Comparative Study of Drawings of AW Works

Items BOQ Tender Drawing Construction Remarks


Drawing
Staff Residence: Quantity: 682
Rate: 80000/- General Notes: General Notes: Not mentioned
1. Bungalow (Plinth Amount: aprox: 54.5 million Excavation and Excavation and protection
Area 341 sq.m) Items: Supply Labour and dewatering; The dewatering; The material in
02 Nos material to construct staff Contractor shall Contractor shall construction
residence, with accessories provide positive provide positive drawing
and fitting including protection protection for
excavation in all soil or rock (mat/sheet all Excavation There is
(as the case may be ), covering) for all slopes difference in safe
termite treatment, Excavation slopes Foundation: allowable bearing
foundation, columns, Foundation: Safe Allowable capacity of 50
beams, ground beams, Safe Allowable Bearing KN/m2 b/w both
slabs, stairs, roof tower, Bearing Capacity Capacity of 200 drawings
roof treatment, finishing of 250 KN/M2 for KN/M2 for all
works, electrical, all types of types of
mechanical works, solid foundations foundations
core doors with G.I frame ( Isolated, (Isolated,
and powder coated Combined, Strip, Combined, Strip,
raft, etc) 1.5 m raft, etc) 1.5 m
aluminium doors, window
and carpentry works, steel below NGL below NGL
gates,
Plumbing/Sewage/Drainage
works, external works
including driveway, ramp,
pavement, and landscaped
area. Etc. complete in all
respect as per design,
drawings, specification and
as directed by the Engineer.

Architecheral Drawing

Ground Floor Plan: G.L = +0.75M G.L = +0.60M


Ground floor plan