PROJECT WOKPLAN AND BUDGET MATRIX

Project Title: Project SEAWALLS (Structure, Enhance, Augment the Walls, Ambience, Lawns, and Landscape
of the School)
Problem Statements: 1. Only 20% of school site is fenced.
2. There are 820 out of 1,139 stakeholders (72%) who actively participated in school’s
extra-curricular activities such as Brigada Eskwela and Gulayan sa Paaralan.
Project Objective Statements: 1. To augment and concretize the perimeter fence
2. To make the school safe, friendly, and attractive by means of restructuring
the damaged structures and enhance the color of school buildings and
facilities
3. To increase stakeholders’ participation to 90%
Root Causes: 1. Students were cutting classes because the school site is not completely fenced.
2. The damaged school facilities were dangerous for students especially during rainy days.
3. The percentage of attendance of stakeholders during the conduct of school activities is low.

ACTIVITY OUTPUT DATE OF PERSON/S BUDGET BUDGET


IMPLEMENTATIO RESPONSIBLE SOURCE
N ITEM AMOUNT
PRE-IMPLEMENTATION
• Assessment of Result of the Principal,
November 2022 Needs
the condition of Needs Physical Assessment
physical Assessment, Facilities Form
facilities and documentation Coordinator,
determining the BE
maintenance Coordinator,
needs of the GPP
school (BE and Coordinator
GPP)
• Presentation Minutes, November 2022 Principal, ICT 1,500 MOOE
of Needs attendance Physical equipment,
sheets, Facilities
documentation Coordinator,
BE
Coordinator,
Assessment GPP
findings to the Coordinator,
school faculty teachers snacks
Accomplished Printer,
• Preparation of Program of Physical
November 2022 bondpaper
Program of Works (POW) Facilities
Works (POW) Coordinator,
for the projects BE
Coordinator,
GPP
Coordinator
• Preparation Copy of received
and distribution communication Physical
December 2022 Printer,
of letters, social Facilities bondpaper
communication media Coordinator,
letters to the announcement BE
stakeholders Coordinator,
• Posting of GPP
advocacy Coordinator
campaign or
announcement
in FB Page to
encourage more
participation
from the
stakeholders

• Conduct a Minutes, December 2022 Principal, ICT 2,000 MOOE


SPT meeting attendance Physical equipment,
about the sheets, Facilities snacks
activities for documentation Coordinator,
Brigada BE
Eskwela Plus Coordinator,
and Gulayan sa GPP
Coordinator,
Paaralan teachers
• Purchase Receipt Principal,
January 2023 Physical 220,036
needed
materials as Facilities
stipulated in Coordinator,
the Program of BE
Works (POW) Coordinator,
GPP
Coordinator,
teachers MOOE
DURING IMPLEMENTATION
BRIGADA ESKWELA
• Concreting of Documentation January-February Physical
Perimeter Fence 2023 Facilities 61,630
Coordinator MOOE
• Concreting of Documentation February-March Physical 31, 906
Pathway 2023 Facilities MOOE
Coordinator,
BE
Coordinator
• Restructuring Documentation March 2023 Physical 20,000
of benches Facilities
Coordinator,
BE
Coordinator MOOE
• Painting of Documentation April 2023 Physical 25,000
school buildings Facilities
and facilities Coordinator,
BE
Coordinator MOOE
• Brigada Documentation January to July Principal, BE Pre-loved Donation
Eskwela Plus 2023 Coordinator, clothings
Activities plus a teachers,
bonus Ukay- parents,
ukay sa Luy-a students
High
GULAYAN SA PAARALAN
• GPP Minutes, 5000.00 MOOE
Symposium on attendance January 2023 Principal, GPP
fertilizer sheets, Coordinator,
production documentation tecahers

• Rehabilitation Documentation GPP 25,000.00 MOOE


of the fences of February 2023 Coordinator
GPP Area

• Renovation of Documentation GPP 10,000.00 MOOE


the nursery and February 2023 Coordinator
hydro house

• Renovation of Documentation March 2023 GPP 5,000.0 MOOE


the school Coordinator
farmhouse and
display area
• Renovation of Documentation GPP 5,000.00 MOOE
the vermi area March 2023 Coordinator
culture
production

• Concreting of Documentation GPP 10,000.00 MOOE


the plant boxes April 2023 Coordinator

• Hiring of Documentation GPP 4000.00 MOOE


additional April 2023 Coordinator
utility intended
for Gulayan sa
Paaralan

• Making of Documentation April 2023 GPP 5000.00 MOOE


Carbonator to Coordinator
produce
carbonated rice
hull
• Pailaw Documentation GPP 5000.00 MOOE
mo,bunga ko.. Coordinator
A darkrection May 2023
attraction to
produce more
yield
• Project water Documentation May 2023 GPP 5000.00 MOOE
drip Coordinator
• Search for the Documentation GPP 2500.00 MOOE
July 2023
Best Gulayan Coordinator
sa Paaralan
and Tahanan
(Implementor
Student and
Teacher)
Documentation Principal,
Physical
• Monitoring January to July Facilities
and Evaluation 2023 Coordinator,
BE
Coordinator,
GPP
Coordinator

POST IMPLEMENTATION
• Consolidation Record of Physical
of attendance of attendance Facilities
July 2023
stakeholders Coordinator,
who BE
participated in Coordinator,
the school GPP
activities Coordinator

• Prepare and Accomplishment July 2023 Physical Printer,


submit Report, Facilities bondpaper,
accomplishment documentation, Coordinator, folder
report attendance BE
sheets Coordinator,
GPP
Coordinator

Prepared by:

PAUL ROMANO B. ROYO RENATO Z. CANTORIA MARUJA E. JAPSON


Project Leader Project Assistant Leader Secretary

AVELYN J. DEQUILLA NARCILITO J. HEBID


Member SPT Member

Noted:

ESTER R. SANTILLAN
Principal I