EOT cranes are inspected using a checklist to ensure they are in safe working condition. The checklist includes 14 items like the physical condition of the crane, condition of railings and power cables, safety features of the hook and load markings. It also checks for machine guarding, load charts, remote controls, operator licensing and safe access. The inspection is signed off by the inspector and reviewer with their details to verify the crane is fit for use.
EOT cranes are inspected using a checklist to ensure they are in safe working condition. The checklist includes 14 items like the physical condition of the crane, condition of railings and power cables, safety features of the hook and load markings. It also checks for machine guarding, load charts, remote controls, operator licensing and safe access. The inspection is signed off by the inspector and reviewer with their details to verify the crane is fit for use.
EOT cranes are inspected using a checklist to ensure they are in safe working condition. The checklist includes 14 items like the physical condition of the crane, condition of railings and power cables, safety features of the hook and load markings. It also checks for machine guarding, load charts, remote controls, operator licensing and safe access. The inspection is signed off by the inspector and reviewer with their details to verify the crane is fit for use.
Company Name : Date of Inspection : Make : Model : Number : Owned/Hired/Contractor :
SN Details Yes/No Comments
1 EOT crane should be physically in good condition, free from defects and should have valid TPI. 2 Railing should be in good condition and free from obstruction. 3 Power cable should be free from defect and organised. 4 Safety latch in hook and in working condition. 5 Safe working load should be marked at proper place and should be visible. 6 Wire rope or sling should be free from defects and tested properly. 7 Rotating parts should be covered properly with machine guarding. 8 Audible horn should be available and in working condition. 9 Load Chart Available at proper place. 10 Deflection Test Should be carried out for smooth operation. 11 Remote should be ion good and working condition. 12 Operator should have suitable and valid license. 13 Safe access and egress should be provided.
Fit for use: Yes/No
Inspection Done By:
Name: Department: Designation: Signature: Date:
Review Done By:
Name: Department: Designation: Signature: Date: