Manpower Report Day 5 8 30 22
Manpower Report Day 5 8 30 22
Villaverde, Allan A.
Manpower Report: Block 04, Lot no. 29-30 Date: August 25, 2022
Current Activities Manpower % Completion
1 Fascia Board Installation 2 100%
2 Ceiling Board Installation 3 100%
3 Roof Flashing Installation 2 65%
TABLE 1.1
Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently, all of the activities are still ongoing with “Window Finishing” having
the most progress with a 95% to completion.
Manpower Report: Block 06, Lot no. 35-36 Date: August 25, 2022
Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 29-30. Currently, the activity “Window Finishing (2 nd floor)” has been completed.
Manpower Report: Block 06, Lot no. 29-30 Date: August 24, 2022