Professional Documents
Culture Documents
170653T - Assignment 03
170653T - Assignment 03
0 M DIAMETER RAFT
FOUNDATION FOR AN ICONIC
TELECOMMUNICATION TOWER
Lecturer in Charge:
Index No : 170653T
Module : CE 4482
List of Figures
1.1 Background
Under this study, it was proposed to carry out a finite element analysis to investigate the
behavior of the raft foundation and subsurface by using the PLAXIS Software.
1.2 Subsurface Characteristics
The raft is founded partly on rock, and since the bed rock is sloping, part of the raft will
be constructed on a concrete fill. The worst case subsurface profile observed through
section A – A are shown in Figure 2.
The critical service loads that are applies on the raft are as follows,
Following geotechnical issues were identified during the initial investigation and
1. Excavation have to be water tight due to the high ground water table, and
secant piles can be use to achieve this purpose.
Since the soil profile is not symmetric about an axis, axisymmetric analysis cannot be
conducted. So, plain strain analysis was conducted.
Since we are using the Plain Strain model, we cannot feed the circular raft into the PLAXIS
software. So, circular footing was converted into an equivalent square footing as follows
and that square footing was feed into the PLAXIS software.
717,000 kN
717,000 kN
20,000 kN 20,000 kN
1,000,000 kNm
1,000,000 kNm
43 m
43 m
717,000 𝑘𝑁
- Vertical pressure applies on the footing = 𝜋𝑥432⁄
= 494𝑘𝑁/𝑚2
4
20,000 𝑘𝑁
- Horizontal pressure applies on the footing = 𝜋𝑥432 = 13.8 𝑘𝑁/𝑚2
⁄4
Application of Moment
- Moments can’t be directly apply on the foundation using PLAXIS software. But,
application of vertical load with an eccentricity can generate a moment which is
equal to 1,000,000 kNm. Therefore, the vertical load (717,000 kN) to be applied on
the raft is applied as follows to generate the required amount of moment.
717,000 kN
717,000 kN
1,000,000 kNm
𝜎 𝜎min
𝜎 𝜎max
- 𝜎max = 𝐹𝐴 (1 + 6 𝐵𝑒 ) =
717,000
1452.2
𝑥 (1 + 6
1.394
43
) = 589.8 𝑘𝑁/𝑚2
- 𝜎min = 𝐹𝐴 (1 − 6 𝐵𝑒 ) =
717,000
1452.2
𝑥 (1 − 6
1.394
43
) = 397.7 𝑘𝑁/𝑚2
However, during the modelling I didn’t model the excavation. So, the residual soil
column above the foundation kept as it is and the effective pressure applies on the raft
by soil column was reduced from the applied load on raft.
So, applied load on the raft for the PLAXIS Model will be,
Stress distribution below the raft due to this new vertical load,
- 𝜎max = 𝐹𝐴 (1 + 6 𝐵𝑒 ) =
459960
1452.2
𝑥 (1 + 6
2.17
43
) = 412.6 𝑘𝑁/𝑚2
- 𝜎min = 𝐹𝐴 (1 − 6 𝐵𝑒 ) =
459960
1452.2
𝑥 (1 − 6
2.17
43
) = 220.8 𝑘𝑁/𝑚2
This stress distribution was applied to the Model as a trapezoidal stress distribution.
Geometry dimensions
- Left -10 m
- Right 100 m
- Top 0 m
- Bottom -93 m
Assumption used during the Modelling,
23 m
10 m
60 m
200 m
Figure 3: FE Model of Raft Foundation
4.0 FOLLOWED CONSTRUCTION SEQUENCE
Rock layers and the concrete fill was modelled initially, and the excavation of top rock
layer and construction of concrete fill was not considered for the construction sequence.
Application of Raft foundation was considered as the first construction step. Then vertical
loads were applied on the raft foundation as a trapezoidally distributed load to account
the moment applied on the raft. Finally horizontal load was applied on the footing as a
uniformly distributed load in horizontal direction.
Maximum shear stress along the rock concrete interface = 318.21 kN/ m2
8.0 PROPOSED MONITORING PLAN
Eventhough the secant pile walls are water tight, there can be water leakages through
the retaining structure. Therefore, the water table level around the project site can be
reduced, and it may cause for the damages to the surrounding structures. Therefore,
the groundwater level at the outside of the retaining structure should carefully
monitor.
The stability of 15m excavation is completely rely on the secant pile retaining
structure. Therefore, it is very important to ensure the safety of retaining structure.
For that, the lateral movement of retaining structure should carefully monitored
through the period of construction.