Floor Schedule (Stonework)
Floor Schedule (Stonework)
Floor Schedule (Stonework)
MATERIAL TARGET START TARGET END TARGET TARGET TARGET START TARGET END
DURATION DURATION DURATION
Item Description LEADTIME DATE DATE START DATE END DATE DATE DATE REMARKS
1 Bar Lounge LOCAL READY 6/1/2023 16/1/2023 9 30/1/2023 14/2/2023 14 15/2/2023 25/2/2023 10
2 Pool Area LOCAL READY 6/1/2023 16/1/2023 9 30/1/2023 14/2/2023 14 15/2/2023 25/2/2023 10
3 Lift Lobby + Internal lift LOCAL READY 6/1/2023 16/1/2023 9 30/1/2023 14/2/2023 14 15/2/2023 25/2/2023 10
MATERIAL TARGET START TARGET END DURATION TARGET TARGET DURATION TARGET START TARGET END DURATION
Item Description LEADTIME DATE DATE START DATE END DATE DATE DATE REMARKS
GROUND FLOOR
2.11 (a) ST28 - 18mm Ice White, polish
1 Living Area LOCAL READY 6/1/2023 16/1/2023 9 30/1/2023 14/2/2023 14 15/2/2023 25/2/2023 10
2 Corridor & Dining Area LOCAL READY 6/1/2023 16/1/2023 9 30/1/2023 14/2/2023 14 15/2/2023 25/2/2023 10
3 Foyer LOCAL READY 6/1/2023 16/1/2023 9 30/1/2023 14/2/2023 14 15/2/2023 25/2/2023 10
4 Staircase LOCAL READY 6/1/2023 16/1/2023 9 30/1/2023 14/2/2023 14 15/2/2023 25/2/2023 10
MATERIAL TARGET START TARGET END DURATION TARGET TARGET DURATION TARGET START TARGET END DURATION
Item Description LEADTIME DATE DATE START DATE END DATE DATE DATE REMARKS
FIRST FLOOR
2.17 (a) ST28 - 18mm Ice White, polish
1 General Corridor 13/2/2023 6/1/2023 16/1/2023 9 30/1/2023 14/2/2023 14 15/2/2023 25/2/2023 10