DAILY PROGRESS REPORT
Presented in table 1.1 are corresponding the progress of ongoing activities on Block 04,
Lot no. 29-30. Currently the activity “Stair Vinyl Laying” has been completed.

Manpower Report: Block 04, Lot no. 29-30 Date: September 15, 2022
  Current Activities Manpower % Completion
1 2nd Floor Vinyl Laying 1 90%
2 Stair Vinyl Laying 1 100%
3 Exterior Painting 1 75%
4 Clearing 2 70%
TABLE 1.1

Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently the activity “Rear Exterior Plastering” has been completed.

Manpower Report: Block 06, Lot no. 35-36 Date: September 15, 2022

Current Activities Manpower % Completion


1 1st Floor Vinyl Laying 1 25%
2 Exterior Painting 1 20%
3 Rear Exterior Plastering 3 100%
TABLE 1.2

Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 29-30. Currently the activity “Vinyl Laying” have been completed.

Manpower Report: Block 06, Lot no. 29-30 Date: September 15, 2022

Current Activities Manpower % Completion


1 Vinyl Laying 1 100%
2 Exterior Painting 1 95%
3 Interior Painting 1 65%
TABLE 1.3