PROJECT CHARTER

Project Name: Age Estimation Project Number:01


and Detection System

Date:10/27/2022 Revision Number:0

1. PROJECT GOALS

1. This system will be deploying in themes park to detect age of children and suggest them their
best ride
2. This system will help to understand what products and services different customer groups
want and can afford
3. Target marketing campaigns more precisely and thus reduce the cost per lead or sale

2. DELIVERABLES

1. Project Proposal
2. SRS Document
3. Use Case Document
4. System Design
5. User Interface
6. Integrated interface with CNN model
7. Integrated interface with CNN model and Database
8. Test Report
9. Project Report

For Internal Use Only Page 1


3. SCOPE DEFINITION

The project will include:

1. Admin will be able to interact through desktop application


2. CNN architecture to predict the age group human’s face
3. Admin will be able to capture an image of person sitting in front of him
4. The Image captured will be sent to model for prediction of age. Picture shall be converted from RGB to
Greyscale.
5. For the back end, MySQL data base will be used to store images and the results of model.
6. If age is not predicted by the model, system will use the information to figure the age of person, and
store that information in database for future use

The project will not include:


1. System will not predict age with 100% of accuracy
2. System will not predict gender of any person

4. PROJECT MILESTONES

Milestones Start Date End Date


System Prototype 7/01/2022 8/9/2022
Detection of an image 9/03/2022 10/15/22
Interface design 10/29/2022 11/2/2022
Database Design 11/4/2022 12/12/2022
Integration of database 12/062022 01/6/2023
and interface
Perform Testing 01/09/2023 2/7/2023
Deployment of the 2/08/2023 03/10/23
System
FYP Report 03/16/2023 04/03/2023

For Internal Use Only Page 2


5. ASSUMPTIONS, CONSTRAINTS & DEPENDENCIES

1. List any constraints (potential factors that will impact the delivery or make it difficult
to manage the project) on the project or dependencies on resources or funding to
the project. Consider time, cost, dates and regulatory issues as constraints or
dependencies to the project.
2. User shall be able to know the basics of using the computer specifically the desktop
applications.
3. User should be literate enough in computers.
4. Hardware should be with higher specifications.
5. If any of our member resigns there may be delay in deliverable.
6. If new features are to be added, this will affect the cost, time and scope of project
7. For example, if customer wants to implement gender as well. It can bring impact on
the scope as well as cost of system. That will take a lot of extra time and resources.

6. RELATED DOCUMENTS

Proposal:

Proposal Presentation:

For Internal Use Only Page 3


7. PROJECT ORGANIZATIONAL STRUCTURE

Identify the key stakeholders and team members by function, name and role.

Function Name Role

Team Lead Arusa Kanwal Supervisor


Software Engineer Gul Fayaz Rumi Documentation
Development
Developer Mamoon Zafar Programmer

8. PROJECT AUTHORIZATION

Approved by: Project Supervisor Date


28/10/2022

Approved by: Project Manager Date


28/10/2022