This document provides an answer to a question about developing a capacity plan using lot splitting for orders of various sizes over a 10 week period when a machine has 2,250 usable minutes per week and each order takes 65 minutes to complete. The answer breaks the process into steps but does not provide the full steps or solution.
This document provides an answer to a question about developing a capacity plan using lot splitting for orders of various sizes over a 10 week period when a machine has 2,250 usable minutes per week and each order takes 65 minutes to complete. The answer breaks the process into steps but does not provide the full steps or solution.
This document provides an answer to a question about developing a capacity plan using lot splitting for orders of various sizes over a 10 week period when a machine has 2,250 usable minutes per week and each order takes 65 minutes to complete. The answer breaks the process into steps but does not provide the full steps or solution.
Karl Knapps, Inc., has received the following orders: Period
1 2 3 4 5 6 7 8 9 10 Order size 0 40 30 40 10 70 40 10 30 60 The entire fabrication for these units is scheduled on one machine. There are 2,250 usable minutes in a week, and each unit will take 65 minutes to complete. Develop a capacity plan, using lot splitting, for the 10-week time period.