Professional Documents
Culture Documents
Watergridpaper WAPTECHjournal
Watergridpaper WAPTECHjournal
ABSTRACT
Telangana Drinking Water Supply Corporation Limited (TDWSCL) is the nodal agency for implementation of Telangana
Drinking Water Supply Project (TDWSP) in the state. TDWSP is a flagship programme of the newly constituted state of
Telangana. The Objective of the project is to ensure safe and sustainable PIPED drinking water supply from surface water
sources at 100 LPCD (litres per capita per day) for rural areas, 135 LPCD for Municipalities, 150 LPCD for Municipal
Corporations and 10% to meet Industrial requirements. The Project comprises of 26 segments in 9 districts and supply water to
62, 01,552 habitations which covers the pipeline of entire state is of about 1.697 lakh Km and it includes 19 nos. of intake
structures, 549 nos. of Over Head Balancing Reservoirs, 550 nos. of Ground Level Balancing Reservoirs & sumps, 35,573 nos.
of Village Over Head Service Reservoirs and 153 nos. of Water Treatment Plants. The Works costing of about Rs. 37813.01 Cr
has been sanctioned. All intake structures, transmission lines, WTP structures are in advance stage and are currently in very good
progress.
The project will be integrated with the existing water supply 3. OBJECTIVE OF THE PROJECT:
schemes. Balance surface water requirements will be To ensure safe and sustainable PIPED drinking water
planned from the proposed Telangana Drinking Water supply from surface water sources at:
Supply Project. The requirement of water for drinking, (i) 100 LPCD ( litres per capita per day) for rural
cooking, domestic need will be taken into account at 100 areas,
liters per capita per day (LPCD) for rural areas, 135 LPCD (ii) 135 LPCD for Municipalities
for municipalities and 150 LPCD for municipal (iii) 150 LPCD for Municipal Corporations
corporations. It is planned to supply water at the door step (iv) 10% to meet Industrial requirements
of every household.
And to provide tap connection to each household in the
The scope of the project in rural areas includes intra-village state. The pylon laid for Mission Bhagiratha scheme is
service reservoirs, construction and distribution network. It shown as below (Fig.1).
is proposed that the committees headed by village
Sarpanches with woman members will manage the rural
water supply systems. Similarly, for urban areas, water will
be supplied in bulk to specified locations and bulk metering
system will be planned to ensure accountability on the part
of local bodies. Telangana Drinking Water Supply
Corporation Limited is formed for implementation of
Telangana Drinking Water Supply Project.
2. NEED OF MISSION BHAGIRATHA: The Project comprises of 26 segments in 9 districts and the
Telangana State suffers from chronic drought conditions – Stages involved in the entire Water supply chain include;
scarcity of drinking water-deficit rainfall in 6 years during a) Sourcing water from Major rivers or reservoirs fed
last decade by these rivers
2
segments as decided by the department & o Disinfection maintains a residual to protect
Government water supply through the supply network.
viii. Site inspections and field testing of various Supplemental chlorine is added to maintain
structures (Intake wells, WTPs, Pipeline, disinfection concentrations while the water is
OHBR’s, GLBR’s, Sumps etc.) pumped through the distribution system. The
ix. Issuing of OK card system before execution purpose is to ensure minimum residual
of works at site after quality checks disinfectant levels at the farthest points of the
x. Project Monitoring & Supervision in every system.
phase of the project Transmission network:
xi. Report if any deviations and variations o The water in the supply network is
observed from the approved designs / maintained at positive required residual
drawings to the notice of the department, the pressure and velocity to ensure water reaches
Contractor and under intimation to Engineer- all parts of network ultimately to the tail end
in-Chief for appropriate action consumer.
xii. Quality Control and Assurance during
execution of works (random) 8. SIMULATION OF NETWORK FLOW BY USING EPANET:
xiii. Field tests – Inlining, outcoating of pipes, The hydraulic designs for raw water pipelines, treated water
Hydraulic test, Ultrasonic test, Radiographic mains and branches as done by Department/ TDWSCL has
test, Sieve analysis, Slump test, compressive been reviewed to ascertain the capacity of the proposed
strength etc. network for delivering the desired quantity of water at
required terminal heads to all the service areas/ habitations.
7. ELEMENTS OF WATER SUPPLY SCHEME: This requires pressure boosting stations, location of
The typical elements/components of the water supply scheme reservoirs and economical sizing of the pipelines will be
are as given below: considered with due importance while reviewing the
Source/Intake: designs.
o Intake structures are used for collecting raw
water from the surface sources such as river, Review of AutoCAD drawings of pipeline alignments i.e.,
lake and reservoir and conveying it further to preparation of LS showing levels, chainage, degree of bends
Water Treatment Plant (WTP). Raw water etc. Site plans of intakes, WTP, OHBR and OHSRs and
from a surface water lake or reservoir is water distribution networks will be done. The already
drawn into the plant through intake prepared base maps will be collected in soft and hard copy
structures. Large debris like logs are form for review to check the planning and alignment of the
prevented from entering and zebra mussel scheme. Finalization of Alignment and LS Plans for
control is performed at the intake. Pumping Mains / Gravity Mains and other Pipeline Works
WTP: including all appurtenances will be done in consultation
o Water treatment generally consists of three with department officials.
steps i.e. Aeration, Coagulation, Clarification,
Filtration and Disinfection. EPANET is a computer program that performs extended
o Aeration brings water and air in close contact period simulation of hydraulic flow (conservation of mass)
in order to remove dissolved gases (such as behavior within pressurized pipe networks. A network
carbon dioxide) and oxidizes dissolved consists of pipes, nodes (pipe junctions), pumps, valves and
metals such as iron, hydrogen sulfide, and storage tanks or reservoirs. EPANET tracks the flow of
volatile organic chemicals water in each pipe, the pressure at each node and the height
(VOCs). Aeration is often the first major of water in each tank throughout the network during a
process at the treatment plant. simulation period comprised of multiple time steps.
o In coagulation, we add a chemical such as
alum which produces positive charges to EPANET is applied at different levels i.e. Primary,
neutralize the negative charges on the Secondary and Tertiary networks. The typical distribution
particles. Then the particles can stick network of hydraulic statement by using EPANET is shown
together, forming larger particles which are below (Fig .4).
more easily removed.
o Clarification refers to the separation of
particles from the water stream. By slower
mixing, turbulence causes the flocculated
water to form larger floc particles that
become cohesive and increase in mass. This
visible floc is kept in suspension until large
enough to settle under the influence of
gravity.
o Chemical addition destabilizes the particle
charges and prepares them for
clariflocculation either by settling or floating
out of the water stream.
3
other execution activities as per the agreement
specifications and as per designs & drawings.
To ensure all the electro-mechanical equipments
construction activities including electrical sub-stations,
air vessels, valves, SCADA units, Telemetry etc as per
agreement specifications and designs & drawings.
To ensure proper pipeline trench restoration and
carting of surplus excavated soils / debris, and proper
road restoration for the project works.
To enforce strict quality control as per the
Agreement / BIS code / CPHEEO or any other
relevant codes at manufacturing premises.
To take initiation for commencement of the civil
works after satisfaction of all the start-up activities.
To monitor the quality of the work and Maintain the
records of tests of various materials such as soil,
concrete, other construction materials, Electrical and
Mechanical etc., at the site.
To develop an OK Card System, a comprehensive
check-list of all activities required for the construction
of each component of a civil structure which would be
okayed by the Engineer-in-Charge (or delegate) when
the Contractor’s Representative reports that that item
of work is ready for execution.
To ensure the maintenance of Placement registers at
site and the same will be verified and reviewed by the
consultant on daily basis. The required formats have to
be designed by the Consultant in consultation with the
Department for adoption.
Some of the site inspection photographs are shown as
below (Fig.5, 6 and 7):
4
Specification relevant Indian Standard or
internationally approved equivalent standard shall be
adopted. The tests shall be carried out prior to delivery
of the Plant and Equipment to Site.
The final inspection of the finished product shall be
commenced within 7 days from the date of receipt of
call letter from the manufacturer/ Executing agency.
The date proposed for inspection at manufacturing site
shall be finalized by the Superintending Engineer
TDWSCL concerned.
All the inspected and approved materials shall have a
distinct identification mark of the inspection agency
and such mark shall be made on each and every piece
of the item as per the purchase order, though actual
tests have been carried out on the random samples as
per IS sampling and testing procedure and furnish OK
Figure 7. Structure showing WTP, OHBR and pump house card from its side to the contractor for lifting of
materials.
10. QUALITY ASSURANCE DURING THE FACTORY INSPECTIONS OF
THE MATERIAL BY WAPCOS:
Some of the factory inspection photographs are shown as below
(Fig.8, 9 and 10):
To inspect and monitor the procurement of materials
as per standards such as pipes, valves, specials,
pumps, motors etc., manufactured for TDWSCL.
To prepare and furnish a copy of Quality Assurance/
Quality control Plan to the Department for approval
before the commencement of inspection.
To attend along with the concerned departmental
officials for pre-delivery quality control inspection of
materials at the manufacturers work site as per
guidelines issued by Department in accordance with
the specifications noted in the supply order ,QAP, and
the relevant Indian Standard Specifications prior to
certification in the presence of department officers and
the inspection shall include witnessing of tests
including the hydraulic test, performance tests, visual,
dimensional and physical checking to the finished
product as per the relevant BIS standards and review Figure 8. Inspection of MS pipe at M/s MEIL factory, Hyd
of such inspection tests internally conducted by the
supplier and as specified in TOR.
To conduct inspection during manufacturing process
for different types of pipes, specials and appurtenances
as per IS specifications and as specified in the work
agreements. In general for all the above pipes, specials
& appurtenances, the factory test broadly as follows:
Gajwel segment work was completed in a record time of 9 Some of the Gajwel segment photographs are shown as below
months and Inaguration & Commissioned by Hon’ble Prime (Fig.13, 14, 15 and 16):
Minister on 7.8.2016 and are shown as below (Fig. 11).
6
Figure 15. Over Head Service Reservoir (OHSR) at Organization, Ministry of Urban Development, Government
Malkapur of India, New Delhi.
The OFC ducts and cables are laid in the trenches along
with pipeline are shown as below (Fig.17 and 18):
13. CONCLUSIONS:
References:
1. CPHEEO 1999, a Manual on Water Supply and Treatment
by Central Public Health and Environmental Engineering