Professional Documents
Culture Documents
Opercom Course For Trainees by TRD
Opercom Course For Trainees by TRD
Opercom Course For Trainees by TRD
Introduction
By T. R. D.
Technique & Régulation
Développement
Technique & Régulation Développement 2008 1 Technique & Régulation Développement 2008 3
Requirements Specifications
Higher efficiency, Precomm. / Com. Guidelines
Reliability, GS EP EXP 101 Rev 4 - 09/05
Safety, Precomm. / Com Techn. Prep.
Short planning, GS EP EXP 103 Rev 4 - 09/05
Precommissioning Execution
GS EP EXP 105 Rev 3 - 09/05
Commissioning Execution
GS EP EXP 107 Rev 3 - 09/05
Technique & Régulation Développement 2008 5 Technique & Régulation Développement 2008 7
Opercom Glossaire
Project,
To cover these requirements of new installations, Discipline,
Unit,
Client, owner, company, operator,
And reach these objectives
Contractor EPSC, EPSCC, Turnkey,
Project team, Contractor, Vendor,
TOTAL has developed OPERCOM Methodology,
Certifying authority.
Based on know how and latest experiences.
Technique & Régulation Développement 2008 6 Technique & Régulation Développement 2008 8
The Final key The Final key
Project Phases
Basic engineering
Detail engineering
Construction & Precom. / item verif.
Project phases Commissioning / basic function verif.
Start-up
Routine operation.
Technique & Régulation Développement 2008 9 Technique & Régulation Développement 2008 11
COMMISSIONING
Commissioning (static)
COMMISSIONING PHASE READY FOR READY FOR (Dynamic)
OERATION
START-UP
Followed by the
ROUTINE phase (introduction of hydrocarbon)
START-UP PHASE PVP
OPERATIONS
Technique & Régulation Développement 2008 10 Technique & Régulation Développement 2008 12
Provisional
Operate prior oil/gas in (PVP, safety tests, ) acceptance
Operate after oil/gas in : bring the process in operation
with oil/gas in , water injection,.. + performance tests
. Mechanical
Mechanical
Completion Ready for Ready for Ready for Final acceptance
Commissioning Start-Up Operation EPC Contract
Technique & Régulation Développement 2008 13 Technique & Régulation Développement 2008 15
Project Phases
The Final key The Final key
Project Phases
Summary of completion activities
Phases Preparation, management, ...
CONSTRUCTION
COMMISSIONING
START-UP OPERATION
PRE-COMMISSIONING
DOSSIERS
Witness Precom
PREPARATION COMMISSIONING
MANAGEMENT involved
16
Technique & Régulation Développement 2008 14 Technique & Régulation Développement 2008 16
The Final key The Final key
Project Phases System Approach
Technique & Régulation Développement 2008 17 Technique & Régulation Développement 2008 19
Functional constraints
Some areas or units are mechanically completed while
others are not,
Start-up sequence of a new plant is directed by
operational constraints:
System Approach
Safety equipment,
Utility equipment (as power generation),
Process equipment,
Optimisation of the start-up phase needs the sequential
completion of multidiscipline units.
Technique & Régulation Développement 2008 18 Technique & Régulation Développement 2008 20
Technique & Régulation Développement 2008 21 Technique & Régulation Développement 2008 23
System Limits
Project planning have to be optimised, considering that
completion activities are organised by system
INSTRUMENTS D
VESSEL
A system is a subdivision of the plant that performs a &
PIPING
C
independent operational function. S
Example:
Fire water
Power generation
Instrument air ELECTRICAL
PUMP
SWB
MECHANICAL MOTOR LCS
Technique & Régulation Développement 2008 22 Technique & Régulation Développement 2008 24
The Final key The Final key
System Approach System Approach
Delimitation_OPERCOM_SS_Selection.ppt
Technique & Régulation Développement 2008 25 Technique & Régulation Développement 2008 27
Technique & Régulation Développement 2008 26 Technique & Régulation Développement 2008 28
Specifications
GS EP EXP 103: Precommissioning technical preparation,
GS EP EXP 105: Precommissioning execution.
Technique & Régulation Développement 2008 29 Technique & Régulation Développement 2008 31
Technique & Régulation Développement 2008 30 Technique & Régulation Développement 2008 32
The Final key The Final key
Precommissioning Precommissioning
Technique & Régulation Développement 2008 33 Technique & Régulation Développement 2008 35
Technique & Régulation Développement 2008 34 Technique & Régulation Développement 2008 36
Technique & Régulation Développement 2008 37 Technique & Régulation Développement 2008 39
Methodology
Dossiers
Technique & Régulation Développement 2008 38 Technique & Régulation Développement 2008 40
The Final key The Final key
Commissioning
Specifications
GS EP EXP 103: Commissioning preparation,
GS EP EXP 107: Commissioning execution.
All required technical procedures and support
Commissioning
documents,
To prepare and carry out commissioning activities.
Technique & Régulation Développement 2008 41 Technique & Régulation Développement 2008 43
Technique & Régulation Développement 2008 42 Technique & Régulation Développement 2008 44
Technique & Régulation Développement 2008 45 Technique & Régulation Développement 2008 47
Technique & Régulation Développement 2008 46 Technique & Régulation Développement 2008 48
The Final key The Final key
Commissioning Commissioning
Technique & Régulation Développement 2008 49 Technique & Régulation Développement 2008 51
Methodology Index
Policy
General preparation
Precommissioning preparation,
Documents, Planning, Contracts.
Commissioning preparation,
Documents, Planning, Contracts, Supports.
Technique & Régulation Développement 2008 53 Technique & Régulation Développement 2008 55
Policy
Precommissioning & commissioning activities have to
be done in a short period,
Company policy is to thoroughly prepare long before
Technical
the beginning of completion activities, not only all
Preparation
precom and com tasks, but also all side activities, such
as organisation, documentation, spares,etc.
So the organisation can be efficient right from day one.
Company policy consists in a common approach from
end of construction until the start-up.
Technique & Régulation Développement 2008 54 Technique & Régulation Développement 2008 56
The Final key The Final key
Technical preparation Technical preparation
General Precommissioning
General preparation activities are: Estimation of manpower and duration of the
Define list of systems and subsystems (refer to GS EP EXP precommissioning activities of each subsystem
101)
Define plant start-up sequence
Issue marked-up PIDs and OLDs showing limits of Preparation of the precommissioning planning showing
subsystems, the beginning and end of the activities by subsystem
FPU PIDs Marked-Up rev99.pdf
Compile equipment lists by subsystems, Identification of the need for vendors, field equipment
Define all tasks related to the partition of the plant into spares, vendors special equipment and special tools
systems and subsystems.
These activities have to take place during the detailed
engineering phase
These activities are an engineering contractor
responsibility.
Technique & Régulation Développement 2008 57 Technique & Régulation Développement 2008 59
Precommissioning Commissioning
Creation of the status index, arranged by subsystem, Creation of the list of all instrument, electrical and
discipline and type of item of equipment, telecommunications basic functions by subsystem,
Reviewing the set of precommissioning master forms, Creation of the commissioning technical data base by
adaptation or amendment the forms as required by the subsystem
distinctive features of the project, Reviewing the set of master functional test sheet forms
Filling out the Check lists and test sheets according to addition, adaptation or amendment of the forms as
the status index. required by the distinctive features of the project,
Issuing the precommissioning dossier Filling out the functional test sheets according to the
technical data base.
Preparation of the list of Piping & Vessels preparation of
each subsystem with detailed procedures and support
documents.
Technique & Régulation Développement 2008 58 Technique & Régulation Développement 2008 60
Commissioning Commissioning
Preparation of the list of planned operational tests, Compilation of the lists of spares, lubricants, chemicals
complemented for each test by a test summary, and special tools included in the various P.O.
schematics and Operational Test Procedures, Preparation of the lists of tools, test equipment and
Development of the task register, list by subsystem of consumables required to carry out commissioning
all elementary commissioning tasks to be carried out, operations,
Estimation of man-hours, manpower, duration of all Definition of the temporary facilities (air, nitrogen,
task, power generation,
.), equipment and connections
Development of the Commissioning network or necessary to carry out commissioning.
subsystem precedence diagrams, Selection of the commissioning staff and execution
Development of the schedule by subsystem and type of personnel with the personnel mobilisation schedule
activity showing the duration, start and end of each Preparation of the vendors representatives schedule and
activity ( Planning level 2). relevant purchase orders
Technique & Régulation Développement 2008 61 Technique & Régulation Développement 2008 63
Commissioning Commissioning
Preparation of the schedule by system of the Preparation of the documentation required for the
commissioning activities ( Planning level 1), preparation and execution of the commissioning tests,
Preparation of the Ready For Start-up dates, Preparation of a cost control procedure in accordance
Preparation of a commissioning progress calculation with project management procedures.
method based on physical progress,
Evaluation of overall man-hours, duration and
preparation execution histograms by discipline,
Preparation of the field commissioning organisation and
deployment schedule,
Technique & Régulation Développement 2008 62 Technique & Régulation Développement 2008 64
Completion Activities :Technical A- Certificates and transfer of
The Final key The Final key
preparation and Execution responsibility
COMPLETION ACTIVITY COMPLETION ACTIVITY
PREPARATION EXECUTION
(GSEXP-103) (GSEXP-105 & GSEXP-107) Definition
A- GENERAL OPERCOM PREPARATION
(GSEXP-101-103)
D – PRECOMMISSIONING EXECUTION Contractor shall issue for Companys signature
(GSEXP-105) Certificates in order to attest that the facilities have
1- Subsystem Preparation
1- Conformity Checks reached predefined stages of Completion.
2- Start-Up Sequence Preparation
3- Coloured Marked-Up Drawing Preparation
2- Static Tests After a full review of realisation on Work Site and
4- Subsystem Engineering List Preparation
3- Piping Tests through document evidence, Company agrees either
B- PRECOMMISSIONING PREPARATION totally (certificate), or partially (interim certificate), that
(GSEXP-103) E- COMMISSIONING EXECUTION the level of completion has been reached to pass to
1- Status Index Preparation (GSEXP-107) further stage.
2- Precomm. Dossier Preparation 1- Preliminary Checks
A Punch list is raised with each certificate which details
2- Functionnal Tests
3- Precomm. Manpower Estimate Preparation exceptions, omissions in, or errors to the necessary
3- Operating tests
4- Long Precomm. Task Preparation completion level, agreed by all parties with priorities
4- Piping & Vessels Preparation
C- COMMISSIONING PREPARATION and dates identified for completion.
(GSEXP-103)
The certificates are raised for each Subsystem up to the
1- Technical Database Preparation
Ready For Start Up certificate.
2- Commissioning Dossier Preparation
3- Comm. Manpower Estimate prepa
Technique et Régulation Développement 67
4- Long Comm. Task Preparation Technique & Régulation Développement 2008 65 Rev. 1-2008 Technique & Régulation Développement 2008 67
Technical preparation : general overview The Final key The Final key
Certificates (cont
)
What is involved
General Preparation These certificates are:
Establish Subsystem Boundaries and prepare coloured PID’s & SLD’s
Develop initial Start-up Sequence in conjunction with Construction
Build Equipment Lists from Engineering lists and schedules
Identify Spares, Temporaries and Specialist requirements
Prepare and issue Preservation Schedules
RFC Ready For Commissioning certificate
Precommissioning Preparation OT Operational Test certificate
Prepare and issue Precommissioning Procedures
Assign OPERCOM Check and Test sheets to each item of equipment
Develop the Precommissioning Status Index
Prepare Precommissioning (RFC) Dossiers for each Subsystem
RFSU Ready For Start Up certificate
Prepare Precommissioning planning and resource levels
Technique & Régulation Développement 2008 66 Technique & Régulation Développement 2008 68
The issuance of these Certificates can be represented as follow: The Sub system will then be energised for further Commissioning
activities.
Conformity checks
Pre-Commissioning Static tests
Flushing, Cleaning &
hydrotest
RFC
The signature of these RFC certificates by the COMPANY
representative does not represent a hand over of the Pre
commissioned Sub system from CONTRACTOR to COMPANY.
Preliminary Checks
Energization
Commissioning Dynamic tests
Operational tests
The Certificate may be issued when the system is substantially
Leak test RFSU
complete and in such case is related to a Punch List including all
pending items.
Oil and Gas IN The Punch List shall indicate in regard of each listed item the
Last Operational tests RFO
Start Up Bring plant on line
Performance tests
scheduled date when it is to be corrected.
FAC time
Operation Performance tests
Technique & Régulation Développement 2008 69 Technique & Régulation Développement 2008 71
When the CONTRACTOR has performed the mechanical completion of a When the CONTRACTOR has brought into normal operation a given
given Sub system, i.e. all the components of such Sub system have been utility functional system, an Operational Test Certificate is issued for the
supplied, assembled and tested in accordance with the specifications, a system.
Ready For Commissioning Certificate is issued for such Sub system to
acknowledge such completion. This certificate is produced after the successful completion of the agreed
Operational Test. It states for each relevant subsystem of the PLANT
This certificate states the acceptance by CONTRACTOR commissioning that it has been brought into operational condition by CONTRACTOR and
team and COMPANY of MECHANICAL COMPLETION for each sub can be used by them for the needs of Commissioning activities with the
system of PLANT (with the exception of items listed on attached Punch exception of items listed on attached Punch List to be cleared in stated
List to be cleared in stated period). period.
Once agreed, this certificate states that the subsequent Sub system is The CONTRACTOR shall be responsible for the Operating and
ready for the performance of Commissioning activities by CONTRACTOR Maintenance of such utility functional system until the Hand Over of the
and particularly for its safe energisation. facilities is made to COMPANY.
Immediately following the signature of the RFC certificate, the Sub Where Operational tests cannot be performed before hand over because
system is placed under the responsibility of the CONTRACTOR hydrocarbons have to be introduced in order to carry out the Operational
Commissioning team for execution of the commissioning activities. test, they shall be performed under the control and supervision of the
COMPANY at a convenient time during Start Up phase with the
The Sub system will then be energised for further Commissioning CONTRACTOR Commissioning personnel.
activities.
Technique & Régulation Développement 2008 70 Technique & Régulation Développement 2008 72
3- Operational tests done after 4- Ready for Start-up certificate
The Final key The Final key
OIL or GAS in (cont..)
The Commissioning team cannot perform some tests, because of The signature of these RFSU certificates by the COMPANY
HC requirement. In this case the sentence: representative represent a technical hand over of the
commissioned Sub system from CONTRACTOR to COMPANY
“Operational Test no: (test reference) to be performed Post Start-up team.
Oil or GAS IN”
shall be mentioned clearly on the Ready for Start-up Certificate,
and shall be also be added in the Punch List.
Technique & Régulation Développement 2008 73 Technique & Régulation Développement 2008 75
Technique & Régulation Développement 2008 77 Technique & Régulation Développement 2008 79
Technique & Régulation Développement 2008 78 Technique & Régulation Développement 2008 80
Factory Acceptance Test OPERATIONAL TEST PROCEDURES
The Final key The Final key
(cont
) Definition
The Inspection Test Plan shall include Factory Acceptance Tests and reference Once all Basic Functions have been functionally tested, system, subsystem
applicable detailed FAT procedures or group of subsystem, is subject to an Operational Test, wherever
applicable.
The CONTRACTOR Commissioning team shall review these detailed FAT
procedures during the preparation phase held in the home office. COMPANY It consists of bringing the system into operation under conditions as close
shall have the right to review and approve all Procedures and add their as possible to normal with inert fluids, not only to live test the automated
comments and witness involvement. devices, controls, normal and shutdown sequences, but also to reveal
possible mechanical or electrical faults (water tightness, vibrations,
VENDOR shall not start work without full approval of the relevant Pre
overheating, overloading, etc.) which may occur during prolonged normal
commissioning and Commissioning procedures with CONTRACTOR /
COMPANY comments incorporated. use.
Every operational test is a multi-discipline activity, conducted in accordance
CONTRACTOR shall ensure that, all the Pre commissioning and Commissioning with an Operational Test Procedure (OTP), which has been established
activities performed on the package, are done in accordance with the same during the Commissioning preparation phase and approved by the
OPERCOM procedures as those applied for the field equipment. CONTRACTOR Operator. There is no standard OTP, since they vary with the plant.
shall foreseen witnessing of the FAT by commissioning personnel at the vendor
premises. Typical subsystems subject to an operational test are, but not limited to: fire
water pumps, air compressors, power generation, ESD system, export
Every item of equipment shall be checked by VENDOR for conformity with the pumps in recycle, process compressors in recycle (with air or nitrogen if
relevant checklist, and every item of the equipment that can be subject to a test, possible, under gas after Start-up if not), sub-sea equipments, freon or
shall be tested, and the tests reported on the relevant test sheets. propane packages, hot oil loop, etc.
Technique & Régulation Développement 2008 81 Technique & Régulation Développement 2008 83
Technique & Régulation Développement 2008 82 Technique & Régulation Développement 2008 84
Technique & Régulation Développement 2008 86 Technique & Régulation Développement 2008 88
The Final key The Final key
Subsystem 1870 Subsystem 1810
Technique & Régulation Développement 2008 89 Technique & Régulation Développement 2008 91
Set points
Technical
Execution
Technique & Régulation Développement 2008 90 Technique & Régulation Développement 2008 92
Index Precommissioning
Breakdown Systematic conformity checks of equipment (transmitter,
Precommissioning execution, motors, cables,
)
Visual inspection
Tasks, documents. quality of installation
Commissioning execution, Compliance with project specifications, safety rules, standard,
Tasks, documents. Static/de-energised tests of equipment
Setting of instrument, setting of valves, machinery alignment,
pressure testing of tubing, de-energised tests of electrical or
instrument equipment
Pipe works flushing & cleaning, pressure test grouped by test
pack
Hydro test
Gross leak tests
Technique & Régulation Développement 2008 93 Technique & Régulation Développement 2008 95
Punch list
TEST
list
Inerting
PROCEDURE RFO
clearance Load of chemicals
Technique & Régulation Développement 2008 94 Technique & Régulation Développement 2008 96
The Final key The Final key
Organisation
Parties
Company,
Project team,
Operations
Organisation Engineering contractor
Construction contractor
Main contractor (EPSCC)
Vendors
Certifying authority
Technique & Régulation Développement 2008 97 Technique & Régulation Développement 2008 99
Organisation Organisation
Technique & Régulation Développement 2008 98 Technique & Régulation Développement 2008 100
Technique & Régulation Développement 2008 101 Technique & Régulation Développement 2008 103
102
Technique & Régulation Développement 2008 102 Technique & Régulation Développement 2008 104
The Final key The Final key
Organisation
Transfers of responsibility
EXAMPLES
Technique & Régulation Développement 2008 105 Technique & Régulation Développement 2008 107
Precommissioning sheets
A1- Precom sheets.xls
A2- Com sheets.xls
Modules and SubSystems lists
Annexes
A3- Moho Subsystem list and modules lists rev3.xls
A4- FPO Module.xls
PID Mark-ups
A5- FPU PIDs Marked-Up.pdf
Technique & Régulation Développement 2008 106 Technique & Régulation Développement 2008 108
Akpo décomposé.PDF
FPSO
Vendor packages
Technique & Régulation Développement 2008 109 Technique & Régulation Développement 2008 111
Your contact
The Final key The Final key
PAZFLOR FPSO WORK PACKAGES
Technique & Régulation Développement 2008 110 Technique & Régulation Développement 2008 112