DAILY PROGRESS REPORT


Presented in table 1.1 are corresponding the progress of ongoing activities on Block 04,
Lot no. 29-30. Currently, the activities “Fascia Board Installation and Ceiling Board Installation”
has been completed.

Manpower Report: Block 04, Lot no. 29-30 Date: August 25, 2022
  Current Activities Manpower % Completion
1 Fascia Board Installation 2 100%
2 Ceiling Board Installation 3 100%
3 Roof Flashing Installation 2 65%
TABLE 1.1

Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently, all of the activities are still ongoing with “Window Finishing” having
the most progress with a 95% to completion.

Manpower Report: Block 06, Lot no. 35-36 Date: August 25, 2022

Current Activities Manpower % Completion


1 Interior Skim Coating (2nd layer) 2 70%
2 Exterior Putty Application 1 5%
3 Window Finishing (2nd floor) 2 95%
4 Tile Works 2 30%
TABLE 1.2

Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 29-30. Currently, the activity “Window Finishing (2 nd floor)” has been completed.

Manpower Report: Block 06, Lot no. 29-30 Date: August 24, 2022

Current Activities Manpower % Completion


1 Window Finishing (2nd floor) 2 100%
TABLE 1.3