Contractors Name:

PT. Wahanacipta Muliagraha

HSE DAILY
REPORT
DAYS : Wendesay Today Workers
111
/DATE : 02/01/2023
Total Man Hours
888
PIC

HSE PERFORMANCE WEATHERS


PERMIT RELEASED
NO. EXPLANATION NO YES REMARKS TIME CONDITION
1 Tool Box Meeting √ - 08:15 : Rain 1. Height Permit
- 13:00 : Rain - Pianting stell Struktural, Febrikasi
2 Personal Protective Equipment √
welded mesh , Installing fascia, (WH)
3 First Aid Kit √ - Painting Stell Struktural instal
Perline, piperack, Gordin mezzanine,
4 Fatality Case √
Flange brance Cladding runner, Intall
5 Medical Treatment Case √ Roof Gater, Installation Ram (IWL)
HSE ISSUE - Piperack, Electrical Colom,cleaning
6 First Aid Case √
& painting, Welding Power
7 Near miss Case √ Messy material in the work area stengtheming plate, install cladding
miner,install roof gater (RPET)
8 Fire Case √ -Installing Sloof Fromwrok (UB)
√ 2. Hot Permit
9 Property Damage Case
- Install Fascia, Febrikasi Welded
Environmental Damage √ Mesh (WH)
10
Case - Flange Brace, Piperack, Clading
√ runner,(IWL)
- Piperack,Electrical colom, Clanding
Runer, Install Proff Gater,Welding
Strenghithening plate (RPET)
3. General Permit
11 - Install Roof Gater, Erection Colom
(RPET)
- Aluminuim Lover, Particion,
Environmental Case Febrikasi Welded Mesh (WH)
- Roof Gatter (IWL)

12 Hazard Findings √ NOTES AND RECOMMENDATION:


13 Working Hours 08.00-22.00 Do housekeeping regularly and place materials neatly and not block the
work area
14 Others
Fire Extinguisher Performance Equipment Performance
Item Pin Pressure Hose Cylinder Equipment Proper Not Proper Remarks
Fire extinguisher √ √ √ √ Bar Bending Machine √
RPET
Fire extinguisher WH √ √ √ √ Bar Cutting Machine √

Fire extinguisher √ √ √ √ Portable Grinder √


Office
Fire extinguisher IWL √ √ √ √ Welding Machine √

Excavator √

Crane 25 ton √

Concrete Mixer √

Gas Cutting Set √


HSE DOCUMENTATION

Toolbox Meeting Painting Steel Piperack