SN Clause Actual Excerpt of Clause(s) Description/Interpretation

O.
1 4.20 In matter of delays experienced due to non-timely or
late responses against requests for information,
clarification of drawing or instruction by the
Architect, Contractor may be entitled to time
extension and additional costs subject to fulfillment
of other procedural requirements under relevant
clauses. Here scope of ‘additional costs’ so-referred
can be extended to entail cost incurrence due to
productivity losses.

2 4.21(i) In matter of delay or disruption due to concealed or


unknown conditions experienced at site then subject
to fulfillment of other procedural requirements under
relevant clauses, Architect is under obligation to
evaluate such conditions, recommend equitable
increase to Contract sum giving notice to other party
as well. Failing which Contractor may claim for the
same. Here scope of ‘equitable increase to Contract
sum’ so-referred can be extended to entail cost
incurrence due to productivity losses.
3 4.21(ii) In matter of nature, quality or quantum of work scope
added, varied, changed or altered through Change
Directive, Architect is under obligation to determine
cost, adjust contract sum and certify payments to
Contractor thereof. Failing which Contractor may
claim for the same. Here scope of ‘adjustment to
Contract sum’ so-referred can be extended to entail
cost incurrence due to productivity losses.

4 4.22(i)
5 4.22(ii) A general procedural clause relating to contractor
claims for additional costs. Puts Contractor’s under
responsibility to intimate his intend to claim for
additional cost against works before executing them.

5 4.22(iii)