Professional Documents
Culture Documents
Manpower Report Day 2 8 23 22
Manpower Report Day 2 8 23 22
Villaverde, Allan A.
Manpower Report: Block 04, Lot no. 29-30 Date: August 23, 2022
Current Activities Manpower % Completion
1 Finishing (Window 2nd Floor) 3 100%
2 Ceiling Works 0 0%
TABLE 1.1
Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently the activity “Exterior Finishing” has been completed.
Manpower Report: Block 06, Lot no. 35-36 Date: August 23, 2022
Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently all the activities are still ongoing with “Interior Plastering” having the
most progress out of all the activities
Manpower Report: Block 06, Lot no. 29-30 Date: August 23, 2022