Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Technical Paper

QUALITY CONTROL AND QUALITY ASSURANCE IN BITUMINOUS


ROAD CONSTRUCTION IN INDIA

Prithvi Singh Kandhal1 Rajan Choudhary2 Abhinay Kumar3

ABSTRACT
Implementation of Quality Control and Quality Assurance (QC/QA) is necessary to ensure consistent and quality
bituminous road construction in India. It should replace the present system of generally reporting “passing” test
results only during construction, which is unacceptable and leads to premature failures.
Quality control is the responsibility of the construction contractor who should prepare and execute a QC plan for the
bituminous paving project. Quality assurance is the responsibility of the owner (such as NHAI, representative of NHAI,
or a concessionaire). For quality assurance paving project is first divided into lots and sublots. Quality assurance is
done with the help of Percent Within Limits (PWL) and pay factors (price adjustments), which are determined for
each lot from test values of sublots.
This paper describes the QC/QA system in detail and the way it should be implemented in India after some pilot
projects. For QA a computer software program based on Excel has been developed at IIT Guwahati exclusively for
this paper and is available online. With this program it is quite easy to calculate the mean, standard deviation, and
PWL once the five sublot test results are entered along with the minimum and maximum specified limits for the test
parameter.

1. INTRODUCTION 2. CURRENT SCENARIO OF QC/QA IN INDIA


Experience in the developed countries such as the US There is no well-established system existing for
has shown that implementation of Quality Control proper Quality Control/Quality Assurance (QC/QA)
(QC) and Quality Assurance (QA) concept is necessary for bituminous construction in India. Quality Control
to obtain consistent and good quality bituminous (QC) involves preparation and execution of a QC Plan
road construction. QC and QA have been defined by
by the contractor. Quality Assurance (QA) involves
AASHTO as follows[1].
quality check and acceptance/rejection of the project
Quality Control: The activities that have to do with lots by the owner. Both QC and QA are not practiced in
making the quality of a product what it should be. It is
India in a desirable manner, which is the subject of this
the responsibility of the construction contractor.
paper. The two main types of concession agreements
Quality Assurance: The activities that have to do with followed presently in India for construction of major
making sure that the quality of a product is what it
highway projects are: (1) Engineering, Procurement
should be. It is the responsibility of the highway agency
and Construction (EPC) agreement, and (2) Hybrid
such as National Highway Authority of India.
Annuity (HA) agreement.
The QC/QA concept is new for India and needs to
be implemented as soon as possible to assure quality Under the EPC agreement, the construction period is
bituminous road construction. There is hardly any usually 2 years and defect liability/maintenance period
quality assurance system in place in India at the present is 5 years, whereas in the HA mode the construction
time, which is unacceptable. period is usually 3 years and defect liability/maintenance

1
Associate Director Emeritus, National Center for Asphalt Technology, Auburn University, USA. Currently in Jaipur,
E-mail: pkandhal@gmail.com
2
Associate Professor, Department of Civil Engineering, IIT Guwahati, E-mail: rajandce@iitg.ernet.in
3
PhD Research Scholar, Department of Civil Engineering, IIT Guwahati, E-mail: abhinayk29@gmail.com

INDIAN HIGHWAYS│OCTOBER 2018 11


Technical Paper

period is 10/12 years. About 90 percent of the total through an independent test/process (supposed to be
construction cost in EPC agreement is regulated by the included under QA), they usually act as “witness” to
government and is paid to contractor in 4 installments tests/checks carried out by the construction contractor.
of 5-6 months each, and the remaining 10 percent is Moreover, in the existing specification/concession
paid during the defect liability period. In the HA mode, agreements, there are no clear guidelines on the
40 percent cost is regulated by the government and acceptance/rejection criteria for any variability in
is paid during the construction period. Remaining 60 the production and construction process. (This paper
percent of the project cost, which was borne by the provides such reasonably clear guidelines.] Under
concessionaire during the construction period, is paid this scenario, contractors or sub-contractors have a
on bi-annual basis during the defect liability period in tendency to bring/ensure all the results (through fair or
installments. unfair means) within the specified ranges or acceptable
As per the Indian specifications and concession limits.They are afraid of some action by the owner if
agreement provisions, QC aspects are to be ensured a result outside the tolerances is reported. This has
through the concessionaire, contractor as well by an been observed by the first author while investigating
independent body. The independent body is called some premature failures of national highways in India.
Authority Engineer in case of EPC agreement and All construction records were of no use because they
showed passing results only despite the fact that NHAI
Independent Engineer in case of the HA mode.
had an Independent Engineer (IE) to oversee the
Most contractors follow the MoRTH Specifications construction quality.
and the Indian Roads Congress Standard
It must be realized that variations in test results of
IRC:111-2009 for Dense Graded Bituminous Mixes,
bituminous mixes is quite natural and common. Test
which specifies the minimum frequency of tests to be
results can be affected by the inherent variability of
performed by the contractor during production and
the materials; asphalt mix; sampling errors; and testing
laying of bituminous mixes[2]. Some examples are as
errors. For example, a segregated hot mix sample can
follows:
decrease or increase the bitumen content test value from
Bitumen content and 3 tests for each 400 tons of what the real value is[3]. Therefore, it is common that
gradation mix (minimum 2 per day) some test results may be outside the tolerance limits of
Marshall tests including 3 tests for each 400 tons of the specifications. The proposed QA process will help
mix (minimum 2 per day) to address such expected variations in bituminous road
voids analysis and & flow construction[4].
Density in the field after 1 test per 700 sq m area 3. MOVE TOWARDS STATISTICAL QA
compaction
SPECIFICATIONS
Specifications provide tolerance limits for the Job-Mix
Formula (JMF) parameters such as follows:
As mentioned earlier, the system in-place in India at
the present time for QA is based on tests performed
Bitumen content ±0.3 %
under QC program, mainly on single samples (so-called
Gradation Varies according to sieve ‘representative’ samples) on the basis of which decision
size (as given in MoRTH is made whether to accept or reject the material/process.
5th Revision)
In cases where results are not found to be within the
Compaction in field Minimum 92% of specified upper and lower limits, additional samples
maximum specific gravity called ‘check’ or ‘confirmatory’ samples are tested. It
of mix
cannot be denied that the existing system creates a lot of
QA should be carried out by the owner (such as NHAI, confusion amongst the agencies responsible for QC/QA
its representative or concessionaire). This aspect of QA regarding judging the overall quality. Therefore, there
is essentially missing currently in India. Agencies that is an urgent need to shift from the current ‘pass or fail’
are responsible for QA rely on the QC process alone. system to a more rational system based on statistical
Under current practice, the owner such as NHAI or its analysis of the results obtained. The statistically based
representative “certify” all the tests/processes/checks QA system will be described in detail, the QC System
done for QC. Instead of ensuring the quality of work is presented first.

12 INDIAN HIGHWAYS│OCTOBER 2018


Technical Paper

3.1 Quality Control by Contractor


Quality Control (QC), also known as “process control”,
is the responsibility of construction contractor. Before
beginning the production of bituminous mixes,
contractor must test all the source (constituent)
materials such as coarse aggregate; fine aggregate; filler
(if any); and paving bitumen and get them approved by
the owner (usually government agency). Then a Job-
Mix Formula (JMF) is developed and approved by the
owner.
The contractor develops a Quality Control (QC) plan
to ensure JMF is reproduced by the hot mix plant with Fig. 2. Control Chart for Air Voids in Compacted
specified tolerances. The QC Plan must include: Marshall Specimens(5)
● Frequency of sampling and testing Control charts offer the following benefits:
● Steps to keep the process under control; to quickly ● Early detection of an impending problem,
determine when process has gone out of control;
● Identify the cause(s) of problem from other control
and to respond adequately to bring the process charts,
back under control
● Decrease variability,
The frequency of sampling and testing is not generally ● Decrease inspection frequency, and
dictated by the owner. Usually it is more than that ● Reduce potential rejection/price adjustments by
recommended by the owner to avoid potential rejection/ the owner
price adjustments.
Control charts help to identify (diagnose) the cause(s)
The owner usually does require that control charts of the problem and to take necessary measures to bring
are maintained by the contractor for process control. the process under control. For example, if the air voids
Outline of a control chart showing upper and lower in the compacted Marshall specimens are on the low
specification limits is given in Fig. 1[5]. Whenever a test side it could be due to high bitumen content and/or
value is obtained it is plotted on the control chart just change in gradation (especially excessive amounts of
like a patient’s body temperature chart maintained in a 0.075 mm material) noted on those respective control
hospital. charts.
3.2 Quality Assurance (QA) by Owner
Quality assurance is the responsibility of the owner
(usually the government agency or its representative)
who determines whether the quality of the product is
what it should be. QA is not based on testing a few
samples per day, which is the case in India at the present
time. If one sample fails it is difficult to quantify the
quality of the paving project. Let’s consider an example.
On a national highway project, the JMF bitumen content
Fig. 1 Typical Control Chart(5)
was established at 5.2 ± 0.3 percent (range of 4.9 to
5.5 percent). Five bitumen contents were determined
Control charts are maintained for bitumen content; on a 2-km section of this highway: 5.1, 4.8, 5.2, 5.3,
gradation (all sieves); Marshall stability and flow; and 5.4 percent. Only one of the bitumen contents
void parameters such as air voids, VMA (voids (4.8%) is outside the acceptable tolerance limits. What
in mineral aggregate), VFB (voids filled with does it mean? Should the paving of the entire 2-km
bitumen); theoretical maximum specific gravity section be rejected based on one test result? Should
of mix, Gmm. Control chart for air voids is shown in more additional samples be taken at the same or nearby
Fig. 2. location until bitumen content passes?

INDIAN HIGHWAYS│OCTOBER 2018 13


Technical Paper

This is where statistics is used without any bias as a tool If so desired by the contractor, the owner or his
to make informed decisions and to resolve disputes. representative can split the loose hot mix and provide
Statistical tools such as mean, standard deviation, one-half to the contractor for verification.
normal distribution curve, Percent Within Limits In the statistically based quality evaluation system, two
(PWL), and pay factors are used for quality assurance. or three important quality parameters are selected for
Therefore, QA is conducted on a statistically based testing and evaluation. This is because so many test
quality evaluation system. A detailed discussion of this parameters such as bitumen content; gradation on all
statistical approach follows. sieve sizes; Marshall test void parameters, stability
For acceptance purposes, the paving project is divided and flow; and in-situ density after compaction, make
into lots and sublots. A ‘lot’ means a quantity of the process rather complex. Moreover, many test
material produced from a single source under similar parameters are correlated with each other and there is
conditions. In the context of asphalt pavement, it no need to test all of them.
typically represents asphalt mix production in a single The following three test parameters are widely used for
day. It can also be a specified tonnage such as 400 tons. acceptance and price adjustments and are considered
The project is accepted on lot by lot basis. If one lot reasonably adequate:
is substandard, the contractor is penalized with price ● Bitumen content
adjustment or rejection of that lot only, rather than the ● Air voids in the compacted Marshall specimens
whole project. This reduces the risk for both contractor ● Percent compaction in the field based on maximum
and owner. specific gravity of mix
Sublots are divisions of a lot used for sampling purposes Proper bitumen content is necessary for the performance
and may be of an approximate length of 100-150 m of of the bituminous pavement. Excessive bitumen
bituminous paving. Generally, 5 sublots are considered content would result in bleeding and/or rutting whereas
within a lot. Samples are taken from each sublot for deficient bitumen content would significantly reduce
performing tests such as bitumen content, gradation, the durability of the bituminous pavement[5]. Proper
and Marshall Test. Sampling within the sublot is done air void content in the compacted Marshall specimens
at random by using X and Y coordinates obtained from is also important for the performance of the pavement.
a table of random numbers. If random locations are Air void content of less than 3 percent increases the
selected within the whole lot, they may not be spread potential for rutting whereas air void content above
out as shown in top of Figure 3. Rather, a stratified 5 or 6 percent increases the potential for premature
sampling plan is adopted in which a lot is divided into aging (oxidation) of the bituminous pavement, which
5 equal sublots and then one random sample is obtained may also induce raveling and stripping. Laboratory
from each sublot as shown in bottom of Fig. 3. Such a air voids also indirectly control the mix composition
sampling plan is adopted for obtaining loose bituminous (bitumen content and gradation of aggregate). Percent
mix behind the paver for determining mix composition compaction in the field is the single most important
(bitumen content and gradation) or obtaining cores for test parameter for the performance of bituminous
determining compaction level. Alternatively, loose mix pavement. The composition of bituminous mix may be
perfect but deficient compaction (high air voids in the
can also be collected at random from trucks leaving the
mat) is likely to cause premature deterioration of the
hot mix plant based on time or tonnage.
bituminous pavement such as raveling and potholes.
After the five sublot samples representing one lot are
tested for the desired parameter(s), the test values are
analyzed statistically to determine the percentage of
this lot which is within specified tolerance limits, that
is, Percent Within Limits (PWL).
Based on the mean and standard deviation of the 5
results, a normal distribution curve is fit to the data. A
normal distribution curve is a ‘bell-shaped’ symmetric
curve that describes the statistical distribution of
engineering measurements, such as asphalt binder
Fig. 3 Sampling from Lots and Sublots content, mix density, or gradation data of bituminous

14 INDIAN HIGHWAYS│OCTOBER 2018


Technical Paper

mixes. Fig. 4 shows two normal distribution curves is requirement of % compaction in the field, which is
‘a’ and ‘b’. Observe that both curves have the same 92% minimum of the mix theoretical maximum specific
mean but the standard deviation for ‘b’ is larger than gravity, Gmm.
‘a’, due to which curve ‘b’ has higher spread or scatter
Referring to Fig. 5, PD is defined as the area (expressed
than curve ‘a’. In other words, curve ‘b’ represents high
as percent of the total) under the normal curve lying
variability.
outside (either towards left or right or both) of the
Using the specifications limits, the fitted normal specified upper and lower limits. Consequently, PWL
distribution curve, is further used to compute two can be defined as per Equation 1:
parameters: percent defective (PD) and percent within
limits (PWL). PD indicates percentage of a lot falling PWL = 100 – (PDU + PDL); for double-limit (1a)
outside the specification limits. PWL, on the other PWL = 100 – PD; for single-limit (1b)
hand, indicates percentage of the lot conforming to the
For a fitted normal distribution, the quantities PD and
specification limits. Fig. 5 illustrates the concepts of PD
PWL can be calculated using any convenient software
and PWL for two cases of double-limit and single-limit
specifications. An example of double-limit specification such as MS Excel. Excel includes an in-built function
is the requirement of design binder content to be in the NORMDIST that computes area under a normal
range of ± 0.3% from optimum distribution curve from negative infinity to a given
value with a given mean and a standard deviation.
A computer software program based on Excel has been
developed at IIT Guwahati exclusively for this paper. It
is very easy to use and can be accessed at the following
internet link to calculate the mean, standard deviation,
and PWL once the five sublot test results are entered
along with the minimum and maximum specified limits.
The link for the program developed at IITG is:
http://www.iitg.ac.in/rajandce/homepage/index.html#
Fig. 4 Normal Distribution Curves
[click on “Other Contributions” tab]
4. ILLUSTRATIVE EXAMPLES ON PWL
CALCULATIONS
The following two examples of binder content and %
compaction in the field have been worked out using the
software mentioned above. Review of reported sublot
test values and calculated PWL should familiarize the
reader with the expected trends. To obtain high PWL
(a) Double-Limit Specification values, a lot (with lower and upper limits) should have
the sample mean close to the target (such as JMF binder
content) and low standard deviation (less spread). If
any one condition is not met, PWL is likely to be lower.
4.1 Example 1 on Binder Content
Table 1 gives the binder content test values for 7 lots
(Lot A through Lot G) each lot consisting of 5 sublots.
Figs. 7, 8, 9, and 10 show the normal distribution
curves along with specified low and high limits for
binder content. Lot A represents a case when a good
(b) Single-Limit Specification
quality control is maintained as seen from the mean
Fig. 5 Concept of PD and PWL (same as the optimum binder content of 5.0 %) and a
binder content of 5% (say), i.e. lower limit = 4.7%; upper low standard deviation. For this case, the PWL is 98.4%
limit = 5.3%. An example of single-limit specification (Fig. 6).

INDIAN HIGHWAYS│OCTOBER 2018 15


Technical Paper
Table 1 PWL Data for Binder Content Lot D and Lot E represent the cases when the binder
(Target: 5%, Lower Limit: 4.6%; Upper Limit: 5.4%) contents are found within the limits but with a high
spread (standard deviation of 0.44), which also results
  Lot A Lot Lot C Lot D Lot Lot F Lot G in low PWL values of about 63 percent (Fig. 8).
B E
Results: 4.9 4.70 5.30 4.6 4.6 4.5 5.1
  5.0 4.70 5.20 4.6 4.6 4.9 5.2
4.8 4.70 5.30 5.4 4.6 5.0 5.0
5.1 4.80 5.50 5.4 5.4 5.2 4.9
5.2 4.50 5.30 5.4 5.4 5.1 5.5
Mean 5.0 4.7 5.3 5.1 4.9 4.9 5.1
Std Dev 0.17 0.11 0.11 0.44 0.44 0.27 0.23
PDU, % 0.96 0.00 23.26 23.26 13.67 4.43 12.94
PDL, % 0.64 23.26 0.00 13.67 23.26 10.41 0.95
PWL,% 98.4 76.7 76.7 63.1 63.1 85.2 86.1
Fig. 8 Normal Distribution Curve for Binder Contents for
Lot D (Firm) and Lot E (Dotted)
Lot F and Lot G represent two cases where the binder
contents have mean near 5.0% (the OBC) with PWL
of around 85% even though in both cases, one binder
content (4.5% in Lot F, and 5.5% in Lot G) is however
outside the limits (Fig. 9).

Fig. 6 Normal Distribution Curve for Bitumen Content (Lot A)

Lot B represents a case where the values are near to the


lower specification limit of 4.6%, and one sublot result
fails to meet the minimum limit of 4.6% (Fig. 7).
Fig. 9 Normal distribution curve for binder contents for Lot
F (firm) and Lot G (dotted)
4.2 Example 2 on Percent Compaction
Table 2 gives the percent compaction data for 5 lots
(Lot A through Lot E), each lot consisting of 5 sublots.
Figs. 10, 11, 12, and 13 show the normal distribution
curves along with the minimum acceptable compaction
level (92% of mix Gmm).
Table 2 PWL Data for Percent Compaction
(Target: Minimum 92% of Mix Gmm)
  Lot A Lot B Lot C Lot D Lot E
Results: 92.2 93.0 91.0 92.0 92.3
Fig. 7 Normal Distribution Curve for Binder Contents for
91.0 91.0 91.0 94.0 92.2
Lot B (Firm) and Lot C (Dotted) 92.5 93.5 95.8 94.5 92.4
Lot C represents a case where the values are near to the 93.0 93.0 96.0 93.0 92.8
93.0 93.0 95.4 94.0 93.3
upper specification limit of 5.4%, and one sublot result Mean 92.3 92.7 93.8 93.5 92.6
exceeds the maximum limit of 5.4%. In both cases Std Dev 0.82 0.97 2.60 1.00 0.45
(Lot B and Lot C), the PWL remains almost the same PD, % 34.0 23.6 24.0 6.7 9.3
(Fig. 7), but is lower than that in the Lot A. PWL, % 66.0 76.4 76.0 93.3 90.7

16 INDIAN HIGHWAYS│OCTOBER 2018


Technical Paper

For Lot A, one compaction result is failing (91%)


and all others are very close to the limit (92%). With
this combination, one is able to get PWL greater than
65 percent (Fig. 10). Lot B represents a scenario similar
to lot A (one result failing, 91%), however remaining
compaction results are well-above the 92% minimum
limit (Fig. 11). A PWL of 76.4% is obtained in this case.

Fig. 13 Normal Distribution Curve for Percent Compaction


for Lot D (Firm) and Lot E (Dotted)

4.3 Outlier Values


Sometimes it is observed that one sublot has a
questionable test value which is very different from
the remaining 4 test values. It can be an outlier which
can be established by routine statistical analysis of the
Fig. 10 Normal Distribution Curve for Percent Compaction 5 test values. There can be some assignable cause for
for Lot A such outlier, which should be investigated in the field.
In such cases, the normal distribution should be based
on the remaining 4 test values.
5. PAY FACTORS BASED ON PWL
Once the PWL is determined for each lot, the
contractor is paid based on it. States in the US have
different tables for pay factors based on PWL.
Table 3 is one example. Pay Factor (PF) is the
percentage of contract cost to be paid to the contractor
Fig. 11 Normal Distribution Curve for Percent Compaction for a Lot based on its quality evaluation. Many states in
for Lot B
the US such as New Mexico, South Dakota, Virginia,
In Lot C, two results are failing but high % compaction and Delaware use the following equation to determine
values for remaining three sublots eventually results in the pay factor (PF) based on PWL[6]:
a high PWL of about 75% (Fig. 12). PF = 55 + 0.5 × PWL
Most states reject the lot if the PWL is less than 60. In
that case the lot has to be removed and replaced.
Suitable pay factor table can be developed in India
based on experience gained on some pilot projects.
The following points need to be kept in view:
A small number of test results outside the specification
limits is a normal phenomenon and not necessarily
Fig. 12 Normal Distribution Curve for Percent Compaction detrimental to the pavement performance. There is high
for Lot C requirement to understand this for bringing a change in
Lot D and Lot E represent two lots that have low the current mindset.
standard deviation with all results in the range of Payment is based on PWL and should allow for both
92-94% (Fig. 13). PWL above 90% is achieved in both potential penalty and bonus.
cases. It is a general expectation that the construction Generally, 90% PWL allows 100% payment.
agencies will not go for over-compaction as it will
increase the cost of construction along with other PWL below 60% is generally not acceptable and
performance related issues of rutting and bleeding. requires rejection/replacement of the lot.
Many highway agencies in the US specify an upper Statistics based end-result specifications for QA have
limit of 97% compaction to avoid such a situation. been used by many Departments of Transportation

INDIAN HIGHWAYS│OCTOBER 2018 17


Technical Paper

(DOTs) in the US, including the state of Pennsylvania small number of test results outside the specification
[7]. Such specifications have significantly improved limits is normal and not necessarily detrimental to the
the quality of hot-mix asphalt produced [8]. It is high performance of the bituminous pavement. Pavements
time that such a system for QC/QA gets implemented with reasonable Percent Within Limits (PWL) lower
in India as well. than 100% should also be accepted.
Table 3 Example of Pay Adjustment Schedule Quality control is the responsibility of the construction
PWL (percent) Pay factor (percent)
contractor who should be required to submit a QC Plan
96-100 105
before executing the paving project. Quality assurance
90-95 PWL + 10
is the responsibility of the owner (such as NHAI, its
representative or a concessionaire) who should divide
60-89 0.5 PWL + 55
the paving project into lots and sublots; test sample from
Below 60 Reject
each sublot; and determine the Percent Within Limits
Based on experience in the US, about 5 to 10% asphalt (PWL) of each lot based on test values of at least 5
paving lots require some price adjustment. Pilot sublots and associated pay factors (price adjustments).
projects need to be considered in India to familiarize
both contractors and owners with the PWL approach A large volume of actual hot mix production test data
and assess the impact of pay factors without actually has been gathered and analyzed in many developed
imposing the price adjustments. countries such as US. Since hot mix plants are similar,
these values can be adopted in India as a starting point.
5.1 Resolution of Differences between Owner and Some QC/QA pilot projects should be undertaken
Contractor Test Results in India as soon as possible to familiarize both the
What if the contractor disputes the owner’s QA test contractors and owners with this concept and to assess
data? This can be resolved by retesting the retained the impact of PWL and pay factors.
sublot samples in presence of the contractor. Retest A computer software program based on Excel has been
does not always give the same test results as shown in developed at IIT Guwahati for this paper. It is very easy
Table 4. to use and can be accessed at the internet link provided
Table 4 Original and Retest Values of Bitumen Contents in the paper to calculate the mean, standard deviation,
and PWL, once the five sublot test results are entered
Test Bitumen contents in sublots
along with the minimum and maximum specified limits.
1 2 3 4 5
Original 6.0 5.6 6.4 5.8 6.1 7. REFERENCES
Retest 6.1 5.7 6.3 5.7 6.1 i. AASHTO. Implementation Manual for Quality Assurance,
1996.
Determine the mean and standard deviation of both lots
(original and retested) and conduct a paired t-test to ii. Indian Roads Congress. Specifications for Dense Graded
Bituminous Mixes. IRC:111-2009.
determine if the two sets of results came from the same
iii. Kandhal, P.S. and S.A. Cross. Effect of Aggregate Gradation
population or not. If yes, the original test results prevail
on Measured Asphalt Content. Transportation Research
and the contractor is charged the cost of retests. If no, Board, Transportation Research Record 1417, 1993.
the retest results prevail and are used for recomputing iv. Roberts, F.L., P.S. Kandhal, and E.R. Brown. Hot Mix Asphalt
the PWL and associated pay factor since testing was Materials, Mix Design and Construction. US Textbook.
done in contractor’s presence. It must be realized that NAPA Education Foundation, Maryland 1996.
decision cannot be made by considering means of v. Kandhal, P.S. Bituminous Road Construction in India.
original and retest values only. Textbook. Prentice Hall of India, New Delhi, July 2016.
vi. Akkinepally, R. and N. Attoh-Okine. Quality Control and
6. SUMMARY Quality Assurance of Hot Mix Asphalt Construction in
Implementation of quality control and quality assurance Delaware. Delaware Center for Transportation Report DCT
(QC/QA) is necessary to ensure consistent and quality 173, July 2006.
bituminous road construction in India. It should replace vii. Pennsylvania Department of Transportation. Specifications
for Highways, Publication 408, 1990.
the present system of generally reporting “passing” test
results only during construction, which is unacceptable viii. Kandhal, P.S., Cominsky, R.J., Maurer, D., and Motter, J.B.
Development and Implementation of Statistically-based End
and highly unfavorable for the long-term performance Result Specifications for Hot Mix Asphalt in Pennsylvania,
of a bituminous paving project. A change in the current Transportation Research Board, Transportation Research
mindset of highway engineers is required to realize that Record1389, 1993.

18 INDIAN HIGHWAYS│OCTOBER 2018

You might also like