ProjectSpace, the online document management system
administered by HEC for the Project. The activities and impacts presented in ESMPs
are consistent with those listed in the register. The register will be used by HEC, THL
and the OE as a tool to monitor the effectiveness of mitigation measures in reducing
risk across the Project, and will be regularly reviewed and updated as the Project
progresses. This will include incorporating any new risks and impacts identified as a
result of the process described in Section 5.1 above.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 73 OF 102
Likelihood Consequences
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 74 OF 102
In the cases where risk level was assessed as a Moderate or High – reduce
risk to Low;
In the cases where risk level was assessed as Low – ensure risk level does
not increase; and
In the cases where risk level was assessed as Extreme – modify the project
to avoid critical risk activities.
The impacts associated with construction of the Project, and particularly in relation to
the scope of this Plan, are included in Table 5-2, along with assigned mitigation
measures / management approaches. The table also outlines the monitoring actions
that will be applied to continually evaluate the effectiveness of these measures and
approaches for the duration of construction.
The mitigation / management procedures listed in Table 5-2 and described further in
various sections of this plan provide the approach to managing emergency events
during the construction phase, and preventing and responding to spills.
Summaries of spill response and emergency response measures are provided below
in Table 5-5 and Table 5-6 respectively, and responses to pandemic events are
outlined in Table 5-3 and Table 5-4.
HEC and Subcontractors are committed to implementing the identified mitigation /
management procedures in order to not cause exceedance of the applicable
standards, and to avoid impacts that can contribute to injuries or casualties of the
labours under the supervision of HEC.
The mitigation / management procedures were identified within the Environmental
and Social Impact Assessment (ESIA) as being appropriate for the environmental
impacts resulting from the anticipated construction activities. The monitoring and
reporting activities will be revised after Detailed Design completion.
Any changes to the SPERP (relating to emergency response and crisis management)
will be consulted on with THL, the PO and the Local relevant authorities.
Site specific emergency response procedures that are to be developed for this Project
include:
Evacuation Procedure;
Fire/smoke Procedure;
Personal Injury Procedure;
Personal Threat Procedure;
Bomb Threat Procedure;
Suspicious mail or package Procedure;
Radioisotope or Biohazard Spill Procedure;
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 75 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY RESPONSE PLAN SUBCONTRACTOR’S CI
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
76 OF 102
2. Pandemic / widespread health emergency. Develop procedures for coordinating with local authorities and complying with national HEC (prior to Conduct monitoring weekly and in the event of an incident as per HEC HSE Manager,
Prolonged illness, fatalities. Loss of workers’ productivity (and direction (e.g. project-specific COVID-19 management policy, now included in CHDVMP, construction) Table 6-1 of this SPERP. Subcontractors (weekly)
delays to delivery) due to sick leave. P10 as Annex C)
HEC HSE Manager, HEC
E.g. Impacts of global COVID-19 pandemic (2020 - ) on workforce Weekly inspection and check of PPE inventory for outbreaks (e.g. Doctor (Dr Pedical),
and Guadalcanal population; outbreak of disease originating masks, gloves, hand sanitiser supply) weekly
from foreign workers arriving to work on Project; outbreak of
gastrointestinal illness at camp; outbreak in community (e.g.
dengue fever)
3. Natural disaster (e.g. earthquake) Prepare an evacuation strategy / plan in the event of a major earthquake. HEC (prior to Report at the time of every event HEC HSE Manager, every
construction) Events and responses reported in Quarterly Safeguards report event
Run earthquake drills to familiarise Project workforce with evacuation HEC Keep record of drills including date, participants and HEC HSE Manager, every
procedures. Subcontractors outcomes/observations drill (at least quarterly)
4. Typhoons, severe weather – causing damage to property and HEC will continuously monitor National and Local meteorological data and issue HEC At the time of every event (as per Table 6-1 of this SPERP)\ HEC HSE Manager, every
natural environment, restricting access to and within Project site, timely warning to all personnel of adverse weather and issue instructions to stop event
endangering lives work as necessary.
In the event of an impending flash flood, the general emergency call will be given HEC Events and responses reported in Quarterly Safeguards report HEC Construction
through site communication systems and all personnel will stop work, make their Subcontractors Manager, HEC HSE
worksites safe and proceed to their assembly points. Manager, THL E&S
Install dike with elevation. HEC Manager, quarterly
Regularly inspect the drainage system. Subcontractors
The Overall Project Director, HEC Construction HSE Team and Sub-Contractor HSE HEC
Team will meet and discuss all options available to decide on the best
management practices for the control of run-off.
Implement Emergency Response Plan which will be the standard procedure for
site and/or process shutdown in the event of a severe weather event (refer to HEC
Annex E for more details of the emergency response plan and shelters/safe Subcontractors
areas).
Spills to the natural environment; accidental exposure of workers or public due to uncontrolled release of hazardous substance
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY RESPONSE PLAN SUBCONTRACTOR’S CI
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
77 OF 102
Subcontractors
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY RESPONSE PLAN SUBCONTRACTOR’S CI
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
78 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
79 OF 102
Additional mitigation measures and management strategies to be implemented firstly to prepare for a pandemic and secondly in response to one are
provided in a series of tables below.
1 Plan co- Ensure Planning co-ordinator and deputy are identified and operational. HEC Project Manager (for HEC
ordination protocols)
Note: The PO Deputy Project Manager
is responsible for implementing the
Project-wide COVID-19 policy, which
HEC supports
2 Plan Test plan during a Business Continuity exercise involving key stakeholders. HEC Project Manager
Effectiveness
3 Suppliers Ensure adequate stocks of materials and equipment such as PPE are procured in accordance with HEC Procurement Manager
relevant Project-wide plans/policies (e.g., for COVID-19 pandemic, the Project-specific COVID-19
management policy applies) and the Workers’ Health and Safety Plan (P8).
4 Secure necessary critical supplies following stock review. HEC Procurement Manager
5 Maintain contact with Sub-contractors to determine availability of resources. Make preparations HEC Procurement Manager
to bring in additional resources at short notice.
6 Medical Issue note to HEC and Sub-contractors’ personnel to encourage seasonal vaccination (if a vaccine HEC HSE Manager
is available).
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
80 OF 102
7 Ensure all pandemic supplies (e.g., face masks) and other communicable diseases protection are HEC HSE Manager
available and of sufficient quantity.
8 Communications Make sure enough trained staff are available to maintain communications throughout the HEC Project Manager
Project.
9 IT Systems Carry out survey to establish which personnel will be able to work from home during a pandemic HEC Project Manager
and outbreak of communicable diseases and what systems and equipment would be required.
10 Human Develop process to record and monitor sick and infected personnel as well as their dependants. HEC HR Manager (consult with Project
Resources (HR) doctor)
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
81 OF 102
1 Operations Convene regular meetings of the Pandemic/ Outbreak Contingency Team HEC Project Manager
(P/OCT) to monitor and oversee the situation. This is known as the TRHDP
COVID-19 Working Party for the 2020 – ongoing COVID-19 pandemic.
2 Hygiene Recruit additional cleaning staff for offices, workers’ camp and other HEC HR Manager
communal places.
3 Issue posters and other material to remind all personnel to wash hands HEC HSE Manager
frequently.
4 Limit face-to-face meetings to a minimum. HEC Project Manager
5 PPE Issue face masks and any other required PPE to all personnel. Make alcohol- HEC HSE Manager
based hand sanitiser (60-80% alcohol content) widely available.
6 People Consider option of recalling foreign travellers. HEC HR Manager
7 Implement tracking system for infection status of employees. HEC HR Manager
8 Explore flexible working arrangements to ensure essential work is covered. HEC HR Manager
9 Alert labour providers of potential need for replacement staff. HEC HR Manager
10 Communication Maintain on-going and proactive communications with Public Health HEC HSE Manager
Authorities.
11 Ensure workforce is kept up to date with infection status and HEC actions to HEC HSE Manager
deal with a pandemic.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
82 OF 102
Table 5.5 - The Actions to be taken during the Pandemic/ Outbreak Capacity Phase
1 Operations Continue monitoring situation and respond in line with advice from Employer HEC Project Manager
and the Authorities.
2 Hygiene Maintain continuous cleaning of work places and communal areas. HEC Project Manager
3 Cancel all meetings, use tele-conferencing. HEC Project Manager
4 Cancel all visitors to site. HEC Project Manager
5 Medical Manage and ensure appropriate distribution of medical and food/water supplies. HEC Occupational Health Provider
6 People Essential personnel only on site. Office based staff to stay away from site. HEC Project Manager
7 Monitor workforce numbers and infection status in all areas and mobilise HEC HR Manager
replacement workers when necessary.
8 Use whatever flexible working arrangements are needed to ensure essential HEC HR Manager
work is covered.
9 Communication Maintain communication with Employer and the Public Health Authorities. HEC Project Manager
10 Continue to update workforce on the developing situation. HEC HSE Manager
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
83 OF 102
Description of Measure
Spill response procedures
In the event of a spill of any hazardous material, work will be ceased in the immediate vicinity and the area will be cleared of all construction personnel except those
involved in the clean-up activities, if necessary.
In the event of a spill of any hazardous material, the following response hierarchy will apply and will be used in the development of the detailed emergency response
procedures:
First priority is to seek medical attention for any injured personnel
Second priority is to prevent further injury to personnel
Third priority is to prevent environmental damage
Fourth priority is to clean-up spill
Fifth priority is to remediate area of spill
Sixth priority is to complete reporting requirements
Seventh priority is to conduct post-incident review and sharing lesson learned using office dashboard, e-mail and project space.
For spills of hazardous materials, appropriate treatment and disposal methods for the known range of hazardous materials will be applied by trained personnel.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
84 OF 102
Description of Measure
Emergency contact details
At each construction site, information on emergency response procedures, emergency contact numbers and communication and reporting procedures (to be
implemented in case of an emergency situation) will be clearly displayed.
Training of personnel
At each construction site where hazardous materials are used and where there exists a potential for a spill, there will be at least two employees on-site at all times
who are trained in appropriate emergency response procedures and communication and reporting procedures to be implemented in case of an incident.
All construction personnel will be trained in basic emergency response procedures including communication and reporting procedures to be implemented in case of
an emergency situation.
Emergency incident communication processes
In the event of a personal emergency implement the Emergency Response Procedure (Annex C. All staff will be made aware of the procedure during Project induction,
and through subsequent safety briefings.
In the event of an accidental release or spill of a hazardous material, the following communication processes will be implemented:
i. Environmental and Social Supervisor immediately notifies Health and Safety Manager and the Project Manager
ii. Health and Safety Manager immediately notifies emergency response team
iii. Health and Safety Manager immediately notifies external emergency authorities (if required)
Communication will initially be verbal, with written communication as soon as practical.
The communication processes will include the following information in relation to accidental releases or spills:
i. Location of spill
ii. Nature of material spilt
iii. Amount of material spilt
iv. Clean-up processes to be implemented
v. Any injuries to personnel
vi. Need for emergency or external assistant
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
85 OF 102
Description of Measure
vii. Any safety/evacuation requirements to be implemented on the construction site
viii. Notification and evacuation of communities that could be affected by spills
Within 48 hours of the completion of a spill clean-up, a report will be submitted to the Owner. The report will be used to identify any required corrective or preventive
actions and emergency response procedures and training programs will be modified accordingly.
General Emergency
First aid teams will be specifically trained and assigned in groups of two to three persons to the different sites.
First aid stations will be provided and will be appropriately equipped.
First aid kits will be readily accessible by workers.
A doctor will be reached when an accident occurs.
Additionally, the local doctor, hired by HEC, will come on site once a month. Two nurses will take shifts to provide medical coverage during working hours in the clinic
located in the workers camp.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION
AND EMERGENCY SUBCONTRACTOR’S CI
RESPONSE PLAN
HEC-CDSB-CESMP- PAGE
TINA RIVER HYDROPOWER REV. 7
DEVELOPMENT PROJECT PPP-014 86 OF 102
6 MONITORING
The spill prevention and emergency response plan has been developed to track the
effectiveness of the mitigation measures during the construction phase.
HEC will undertake additional monitoring if the monitoring program records shows
significant increase of property damages, injury and fatality of the workers.
Immediate and real time information on emergencies and emergency response, for
Project management and other stakeholders will be the responsibility of the
emergency supervisor.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT
WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
87 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
88 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
89 OF 102
Impacts from chemical/oil At the construction site, work Incident reporting; Every week during the HEC HSE Manager/ Quarterly and in
spill camps; and Number of construction phase. Sub-contractors the event of an
Along the transportation emergencies; and incident
routes Soil and groundwater
analysis result at the
spill-contaminated site.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
90 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
91 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
92 OF 102
Impacts from food poisoning At the construction site, and Outbreak Review Every week during the HEC HSE Manager/ Quarterly and in
of workers work camps; reporting; construction phase. Sub-contractors the event of an
Number of the sick incident
labours; and
Outbreak protection
equipment inspection
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 93 OF 102
An Auditing and Reporting Program is required to ensure that the mitigation / management measures
are appropriate to prevent spills and emergency planning.
HEC’s onsite HSE Officer will set and monitor Key Performance Indicators such as:
7.1 AUDITING
HEC will be subject to internal and external audits. The internal audits will be conducted by the HEC
Headquarter on the onsite team. Internal examinations performed by the onsite staff are referred as
inspections. The external audits will be conducted by an THL E&S Manager, PO E&S Monitoring team,
and THL Owner’s Engineer (OE).
The detailed structure and content of auditing process is presented in the Construction Environmental
Social Management Plan (CESMP; P1). The below Table 7-1 presents a summary of the process.
HEC Headquarter HSE Team HEC onsite team Every six months
External and Internal auditors shall notify by email the HEC Project Management Team (Project
Manager, Construction Manager and HSE Manager) about upcoming audit events. This will provide a
mechanism to communicate the schedule, activities and objectives of the audits. If urgent, the Project
Site may be notified via phone or fax.
The audit process involves reviewing onsite activities to assess compliance with the management
plans, national requirements, good industry practice and HEC internal standards. The auditor will
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 94 OF 102
review all records of previous audits and evaluate historic compliance and the use of appropriate
corrective actions.
Findings from the audit will be summarised in an audit report. A copy of the resulting audit report is
to be made available upon request for reference and, where necessary, implementation of any
identified corrective actions.
The Key Performance Indicators to be considered when auditing this management plan are:
All reports are to be maintained at the project site for the entire construction period.
7.2 REPORTING
Internally, the reporting hierarchy proceeds as follows: Subcontractor, Emergency Supervisor, HSE or
Construction Manager, Project manager. Externally, HEC reports directly to THL who in turn reports
to PO, lenders and relevant authorities.
In case of accident, the Emergency Supervisor is in charge to record all accidents immediately after
they occur and collect reports from appointed personnel or subcontractors that witnessed an
accident. The Emergency Supervisor will immediately report to the HSE Manager which in turn will
communicate the event to the Project Manager.
The scope of the reporting program to be undertaken by HEC is shown in Table 7-2
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 95 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 96 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND EMERGENCY
SUBCONTRACTOR’S CI
RESPONSE PLAN
PAGE
TINA RIVER HYDROPOWER DEVELOPMENT PROJECT HEC-CDSB-CESMP-PPP-014 REV. 7
97 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 98 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 99 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 100 OF 102
First aid treatment procedures for minor & major worker injuries
Any person(s) who discovers the occurrence of the injured will raise the alarm by shouting “Help!
Help! Help!”.
The person(s) will inform the Project key personnel and any of the Project ERT members
immediately.
If the situation does not pose any danger, the person(s) will remain at the emergency location
and provide assistance such as helping the injured, warning unknowing personnel to stay away
from the affected areas, etc. until the Project ERT arrives.
Upon reaching the incident location, the Project ERT will take over the control of the area. The
Project ERT will cordon off the affected area and instruct all personnel to keep away from the
danger locations, except for project ERT members who are conducting rescue and/or evacuation
of the personnel.
The Project ERT will call the HSE Manager and report the status of the injured worker.
For first aid treatment case, the first-aid team will administer first-aid treatment to the injured or
the injured walk to the first aid treatment room for basic treatment.
For minor injury case such as the injured is still conscious and is able to move with assistance, a
transport is arranged to send the injured to nearest clinic/ hospital and staff/ or subcontractor
supervisor will accompany the injured.
For severe injury case, such as injuries sustained are critical and Injured is either unconscious or
is not able to move, the Project Manager or HSE Manager will give instructions to activate Project
Security to lead Responders to the location.
Project Manager will inform Top Management / Owner Management and provide situation
verbally report on regular interval if the severe injury is occurred.
Follow-up with Incident Reporting and Investigation when the injury is reportable case. The
incident report will be sent to the relevant parties.
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 101 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
SPILL PREVENTION AND
EMERGENCY RESPONSE SUBCONTRACTOR’S CI
PLAN
PAGE
TINA RIVER HYDROPOWER HEC-CDSB-CESMP-PPP-014 REV. 7
DEVELOPMENT PROJECT 102 OF 102
CONFIDENTIAL: THIS DOCUMENT IS CONFIDENTIAL AND MUST NOT BE COPIED OR REPRODUCED EXCEPT WITH THE EXPRESS
PERMISSION OF HYUNDAI ENGINEERING CO., LTD.
HEAT STRESS SHELTER & ASSEMBLY POINT(LOT1&2&3)
ly
on
n
io
ct
tru
Honiara Port~ Int’l AirPort
ns
co
ad
ro
CAMP AREA
ss
ce
ac
1
ot
rL
fo
* AS per a construction & manpower mobilization schedule, shelter and assembly location will be changed.
HEAT STRESS SHELTER & ASSEMBLY POINT(CAMP)
ly
on
n
io
ct
tru
ns
co
ad
ro
ss
ce
ac
1
ot
rL
fo
d
o ve
pr
Ap
ly
on
n
io
ct
tru
ns
co
ad
ro
ss
ce
ac
1
ot
rL
fo
d
o ve
pr
Ap
ly
on
n
io
ct
tru
ns
co
ad
ro
ss
ce
ac
1
ot
rL
fo
d
o ve
pr
Ap
ns
tru
ct
io
n
on
ly
ly
on
n
io
ct
tru
ns
1. INTRODUCTION
co
ad
2. EMERGENCY RESPONSE PLAN
ro
ss
- Overall
ce
- Scenario 1 : Accident
- Scenario 2 : Security and Medical
ac
1
3.
ot
OTHERS
rL
fo
4. REFERENCE DATA
d
ove
pr
Ap
1. INTRODUCTION
ly
■ SITE LAYOUT
on
n
Air port
io
Assembly Point
ct
First Gathering place
tru
Escape Route Exist Road
ns
L= 7.3Km
co
Black point
Junction
ad
Access Road 0Km+000
Lot 2 (L=6.2KM,B=4.5M)
ro
Lot 1 (L=13.4KM,B=7M)
ss
Core boundary
Camp Site
Office Site L=3.3km
ce
5Km+200 3Km+300
L=14.4km
ac
Dam Site BP(2)
BP& Office site
2Km+500 1 Manakiki Village
ot
13Km+400 9Km+400
7Km+400
rL
Powerhouse
fo
d
o ve
Aggregate Site
pr
Ap
3
1. INTRODUCTION
ly
■ SCOPE
on
On this manual described to training on relevant manpower for the dangerous status that could be affect on Tiny Hydro project
such as the following any type of emergency, natural disaster, Etc.
n
io
■ OBJECTIVE
ct
The goal on this manual is to minimize any damage or loss to this construction project especially suspension construction by
tru
managing to Manpower with safety action and set of guidelines for emergency situation in any case of accident.
ns
■ EMERGENCY SITUATION CASE
co
ad
Emergency Case 4
ro
Emergency Case 1
Emergency medical services is not available or
ss
Safety accident at Workplace doesn't have enough facility on the area.
ce
Emergency Case 2
ac
Emergency Case 5
Industrial accident can be deeply affected to the
public such as Explosion, Exposure hazardous1 Occurred Terrorism, Protests, and etc. inside of the
substance, country.
ot
rL
Force Majeure situation such as earthquake, Flood, Construction project not able to continue due to
d
Typhoon, Tsunami, and disease Political and Religion conflict, and Etc.
o ve
pr
SCENARIO 1 SCENARIO 2
Ap
4
2. EMERGENCY RESPONSE (OVERALL)
ly
■ ROLE & RESPONSIBILITIES
on
SITE MANAGER
n
io
1. Establish Emergency prevention plan especially Industrial and Environment Accident to public.
ct
2. Managing total manpower especially sustain safety condition to all manpower.
tru
3. Supervise Emergency action plan and training to all manpower properly.
ns
4. Make Final Decision in any kind of emergency situation.
co
ad
SAFETY MANAGER
ro
ss
1. Make actual emergency plan, and keeping update on safety information.
2. Monitoring Safety status and Report to Site manager.
ce
3. Review all safety data and execute approval.
ac
1
ot
ADMIN MANAGER
rL
5
2. EMERGENCY RESPONSE (OVERALL)
ly
■ ROLE & RESPONSIBILITIES
on
Role Duty.1 Duty.2
n
io
Manage overall current status Manage overall current status
Site Manager
ct
Decision level of emergency status Decision level of emergency status
tru
Planning for emergency situation and keep it update Planning for emergency situation and keep it update
ns
Monitoring to plan's action Monitoring to plan's action
HSE Team
Review and control data and report Review and control data and report
co
Handling Administration issue.(Ask Admin Dept.) Handling Administration issue.(Ask Admin Dept.)
ad
ro
Keep update current issue and notice it to all
Control to manpower depend on commander's order
Report current issue to HQ and follow their instruct.
Keep update current situation and notice it to all
ss
Admin Team Control Manpower
Establishment cooperation system for national
Arrange security service(from Police, Military officer)
ce
organizations agency
Analysis Current situation
ac
1 Research Emergency zone
Rescue manpower Planning beget to be project withdrawal.
ot
Responsibility main Material & Equipment Manage document to be project withdrawal
Construction & Admin
Transfer patients to hospital Secure Emergency Food/medicine, communication
rL
Team Support Site work Check Transformation plan such as Fuel, Etc
fo
Construction team
Be Communicator to relevant organizations Control Site and protect goods
pr
Site situation handling Control Manpower
Ap
6
2. EMERGENCY RESPONSE (OVERALL)
ly
■ ORGANIZATION CHART
on
n
io
ct
tru
ns
co
ad
ro
ss
ce
ac
1
ot
rL
fo
d
ove
pr
Ap
7
2. EMERGENCY RESPONSE (OVERALL)
ly
■ ORGANIZATION CHART
on
GENERAL CONDUCTOR
n
io
Site Manager
ct
Chungryul. Ha
tru
+677-7119096
HSE TEAM Admin Team
ns
Daeyong Kim M
Jungmin. Kim
co
M +677-7229259
+677-7411755
Soonyeon Kwon
ad
Jonathan S
S +677-7169565
+677-7382076
ro
ss
ce
Admin Team & Construction Construction team Construction & Admin Team
ac
Youngmok. Kim Jaebong. You Hyeongsik park
M M M
+677-7440589 1 +677-7169559 +677-7411752
ot
Geomryeol. Kwak Youngdae. Kim
S S Minhyeok Back
rL
+677-7411754 +677-7440595 S
+677-7440576
Il ji Shin Jinho. Kim
fo
S S Kunsup Song
+677-7411757 +677-7118715 S
+677-7342868
d
S S Taein. Hur
+677-7440585 +677-7198285 S
o
+677-7440578
pr
8
2. EMERGENCY RESPONSE (SCENARIO 1: ACCIDENT OCCURED)
ly
■ EMERGENCY SITUATION LEVEL
on
Division Public (General Accident) Natural Disaster Report Remark
n
io
ct
LEVEL 1 ㆍNormal Situation ㆍNormal Situation - -
tru
ns
HQ General
ㆍLight accident Manager
co
LEVEL 2 ㆍApply mediation to local organization ㆍNatural Disaster forecast -
ㆍExternal problem of construction site. notice on media HQ HSE
ad
Manager
ro
HQ General
ㆍLTI(Less then Three Months) Manager
ss
LEVEL 3 ㆍApply mediation to central organization ㆍNatural Accident occurred -
ce
ㆍA fine for Environment and Industrial accident HQ HSE
Manager
ac
1
ot
ㆍOccurred LTI(More then Three Months) HQ
LEVEL 4 ㆍSuspension construction work -
ㆍProperty Damage (More then 34,000SBD) Representative
rL
fo
Standard
ve
ㆍOccurred Riot
:Dead
ㆍMore then 2cases LTI(More then Three Months)
:Injure more then three
o
34,000SBD)
:Media report(a disaster)
9
2. EMERGENCY RESPONSE (SCENARIO 1: ACCIDENT OCCURED)
ly
■ WORK FLOW
on
Division In Charge Actions Remark
n
io
Occurred Accident First discoverer The first discoverer should report to Safety team. Ex) Fire, Explosion,
ct
※ Content 1) The Place Natural Disaster
tru
2) Current situation
3) The discoverer's name and position
ns
co
Report Accident Make final decision depend on current situation
Site Manager
※ Consider 1) Current situation and additional issue
ad
2) Suspension work
3) Make plan to prevention
ro
Recognize current 4) Review similar case of accident
situation - Make decision suspension work(Work permit is not affect)
ss
ce
Safety Team - Notice Current Situation to all manpower
- Contact Related organization(Fire station, Hospital, Etc.) Refer to Emergency
ac
- Report HQ(any method) contact no. on next
- 1Make alarm(The sound type should be different depend pages.
Notice Current
Situation on emergency level)
ot
rL
10
2. EMERGENCY RESPONSE (SCENARIO 1: ACCIDENT OCCURED)
ly
■ WORK FLOW CHART
on
Accident
n
io
ct
First Discoverer
tru
ns
PM HQ Manager
Lev. 1 Aware
co
Lev. 5
More then
situation
ad
Lev. 2~5 Lev. 2~5 HQ Admin
HQ Financial Representative
ro
More thenLev.3 (Report) HQ Planning
More then Lev. 4
THL/Organization Manpower
ss
HQ HSE
ce
HQ HSE Team MANAGER
ac
Injured
First Action Occurred
1 Hyundai
Only Needed Only needed Construction
ot
ISOS
rL
+82-2-3140-1700 HQ HEC
Planning Team(1)
d
Situation ABNORMAL
ve
Monitoring
※ Serious Accident
o
urgently.
- -National
Close Transfer
Ap
- -International
- -Mother Country
11
2. EMERGENCY RESPONSE (SCENARIO 2: OVERSEAS/EMERGENCY)
ly
■ SECURITY ALERT LEVEL
on
Division Current social atmosphere Response Report
n
io
LEVEL 1
ㆍStable ㆍMake planning for prevention Accident
ct
S t a b le
ㆍLawful ㆍEducate and Training
tru
GREEN
ns
[Site organization] [HQ organization]
LEVEL 2 ㆍSocial Unstable
- Training and security action - Monitoring and instruct to site
co
Atten ㆍTerrorism, ㆍHQ G/manager
t io n - Daily report for current situation
ㆍFalse Rumors ㆍDaily report
- Research disease information and
ad
BLUE ㆍConfirmed disease case
get quarantine
ro
[Site organization] [HQ organization] ㆍHQ G/manger
LEVEL 3 ㆍOccurred Terror and Injured - Increase security Level and status - Monitoring and instruct to site ㆍShare Information
ss
Cauti ㆍImprove Security Level - Report current situation every - Keep in touch with other local corporation. ㆍReport Current
on ㆍAnti Foreigner through Media, Internet moment
ce
Issues any time
YELLOW ㆍIncreased sick patient - Keep watch Patient and get
ac
quarantine
[Site organization]
1 [HQ organization]
- Make curfew(No outside going) - Set emergency organization
LEVEL 4 ㆍTerrorism community active ㆍRepresentative
- Suspension project(temporally) - Establishment of cooperation system
ot
A le r t
ㆍTerror occurred frequently. ㆍShare information
- Use hospital and get quarantine for government agencies
ㆍKidnap Occurred ㆍReport Current
rL
- Instruct to site
d
12
2. EMERGENCY RESPONSE (SCENARIO 2: OVERSEAS/EMERGENCY)
ly
■ WORK FLOW
on
Division In charge Action Remark
n
io
Keep Close Current Site Manager - Set Site Emergency Organization (Level 4) Make sure their
ct
- Increase security numbers and instruct curfew to manpower own duty
Situation
tru
Admin Manager - Set emergency contact system (Police, Military, Hospital ,HQ)
- Request security to police and military service Recognize current
ns
Precaution issue and inform to
co
Admin Team - Research Emergency zone. manpower
- Manage beget to be project withdrawal.
- Manage document to be project withdrawal.
ad
- Secure Emergency Food/medicine, communication
- Secure Transformation plan such as Fuel, Etc.
ro
- Handling Manpower plan to be project withdrawal When Departure
ss
Admin Team - Set route to prepare withdrawal
ce
Occurred
- Confirm needed document for airplane Consult with THL
Emergency
ac
- Secure emergency food and medicine, communication
method.
1
Construction Team - Set emergency organization and make decision to escape
ot
area (Level 5)
rL
- Handling documents
ve
13
2. EMERGENCY RESPONSE (SCENARIO 2: OVERSEAS/EMERGENCY)
ly
■ WORK FLOW CHART
on
Accident
n
io
ct
First Discoverer
tru
ns
PM HQ Manager
Lev. 1 Judge
co
Lev. 5
More then
situation
ad
Lev. 2~5 Lev. 2~5 HQ Admin
HQ Financial Representative
ro
More thenLev.3 (Report) HQ Planning
More then Lev. 4
THL/Organization Manpower
ss
HQ HSE
ce
HQ HSE Team MANAGER
ac
Injured
First Action Occurred
1 Hyundai
Only Needed Only needed Construction
ot
ISOS
rL
+82-2-3140-1700 HQ HEC
Planning Team(1)
d
Situation ABNORMAL
ve
Monitoring
※ Serious Accident
o
urgently.
- -National
Close Transfer
Ap
- -International
- -Mother Country
14
2. EMERGENCY RESPONSE (SCENARIO 2: OVERSEAS/EMERGENCY)
ly
■ HOSPITAL INFORMATION & ETC
on
n
Emergency/urgent Situation Action
io
ct
□ Malaria/Dengue fever □ The Malaria is infected by female mosquito and the symptom is similar with cold and it occur indigestion also high
tru
fever.
▷ symptoms usually appear 10–15 days after the infective mosquito bite.
ns
▷ Typically during the day the mosquito can cause dengue fever but from the evening the mosquito cause malaria.
co
▷ During the 2018 year in Solomon island, the malaria patients reported it has around 30,000 case and 12 death out of them.
▷ The malaria is curable in Solomon islands, but there is no medicine for Dengue fever to relieve.
ad
▷ When the symptom is occur should be test by malaria kit and visit hospital to get blood test and get description and medicine accordingly
ro
▷ Generally, people are going to private hospital for better quality medical service such as injection into body and take medicine
▷ At workplace should wear long sleeve cloth and prepare mosquito repellent at home also test kit and try to understand how to using them.
ss
□ Trauma/fracture(Broken Bone)
ce
□ When get Trauma/fracture(Broken Bone) should be get first-aid activities and transfer to hospital the soonest.
ac
▷ Check at the hospital whether can get correct diagnosis and Treatment service or not.
▷ What if in Solomon islands there is no correct the medical service then have to go Australia by airplane instead.
1
□ Internal diseases/Wound
ot
□ Get Medical check up on hospital when you worried about internal diseases and further medical services.
rL
▷ What if worried about Internal diseases then can visit national hospital and get some help.
fo
▷ In Solomon islands there is not enough medicine in sometimes, but trying to get it from Australia then it takes too much time.
□ The services of Ambulance
d
□ The Ambulance service is available National and St, John hospital, but it doesn't have enough facility inside of vehicle.
▷ What if there is no proper medical service available then can be transfer by airplane at St. John Hospital which is
o
pr
□ Helicopter service
□ Helicopter service is available since the ambulance sometime cannot enter due to road condition.(Henderson Airport
Ap
area)
▷ The Hospital and police office help is necessary when transfer patient by helicopter
15
2. EMERGENCY RESPONSE (SCENARIO 2: OVERSEAS/EMERGENCY)
ly
■ HOSPITAL INFORMATION & ETC
on
n
Emergency/urgent Situation Action
io
ct
□ Police Station □ Contact No. : 999 (Hot-line) / 24421 (Control Office) / 23666 (Resident Center)
tru
□ Medical Emergency □ Emergency : 911 (Hot-line) / 955 (Disaster) / 988 (Fire) / 933 (Forecaster office)
ns
□ MHMS : 27936 / 27937
co
□ Maritime Rescue : 21609 / 27685 or 977
□ Ambulance : 111 (St. John) / 4400 (National Hospital)
ad
□ Helicopter Service : 7494398 (Gary, Pilot)
ro
□ National Referral Hospital □ Free medical services is available at Solomon National Hospital on Honiara
ss
(National Hospital) □ Medical Officer 50 persons and equip with sick room number of 300
ce
□ But there is no high-level medical service also it seems like not clean all of the facility
ac
therefore the foreigner usually doesn't use here. (Basic Surgery is available such as Appendectomy)
□ Operating Emergency room and Ambulance : 25256 (Emergency) / 4400 (National Hospital.)
1
□ Equip with X-ray and Ultrasound Equipment(No MRI/CT)
ot
rL
□ Honiara International Medical □ Located Panatina area and private (Doctor: 1 person Nurse: 1 person Part-time: 2person Etc.)
fo
Center □ Cooperated with KOICA and can get check up services not only for malaria and Dengue fever
also General one.
d
ve
□ Contact No. : Fletcher Kakai (8472739, Doctor) / Linda Kakai (38346, Nurse)
□ Working Hour : Daytime (08:00~16:30), Sat. (09:00~16:30), Sun. only for emergency
Ap
16
2. EMERGENCY RESPONSE (SCENARIO 2: OVERSEAS/EMERGENCY)
ly
■ HOSPITAL INFORMATION & ETC
on
Emergency/urgent Situation Action
n
io
□ Ecall Health Center □ Located Alvaro Building as Private hospital (Doctor:1person, Nurse:1person, Part-
ct
time:3person)
tru
□ Cooperated with KOICA and can get check up services not only for malaria and Dengue fever
ns
also General one.
co
□ Available Basic surgery / Immune Treatment / Issue Medical Certification
□ General Diagnosis service is not available such as HIV etc.
ad
□ Contact No. : Lazarus Tavichikai (8687403, Doctor) / Christina Tavichika (23130, Nurse)
ro
□ Hyperchem Pharmacy □ Working Hour : Day time (08:00~16:30), Sat. (09:00~16:30), Sun. Only for emergency
ss
□ Located in Central Plaza of Honiara
ce
□ Malaria/Dengue fever check up(30~50SBD) and general medicine service is available.
ac
□ Contact No. : 23588 (Day time 08:00~19:00, Sat. 08:00~17:00, Sun. 09:30 ~ 15:30)
□ People Pharmacy 1
□ Located in Kwaimani Building of west Honiara
ot
□ Malaria/Dengue fever check up(30~50SBD) and general medicine service is available.
rL
(HEC joined this insurance) □ When employee is outside of Korea for business/work then this insurance will be joined
d
□ Emergency situation such as Disease / Accident / Terror / then can contact (+82-2-2-3140-
o
□ Emergency Center -> Connect Local -> Medical service is not available on local then make
Ap
ly
■ SECURITY EVACUATION ROUTE (AIR EVACUTION)
on
n
Air port
io
Assembly Point
ct
First Gathering place
tru
Exist Road
Escape Route Exist Road
ns
L= 7.3Km
L= 7.3Km
co
Black point
Junction
ad
Access Road 0Km+000
Lot 2 (L=6.2KM,B=4.5M)
ro
Lot 1 (L=13.4KM,B=7M)
ss
Core boundary
Camp Site
Office Site L=3.3km
ce
5Km+200 3Km+300
L=14.4km
ac
Dam Site BP(2)
BP& Office site
2Km+500 1 Manakiki Village
ot
13Km+400 9Km+400
7Km+400
rL
Powerhouse
fo
d
o ve
Aggregate Site
Project Site (Camp & Office) ▶ Honiara Airport ▶ Brisbane (AUS) ▶ Incheon(Korea)
pr
Project Site (Camp & Office) ▶ Honiara Airport ▶ PNG ▶ Maynila(Philippines) ▶ Incheon(Korea)
Ap
18
3. OTHERS
ly
■ EMERGENCY RESPONSE DRILLS
on
Progress Rate
n
io
Classification Training Example Construction
Commi-
ct
Remark
Middle ssioning
tru
Early stage Finish stage
stage
ns
Serious Work Accident ○
co
Emergency Rescues at Height ○ ○
ad
Emergency Rescues from Confined Space ○ ○ ○
Safety Accident
ro
Collapse Scaffolding ○
ss
On-Site Vehicle Accident ○
ce
Crane Incident ○
ac
Fire ○
Fire Related Incident
Explosion 1 ○
ot
Violent Conduct ○
Security
rL
Evacuation ○
fo
Etc. Others ○
o ve
2. Fire Related Incident : Scenario suitable for site condition (Camp, Office, Powerhouse, 2 Times/year)
Ap
19
3. OTHERS
ly
■ EMERGENCY CONTACT POINT
on
Category Contact No. Description Remark
n
Site Manager +677-7119096 Chungryul. Ha
io
HSE Manager +677-7411755 Daeyoung. Kim
ct
tru
Site Social Staff 1 +677-7818626 Withlam Kikolo (Namopila Community)
Social Staff 2 +677-7445718 Daniel Una Area
ns
Social Staff 3 +677-7110953 Job Vari
co
DPM +677-7496338 Fred Conning
ad
PO &
CFO +677-7975259 Jaeil. Ryoo
THL
ro
OE +642-12416900 Bird Andrew
ss
PNG Embassy +675-3215826 Woo rim, Kang
ce
Life & Death
Hospital 1 25256 (Emergency) / 4400 National Referral Hospital 999
Situation
ac
Honiara International Medical Center Disaster
Hospital 2 1
+677-8472739 955
Fletcher Kakai council
ot
Serch &
Hospital 3 +82-2-3140-1700 977
rL
International SOS
Organiza Rescue
tions &
fo
Weather +677-27658
Fire Station +62-22-87782113 988
forecating 933
o
pr
20
3. OTHERS
ly
■ EQUIPMENT & FACILITIES
on
n
Category Item Location Description Quantity Remark
io
ct
SUV Muster Point For Site emergency Situation 8 EA 32 Person
tru
Truck Muster Point For Site emergency Situation 2 EA 20 Person
ns
All
co
Ambulance Muster Point Proceeding purchase 1 EA
ad
First Aid Box Medical Center - 5 EA
ro
Fire Extinguisher - Site 10 EA / Office 10 EA / Camp 30 EA 50 EA 3.5Kg
ss
Fire-Fighting Fire Extinguisher - B/P 1EA, CP 1EA 2 EA 20Kg
ce
ac
Noise & Vibrator Test
1 1 Set
ot
21
# Reference
ly
■ SITE LAYOUT
on
Air port
n
io
ct
tru
Exist Road
L= 7.3Km
ns
Black point
co
Junction
ad
Access Road 0Km+000
Lot 2 (L=6.2KM,B=4.5M) Lot 1 (L=13.4KM,B=7M)
ro
Lot 3 (L=1.9KM,B=4.5M)
Camp site(3ha)
ss
Core boundary
Camp Site
Office Site L=3.3km
ce
5Km+200 3Km+300
L=14.4km
ac
Dam Site BP(2)
BP& Office site
2Km+500 1
ot
Manakiki Village
13Km+400 9Km+400
rL
7Km+400
12Km+000 Marava Village
fo
Powerhouse
d
o ve
pr
Aggregate Site
Ap
22
Emergency Communication Network.
ly
Emergency Communication Network.
on
Emergency
n
io
ct
tru
[PO] [Ambulance Services/Hospital]
Deputy Project Manager TEL. 911
ns
[Police Station Henderson]
TEL +677-7496338 [National Referral Hospital]
TEL. +677 - 7265936
co
[THL]
+677 - 7716519 TEL. 25256/4400
CEO
ad
TEL +677-7975259 [Fire Department]
TEL.
ro
[SolPower]
[Government] TEL +677-42480
ss
MECDM [Community Contact Point]
ce
TEL. 26026 Withlam Kikolo
ac
MMERE [EPC Contractor] TEL. 7818626
TEL. 21522 Deputy Project Manager
1 Daniel Una seli
TEL +677-7119096
GP TEL. 7445718
ot
[HSE Manager]
TEL. +677-7551812 Job Vari
rL
TEL +677-7411755
CITY COUNCEL [Sub-Con] TEL. 7710953
fo
Tina community
o
Emergency
Ap
23
Community Contact Point
ly
on
Contact
Communities Villages Sub tribes/clans In the community Name or Rep Remark
Point
n
io
Namopila, Choro, Senge, Habusi, Sutahuri, Kaokao, Uluna, Koenihao, John Bate No Phone
Namopila community
ct
Pachuki, Komureo, Kochiabolo, Sabaha Welson Keapulu 719-2452
tru
Antioch, Valesala, Valekocha, Kochiabolo, Lasi, Kaipalipali, Kaokao, Kendmiel Lauri 000-0000
Antioch community
ns
Vatunandi Charana, Roha, Koenihao, Sutahuri, Uluna Rex Meki 879-1014
co
Kochiabolo, Charana, Kaipalipali, Roha, Withlam Kikolo 781-8626 HEC
Verakuchi community Mangakiki, Verakuji, Hanilake
Sarahi Jetro Baesi 725-0027 Coodinator
ad
Peter Rocky 724-3016
ro
Tina, Valebarik, Valebebe, Sarahi, Riva, Chavuchavu, Rausere,
Tina community Apolosi Welsly 731-3089
Tahurasa, Valemaota, Sudungana,
Caspar Variri 799-1836
ss
ce
Marava, Ngongati, Rate CHS,
Marava community Charana, Kochiabolo, Kaipalipali, Sabaha Michael Meki 740-4836
Vera'ande, Verakwele, New Mahata
ac
1 Chavuchavu, Uluna, Kaokao, Halisia, Alphias Kiho 727-2880
Katihana community Katihana
Rausere, Chacha, Kochiabolo Sipiriano Masi 741-1160
ot
rL
Haimane community Haimane Koenihao, Lango, Sutahuri, Uluna Henri Gesi 723-3458
d
ve
24
ACCIDENT REPORT AND EMERGENCY CALLS
ly
ATTACHMENT 1 – ACCIDENT REPORT AND EMERGENCY CALLS
on
n
io
•RESUCITATION
ct
PERSONAL HEALTH TRANSPORT
•EMERGENCY AMBULANCE OR PRIVATE
CARE
tru
INJURED •URGENCY VEHICLE
NURSE OR
•RESUCITATION
EMERGENCY
ns
•EMERGENCY
BRIGADE
•URGENCY
co
4. NO URGENCY
ad
(MINOR)
ro
PLACE OF CARE
ss
NURSING
Dr. +677-8576660
ce
ac
WORK AREA YES LABOR
NO
ASSIGNED
1 OK?
ot
rL
SITE DIRECTOR
CR. HA HOSPITAL & POLICE
NATIONAL REFERRALL
fo
+677-7119096
HSE TEAM HOSPITAL
SITE MANAGER
SUNG PUNG 25256 & 4400
d
JB.YOO
+677-7134459 HSE MANAGER POLICE (HENDERSON
ve
+677-7169559
COODINATOR DY.KIM STATION)
+677-7818626 +677-7411755 7265936
o
25