Question

Karl Knapps, Inc., has received the following orders: Period


1 2 3 4 5 6 7 8 9 10 Order size 0 40 30 40 10 70 40 10 30 60
The entire fabrication for these units is scheduled on one
machine. There are 2,250 usable minutes in a week, and
each unit will take 65 minutes to complete. Develop a
capacity plan, using lot splitting, for the 10-week time period.

Answer & Explaination

Step 1

Step 2