Ω Planning Procedure
Reorder Target
Fixed Lot Safety Period Target Stock
Planning Lot-Sizing Method Point Days Of
Size Qty Stock Type Supply Quantity
1) (Driver - Sales order, i.e. Planning and procurement run when you book your sales order)
Demand Drive
Planning Ö - Ö - - -
Fixed Lot Size
- - - - - -
Lot for Lot
- - Ö Ö - -
Periodic lot-size
- - - - Ö -
Target Days Of
Supply
- - Ö - - Ö
Target stock level
2) (Driver - Reorder Point, i.e. MRP will be running based on your reorder quantity mentioned in the ma
Consumption
Based Planning Ö Ö - - - -
Fixed Lot Size
- Ö - - - -
Lot for Lot
- If you have selected demand-driven planning as your planning procedure, all planning
proposals are created by date and quantity for each requirement.
With the periodic lot-sizing method, a planning proposal is created for all requirements
within a fixed period. You use periodic lots to reduce the number of orders and ordering
Weeks, Month costs
With this method, the planning proposal quantity is high enough to cover all demand
within a number of days after the due date of the planning proposal (that is, within the
target days of supply)
Days You use target days of supply to reduce the number of orders and the cost per order.
Target Stock Level’ is useful if you have limited warehouse capacity. If demand-driven
planning has been selected as your planning procedure, planning proposals are created
when the projected stock falls below zero, or if a safety stock is maintained, when the
projected stock falls below the safety stock.
Quantity Data
ur reorder quantity mentioned in the material master)
If consumption-based planning has been selected as your planning procedure, planning
proposals are created if the available stock is below a threshold value such as a reorder
Quantity Data point or safety stock.
If you have selected consumption-based planning as your planning procedure, planning
proposals are created if the available stock falls below a threshold value such as a reorder
Quantity Data point.
Target Stock Level’ is useful if you have limited warehouse capacity. If consumption-based
Quantity Data planning has been selected as your planning procedure, planning proposals are created if
the available stock is below a threshold value such as reorder point or safety stock
Fixed Lot SiSafety stock Stock Purchase Proposal
BOM Explod
Production Proposal is created subject availabilty of stock