Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 7

MISSION BHAGIRATHA FOR DRINKING WATER SUPPLY IN TELANGANA STATE

B.Arunachalam1, DR. S.V.N.Rao2,

ABSTRACT
Telangana Drinking Water Supply Corporation Limited (TDWSCL) is the nodal agency for implementation of Telangana
Drinking Water Supply Project (TDWSP) in the state. TDWSP is a flagship programme of the newly constituted state of
Telangana. The Objective of the project is to ensure safe and sustainable PIPED drinking water supply from surface water
sources at 100 LPCD (litres per capita per day) for rural areas, 135 LPCD for Municipalities, 150 LPCD for Municipal
Corporations and 10% to meet Industrial requirements. The Project comprises of 26 segments in 9 districts and supply water to
62, 01,552 habitations which covers the pipeline of entire state is of about 1.697 lakh Km and it includes 19 nos. of intake
structures, 549 nos. of Over Head Balancing Reservoirs, 550 nos. of Ground Level Balancing Reservoirs & sumps, 35,573 nos.
of Village Over Head Service Reservoirs and 153 nos. of Water Treatment Plants. The Works costing of about Rs. 37813.01 Cr
has been sanctioned. All intake structures, transmission lines, WTP structures are in advance stage and are currently in very good
progress.

1. INTRODUCTION: a. Severe drought leading to ecological


Telangana Drinking Water Supply Corporation Limited imbalance.
(TDWSCL) is the nodal agency for implementation of b. Depletion of Ground water – by more than 3
Telangana Drinking Water Supply Project in the state. metres in the last 10 years.
TDWSP is a flagship programme of the newly constituted Rain shadow area increasing alarmingly, inadequate
state of Telangana. infrastructure and supply and Current Schemes also
plagued by
The State Government has embarked on a vision to provide  Fluoride affected GW sources
safe, adequate, permanent and sustainable water supply to  Prevalence of contamination leading to water
rural, urban and industrial areas by 2018. Apart from water borne diseases
for domestic use, the project is planned to meet the water  Poor Water quality
needs of commercial entities, industrial units, Special Already covered habitations slipping back to Quality
Economic Zones, etc. affected and scarcity habitations

The project will be integrated with the existing water supply 3. OBJECTIVE OF THE PROJECT:
schemes. Balance surface water requirements will be To ensure safe and sustainable PIPED drinking water
planned from the proposed Telangana Drinking Water supply from surface water sources at:
Supply Project. The requirement of water for drinking, (i) 100 LPCD ( litres per capita per day) for rural
cooking, domestic need will be taken into account at 100 areas,
liters per capita per day (LPCD) for rural areas, 135 LPCD (ii) 135 LPCD for Municipalities
for municipalities and 150 LPCD for municipal (iii) 150 LPCD for Municipal Corporations
corporations. It is planned to supply water at the door step (iv) 10% to meet Industrial requirements
of every household.
And to provide tap connection to each household in the
The scope of the project in rural areas includes intra-village state. The pylon laid for Mission Bhagiratha scheme is
service reservoirs, construction and distribution network. It shown as below (Fig.1).
is proposed that the committees headed by village
Sarpanches with woman members will manage the rural
water supply systems. Similarly, for urban areas, water will
be supplied in bulk to specified locations and bulk metering
system will be planned to ensure accountability on the part
of local bodies. Telangana Drinking Water Supply
Corporation Limited is formed for implementation of
Telangana Drinking Water Supply Project.

WAPCOS has been given the task of undertaking the


consultancy services for Vetting of DPRs, Project
Monitoring, Supervision and Quality Control of works
under TDWSP. Figure 1: Mission Bhagiratha pylon

2. NEED OF MISSION BHAGIRATHA: The Project comprises of 26 segments in 9 districts and the
Telangana State suffers from chronic drought conditions – Stages involved in the entire Water supply chain include;
scarcity of drinking water-deficit rainfall in 6 years during a) Sourcing water from Major rivers or reservoirs fed
last decade by these rivers

1. Senior Engineer, WAPCOS Ltd., Regional Office, AC Guards, Hyderabad-500 004.


2. Project Director, WAPCOS Ltd., Regional Office, AC Guards, Hyderabad-500 004.
b) Purify the raw water in nearby Water treatment No. District Segment Name
Plant. 24 Warangal HMWSSB metro segment
25 Khammam Godavari-Kothagudem segment
c) Pump treated water to the major OHSRs & Sumps 26 Khammam Palair and Wyra segments
at the highest points 5. MAIN SOURCE OF THE SCHEME:
d) Transmit from the highest point through secondary The Telangana Water Grid would depend on water
pipeline network to all the habitations by gravity resources available in Krishna & Godavari which are two
(98%) perennial rivers flowing through the state. A total of 34
e) Distribute to each house hold through a modern, TMC of water from Godavari River and 21.5 TMC from
rationalized intra village network by providing tap Krishna River would be utilized for the water grid.
connections to each household.
This scientifically designed project intends to use the
4. DETAILS OF PROJECT AREA: natural gradient wherever possible and pump water where
The entire project comprises of 26 segments in 9 districts of necessary and supply water through pipelines. The state-
Telangana state are shown as below (Fig. 2). level grid will comprise of a total of 26 internal grids. The
main trunk pipelines of this project would run about 5000
KM, and the secondary pipelines running a length of about
50000 KM would be used to fill service tanks inhabitations
and the village-level pipeline network of about 75,000 KM
would be used to provide clean drinking water to
households. The contour map of the Telangana state is
shown as below (Fig. 3).

Figure 2: Location Map of the project

The segment wise details of the project are given in Table-1.


Table 1: Segment wise details of the project

No. District Segment Name


1 Mahabubnagar Srisailam-Gudipally-Mahabubnagar
Part-I,II Primary &Secondary segment
2 Mahabubnagar Jurala segment
3 Rangareddy HMWSSB-Medchal segment Figure 3: Contour map of the Telangana state
4 Rangareddy Srisailam segment
5 Nalgonda AKBR segment 6. SCOPE OF CONSULTANCY SERVICES:
6 Nalgonda NSP Tailpond segment The scope of services specified for consultancy services are:
7 Nalgonda Nalgonda-Augmentation segment
8 Medak Singur-Narayankhed, Andole, Medak i. Vetting of already prepared DPRs, designs,
9 Medak Singur-Sangareddy segment drawings for achieving comprehensiveness of
10 Medak Singur-Narsapur segment the project.
11 Medak HMWSSB – Gajwel segment ii. Examine and finalize the planning of the
12 Nizamabad SRSP Balkonda-segment proposed water supply system, demand
13 Nizamabad Singur-Jukkal, Bhodan segment
14 Karimnagar SRSP-Korutla, Jagtial segment
calculations, hydraulic designs, general
15 Karimnagar MMD-Sircilla and Yellampally- arrangement of the system, structural
Peddapally segment components of the system, etc.
16 Karimnagar L Madugu-Manthani, Bhupalapalli iii. Vetting of DPR’s as per IS codes and
segment CPHEEO manual (1999)
17 A Karimnagar LMD-Karimnagar, Ramadugu segment
17 B Karimnagar LMD-Manakondur, Husnabad, Huzurabad iv. Vetting of Structural and Hydraulic Designs
segment v. Factory inspections (MS, DI, HDPE, PCC
18 Adilabad SRSP-Adilabad segment and BWSC pipes), Valves and Electro
19 Adilabad Komarambheem-Asifabad segment mechanical equipments
20 Adilabad Yellampally-Mancherial and Kaddem vi. Checking Hydraulic simulation for pipe
segment
21 Warangal Palair segment-17 mandals in Wgl + 1 network using EPANET / Water gems
mandal Kmm districts software for optimization
22 Warangal Godavari-Mangapet vii. The review service shall be in phased
23 Warangal LMD-Manakondur extn-parkal, Ghanpur, manner based on the priority of the
Warangal

2
segments as decided by the department & o Disinfection maintains a residual to protect
Government water supply through the supply network.
viii. Site inspections and field testing of various Supplemental chlorine is added to maintain
structures (Intake wells, WTPs, Pipeline, disinfection concentrations while the water is
OHBR’s, GLBR’s, Sumps etc.) pumped through the distribution system. The
ix. Issuing of OK card system before execution purpose is to ensure minimum residual
of works at site after quality checks disinfectant levels at the farthest points of the
x. Project Monitoring & Supervision in every system.
phase of the project  Transmission network:
xi. Report if any deviations and variations o The water in the supply network is
observed from the approved designs / maintained at positive required residual
drawings to the notice of the department, the pressure and velocity to ensure water reaches
Contractor and under intimation to Engineer- all parts of network ultimately to the tail end
in-Chief for appropriate action consumer.
xii. Quality Control and Assurance during
execution of works (random) 8. SIMULATION OF NETWORK FLOW BY USING EPANET:
xiii. Field tests – Inlining, outcoating of pipes, The hydraulic designs for raw water pipelines, treated water
Hydraulic test, Ultrasonic test, Radiographic mains and branches as done by Department/ TDWSCL has
test, Sieve analysis, Slump test, compressive been reviewed to ascertain the capacity of the proposed
strength etc. network for delivering the desired quantity of water at
required terminal heads to all the service areas/ habitations.
7. ELEMENTS OF WATER SUPPLY SCHEME: This requires pressure boosting stations, location of
The typical elements/components of the water supply scheme reservoirs and economical sizing of the pipelines will be
are as given below: considered with due importance while reviewing the
 Source/Intake: designs.
o Intake structures are used for collecting raw
water from the surface sources such as river, Review of AutoCAD drawings of pipeline alignments i.e.,
lake and reservoir and conveying it further to preparation of LS showing levels, chainage, degree of bends
Water Treatment Plant (WTP). Raw water etc. Site plans of intakes, WTP, OHBR and OHSRs and
from a surface water lake or reservoir is water distribution networks will be done. The already
drawn into the plant through intake prepared base maps will be collected in soft and hard copy
structures.  Large debris like logs are form for review to check the planning and alignment of the
prevented from entering and zebra mussel scheme. Finalization of Alignment and LS Plans for
control is performed at the intake. Pumping Mains / Gravity Mains and other Pipeline Works
 WTP: including all appurtenances will be done in consultation
o Water treatment generally consists of three with department officials.
steps i.e. Aeration, Coagulation, Clarification,
Filtration and Disinfection. EPANET is a computer program that performs extended
o Aeration brings water and air in close contact period simulation of hydraulic flow (conservation of mass)
in order to remove dissolved gases (such as behavior within pressurized pipe networks. A network
carbon dioxide) and oxidizes dissolved consists of pipes, nodes (pipe junctions), pumps, valves and
metals such as iron, hydrogen sulfide, and storage tanks or reservoirs. EPANET tracks the flow of
volatile organic chemicals water in each pipe, the pressure at each node and the height
(VOCs). Aeration is often the first major of water in each tank throughout the network during a
process at the treatment plant. simulation period comprised of multiple time steps.
o In coagulation, we add a chemical such as
alum which produces positive charges to EPANET is applied at different levels i.e. Primary,
neutralize the negative charges on the Secondary and Tertiary networks. The typical distribution
particles. Then the particles can stick network of hydraulic statement by using EPANET is shown
together, forming larger particles which are below (Fig .4).
more easily removed.
o Clarification refers to the separation of
particles from the water stream. By slower
mixing, turbulence causes the flocculated
water to form larger floc particles that
become cohesive and increase in mass.  This
visible floc is kept in suspension until large
enough to settle under the influence of
gravity.
o Chemical addition destabilizes the particle
charges and prepares them for
clariflocculation either by settling or floating
out of the water stream.

3
other execution activities as per the agreement
specifications and as per designs & drawings.
 To ensure all the electro-mechanical equipments
construction activities including electrical sub-stations,
air vessels, valves, SCADA units, Telemetry etc as per
agreement specifications and designs & drawings.
 To ensure proper pipeline trench restoration and
carting of surplus excavated soils / debris, and proper
road restoration for the project works.
 To enforce strict quality control as per the
Agreement / BIS code / CPHEEO or any other
relevant codes at manufacturing premises.
 To take initiation for commencement of the civil
works after satisfaction of all the start-up activities.
 To monitor the quality of the work and Maintain the
records of tests of various materials such as soil,
concrete, other construction materials, Electrical and
Mechanical etc., at the site.
 To develop an OK Card System, a comprehensive
check-list of all activities required for the construction
of each component of a civil structure which would be
okayed by the Engineer-in-Charge (or delegate) when
the Contractor’s Representative reports that that item
of work is ready for execution.
 To ensure the maintenance of Placement registers at
site and the same will be verified and reviewed by the
consultant on daily basis. The required formats have to
be designed by the Consultant in consultation with the
Department for adoption.
Some of the site inspection photographs are shown as
below (Fig.5, 6 and 7):

Figure 4. Typical distribution network by using EPANET

9. QUALITY ASSURANCE DURING THE SITE INSPECTIONS OF THE


STRUCTURES AND PIPELINE WORKS BY WAPCOS:
 To ensure all other civil structures construction
activities such as on going Intake structures, treatment
plant units, clear water reservoirs, raw water sumps,
pumping stations, watchman quarters, compound
walls, cross drain works, thrust blocks, bridges,
railway crossings, NH crossings, raw water intake
channels etc as per the agreement specifications duly Figure 5. Intake well at SRSP near Velmal, SRSP Adilabad
checking the reinforcement, centering, shuttering and segment
scaffolding before the concreting for Concreting
works as per designs & drawings.
 To check all designs and drawings submitted by the
agencies during the course of execution of work for
various components and their translation to ground (X,
Y and Z corodinates)
 To ensure that all critical components of the structures
such as foundations, Floor Slabs, Bottom Slab, Side
walls etc. including placement of reinforcement as
structural designs and Bar bending schedules.
 To ensure the laying of pipe line net work laying
works as per the approved alignment.
 To ensure the pipeline excavated trench dimensions,
bedding, laying, jointing, welding, ultrasonic testing, Figure 6. Laying of MS pipeline, Yellore segment in
radio graphic testing, hydraulic testing etc and all progress

4
Specification relevant Indian Standard or
internationally approved equivalent standard shall be
adopted. The tests shall be carried out prior to delivery
of the Plant and Equipment to Site.
 The final inspection of the finished product shall be
commenced within 7 days from the date of receipt of
call letter from the manufacturer/ Executing agency.
The date proposed for inspection at manufacturing site
shall be finalized by the Superintending Engineer
TDWSCL concerned.
 All the inspected and approved materials shall have a
distinct identification mark of the inspection agency
and such mark shall be made on each and every piece
of the item as per the purchase order, though actual
tests have been carried out on the random samples as
per IS sampling and testing procedure and furnish OK
Figure 7. Structure showing WTP, OHBR and pump house card from its side to the contractor for lifting of
materials.
10. QUALITY ASSURANCE DURING THE FACTORY INSPECTIONS OF
THE MATERIAL BY WAPCOS:
Some of the factory inspection photographs are shown as below
(Fig.8, 9 and 10):
 To inspect and monitor the procurement of materials
as per standards such as pipes, valves, specials,
pumps, motors etc., manufactured for TDWSCL.
 To prepare and furnish a copy of Quality Assurance/
Quality control Plan to the Department for approval
before the commencement of inspection.
 To attend along with the concerned departmental
officials for pre-delivery quality control inspection of
materials at the manufacturers work site as per
guidelines issued by Department in accordance with
the specifications noted in the supply order ,QAP, and
the relevant Indian Standard Specifications prior to
certification in the presence of department officers and
the inspection shall include witnessing of tests
including the hydraulic test, performance tests, visual,
dimensional and physical checking to the finished
product as per the relevant BIS standards and review Figure 8. Inspection of MS pipe at M/s MEIL factory, Hyd
of such inspection tests internally conducted by the
supplier and as specified in TOR.
 To conduct inspection during manufacturing process
for different types of pipes, specials and appurtenances
as per IS specifications and as specified in the work
agreements. In general for all the above pipes, specials
& appurtenances, the factory test broadly as follows:

o Materials check for its suitability as per


specifications
o Check of design parameters during
manufacturing process,
o Visual inspection, Appearance and Workmanship,
o Dimensions of pipes, Physical and chemical
characteristics, Figure 9. Inspection of sluice gates at M/s Oriental Castings
o Mechanical properties / Hydrostatics factory, New Delhi
characteristics / impact strength,
o Marking and other respective test as per relevant
IS, Sampling shall be done as per relevant IS
method
 Any equipment used in the testing of the Plant and
Equipment in all respects comply with the appropriate
safety regulations and/or requirements regarding
electrical apparatus for the safety of the Plant and the
men working thereon.
 All inspection and testing will be carried out in
accordance with the Specification and in absence of
5
The salient features of the project are:
Primary segment:
 OHBR’s - 6 Nos. (90, 150, 220 & 550 KL)
 Sumps - 6 Nos. (200, 300, 725, 1600, 4200 & 14000 KL)
 MS Pipe Line - 9.65 KM (1200 mm dia, 12 to 16 mm
thick)
 DI Pipe Line - 363.23 KM (100 mm to 900 mm dia)
 HDPE Pipe Line - 1915.26 KM (63 mm to 280 mm dia)
Secondary segment:
 Secondary & Intra network Segment consisting of 6
mandals are Jagdevpur Mandal, Gajwel Mandal, Toopran
Mandal, Wargal Mandal, Mulugu Mandal, Kondapak
Mandal
 All the above mandals are to be provided with Over Head
Figure 10. Inspection of valves at M/s KBL factory, Pune Service Reservoirs for various capacities (20, 40, 60, 90,
100, 120, 150 KL) – 149 No’s in total
11. COMPLETION OF GAJWEL SEGMENT:  House Service Connection – 71,399 Nos.

Gajwel segment work was completed in a record time of 9 Some of the Gajwel segment photographs are shown as below
months and Inaguration & Commissioned by Hon’ble Prime (Fig.13, 14, 15 and 16):
Minister on 7.8.2016 and are shown as below (Fig. 11).

Figure 13. Laying and Jointing of DI pipeline

Figure 11. Gajwel segment commissioned by Hon’ble Prime


Minister Sh. Narenda Modi on 7th August, 2016

It covers the population of 3.350 lakhs, households of 0.78


lakhs and Habitations / ULBs of 244. The flow diagram of
Gajwel segment is shown as below (Fig.12):

Figure 14. House service connections – Fixing of Saddle

Figure 12. Flow diagram of Gajwel segment

6
Figure 15. Over Head Service Reservoir (OHSR) at Organization, Ministry of Urban Development, Government
Malkapur of India, New Delhi.

Figure 16. Supply of water to the household

12. LAYING OF OPTICAL FIBRE CABLE (OFC) NETWORK:

To take advantage of ongoing Mission Bhagiratha project


involving laying of pieplines in trenches all over Telangana
state, the government decided to integrate OFC cabling so
as to extend internet facility for multiple objectives. This
will benefit the common man in rural areas for e-learning,
e-health and e-governance etc,.

The OFC ducts and cables are laid in the trenches along
with pipeline are shown as below (Fig.17 and 18):

Figure 17. OFC Duct procured at Site

Figure 18. Laying of OFC Duct along with water pipe

13. CONCLUSIONS:

The Mission Bhagiratha a flagship project of Telangana state is


making tremendous physical progress without any dearth of
funds. The project has become exemplary for many other states
to emulate. The government of Tamilnadu, Uttar Pradesh,
Maharashtra and West Bengal are now planning to take up this
project in their states.

References:
1. CPHEEO 1999, a Manual on Water Supply and Treatment
by Central Public Health and Environmental Engineering

You might also like