DAILY PROGRESS REPORT


Presented in table 1.1 are corresponding the progress of ongoing activities on Block 04,
Lot no. 29-30. Currently, the activity “Electrical Works” has been completed.

Manpower Report: Block 04, Lot no. 29-30 Date: August 25, 2022
  Current Activities Manpower % Completion
1 Electrical Works 1 100%
TABLE 1.1

Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently, all of the activities are still ongoing with “Exterior Finishing” having the
most progress with a 90% to completion.

Manpower Report: Block 06, Lot no. 35-36 Date: August 25, 2022

Current Activities Manpower % Completion


1 Exterior Finishing 3 90%
2 Exterior Plastering 1 3%
3 Ceiling Steel Framework 2 50%
TABLE 1.2

Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 29-30. Currently, the activity “Fascia Board Installation” has been completed.

Manpower Report: Block 06, Lot no. 29-30 Date: August 24, 2022

Current Activities Manpower % Completion


1 Fascia Board Installation 3 100%
2 Roof Flashing Installation 3 50%
3 Exterior Finishing 5 65%
4 Stair Framing Installation 3 75%
TABLE 1.3