Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

PROPOSED DRUG ABUSE TREATMENT

AND REHABILITATION CENTER


Brgy. Osorio, Trece Martires, Cavite

08/11/2019
FLOOR AREA: 90.00
MALE DATRC- B13: DORM MANAGER BILL OF QUANTITY (BOQ) COST PER SM 46,069.83

Division Description Unit Quantity Unit Cost Total Amount Remarks

2 SITE DEVELOPMENT 708,469.14


(Manner of Installation/ Execution shall be compliant with the standard methodology and acceptable norms and shall follow the Architect/ Engineer's further instruction)
2.01 Site Preparations
2.01.01 Clearing and Grubbing sq.m. 90.00 31.75 2,857.50
2.01.02 Demolition Works lot 1.00 491.89 491.89 Provisional Amount
2.01.03 Disposal of Debris from demolition cu.m. 0.77 2,523.11 1,954.49 Provisional Amount
2.01.04 Dayworks lot 1.00 7,791.12 7,791.12 Provisional Amount
Subtotal for 2.01 - Site Preparations 13,095.00
2.02 Earthworks
2.02.01 Structural Excavation for Building Foundations cu.m. 257.93 762.00 196,538.85
2.02.02 Hauling and Disposal of excavated unsuitable material cu.m. 51.59 1,270.00 65,512.95
2.02.03 Backfilling and Compaction cu.m. 206.34 1,270.00 262,051.80
2.02.04 Disposal of Water (Dewatering) lot 1.00 1,229.73 1,229.73 Provisional Amount
2.02.05 Trimming Works sq.m. 214.51 635.00 136,213.85
2.02.06 Soil Poisoning sq.m. 224.75 127.00 28,543.25 Provisional Amount
2.02.07 Gravel Bedding (100mm thk.) cu.m. 2.08 2,540.00 5,283.71
Subtotal for 2.02 - Earthworks 695,374.14
3 CONCRETE WORKS 259,602.02
(Supply and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions. Manner of
Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project requirements

3.01A Reinforcing Steel Bars; Grade 60


3.01.01 Foundations kgs 45.52 77.47 3,526.19
3.01.02 Columns kgs 417.30 77.47 32,328.55
3.01.03 Concrete Walls kgs 77.47 -
3.01.04 Beams and Girders kgs 359.35 77.47 27,839.00
3.01B Reinforcing Steel Bars; Grade 40
3.01.05 Suspended Slabs; Slabs on-grade kgs 285.07 75.97 21,656.85
3.01.06 Stairs kgs 75.97 -
3.01.07 Sewage and Sump pits kgs
Subtotal for CONCRETE WORKS- 85,350.58
3.02 Formworks; including shoring and bracing work
3.02.01 Foundations sq.m. 1.60 2,778.15 4,445.04
3.02.02 Columns sq.m. 8.88 2,778.15 24,669.97
3.02.03 Concrete Walls sq.m. 2,778.15 -
3.02.04 Beams and Girders sq.m. 16.74 2,778.15 46,506.23
3.02.05 Suspended Slabs; Slabs on-grade sq.m. - 2,778.15 -
3.02.06 Stairs sq.m. - 2,778.15 -
3.02.07 Sewage and Sump pits sq.m.
Subtotal for 3.02- Formworks; including shoring and 75,621.24
3.03 Cast-in-place
bracing work Concrete
3.03.01 Foundations cu.m. 1.28 6,854.95 8,774.34
3.03.02 Columns cu.m. 2.37 6,854.95 16,232.52
3.03.03 Concrete Walls cu.m. 6,854.95 -
3.03.04 Beams and Girders cu.m. 2.60 6,854.95 17,850.29
3.03.05 Suspended Slabs; Slabs on-grade cu.m. 7.69 6,854.95 52,700.86
3.03.06 Stairs cu.m. 6,854.95 -
3.03.07 Sewage and Sump pits cu.m.
Subtotal for 3.03- Cast-in-place Concrete 95,558.00
3.04 Concrete Accessories
3.04.01 Waterstops l.m. 0.39 1,090.50 422.37 Provisional Quantity
3.04.02 Contraction Joints l.m. 1.94 652.40 1,263.43 Provisional Quantity
3.04.03 Expansion Joints l.m. 1.94 652.40 1,263.43 Provisional Quantity
3.04.04 Block-outs sets 0.39 317.50 122.97 Provisional Quantity
Subtotal for 3.04- Concrete Accessories 3,072.20
4 MASONRY 179,235.10

Block Masonry (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
4.01
Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project requirements

4.01.01 CHB Laying 150mm sq.m. 56.75 1,079.50 61,261.63


4.01.02 CHB Laying 100mm sq.m. 29.77 889.00 26,465.53
Subtotal for 4.01- Block Masonry (Supply and installation
87,727.16
of contracted scope with fittings and hardware to
Division Description Unit Quantity Unit Cost Total Amount Remarks

Plastering (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
4.02
Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project requirements
4.02.01 Exterior Plastering sq.m. 56.75 571.50 32,432.63
4.02.02 Interior plastering sq.m. 116.29 508.00 59,075.32
Subtotal for 4.02.01- Exterior Plastering 91,507.95
Roof Deck Topping (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per Architect/ Engineer's specification, approval and
4.03
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project requirements
50mm Concrete Topping on roofdecks;
4.03.01 sq.m. - 342.75 -
Verify specifications
Subtotal for 4.03- Roof Deck Topping (Supply and
-
installation of contracted scope with fittings and
5 METALS 260,887.21
Structural Metal Framing (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's
5.01 specification, approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance
with the project requirements
5.01.01 Structural Steel Framing Beams and Columns including Base kgs - 104.08 -
Plates, Anchor Bolts and nuts, washers and other accessories to
complete the system
5.01.02 Roof Framing; Rafters, Trusses, Purlins, including base plates, sq.m. 2,506.60 104.08
anchor bolts and nuts, washers and other accessories to
complete the system 260,887.21
Metal Fabrications (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
5.02 approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project
requirements
5.02.01 Stair Railings l.m. - 4,737.47 -
5.02.02 Stair metal nosing l.m. - 1,016.00 -
Subtotal for 5- METALS 260,887.21
6 CARPENTRY/CASEWORK 23,285.85
Casework (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per Architect/ Engineer's specification, approval and
6.01 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
Male MaleDorm Manager; Pantry, CAB-B1 with CAB-B3A set(s) 1.00 23,285.85 23,285.85
Subtotal for 6.01- Casework 23,285.85
7 THERMAL AND MOISTURE PROTECTION 187,559.08
Damp Proofing and Water Proofing (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
7.01 approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project
requirements
7.01.01 Polyethelene sheet, 6mil damp proofing for footings and slabs sq.m. 72.00 63.50 4,572.00
on ground
7.01.02 WP-1: Solvent free Liquid-applied elastomeric waterproofing sq.m.
membran
7.01.03 WP-2: 2 component cementitious waterproofing system sq.m. - 1,905.00 -
7.01.04 WP-3: Potable Water Grade 2 component epoxy coating sq.m.
7.01.05 WP-4: Xypex Crystalline Waterproofing sq.m.
Hot-applied Membrane Water Proofing for roof decks,
7.01.06 sq.m.
verify specifications
Subtotal for 7.01- Damp Proofing and Water Proofing
4,572.00
(Supply and installation of contracted scope with fittings
7.02
Thermal Protection (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project requirements

7.02.01 Rigid Thermal Insulation for Roof Decks sq.m. - 952.50 -


7.02.02 Roof Thermal Insulation, verify specifications sq.m. 250.30 184.15 46,093.23
Subtotal for 7.02- Thermal Protection (Supply and
46,093.23
installation of contracted scope with fittings and
7.03 Roof Covering (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
7.03.01 Preformed Pre-painted G.I. "Banawe" Type Roof, ga. 24, l.m. 100.57 1,361.21 136,893.85
including Bended Accessories, Metal Gutters 0.6mm thk and
consumables
7.03.02 Reinforced Concrete Gutter l.m. - 1,905.00 -
7.03.03 Laminated Glass Skylight, verify specs sq.m. - 1,769.57 -
Subtotal for 7.03- Roof Covering (Supply and installation
136,893.85
of the system with fittings and hardware to complete. All
8 OPENINGS 346,612.19
8.01 Doors (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions. Manner of
Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as "approved
equivalent" in case the specified are not locally available)
8.01.01 Framed Hollow Core Flush Wood Door Type A
8.01.01.01 set(s) 1.00 14,081.82 14,081.82
Framed Hollow Core Flush Wood Door Type A; with Vision Panel
Type VP-1; Door Action Type Swing; 800Wx2400H; HPL Door Face
Finish; Jamb Type J-1; Hinge Type H-1 (4pcs); Lockset Type L-2
(1pc); Door Stop Type S-3(1pc); Door Silencer (M-2)
Division Description Unit Quantity Unit Cost Total Amount Remarks

8.01.02 Solid Core Flush Wood Door Type B


8.01.02.01 Solid Core Flush Wood Door Type B; Single Leaf; With Louver; set(s) 1.00 16,716.70 16,716.70
Swing Type; 800Wx2400H; HPL Door Face Finish; Jamb Type J-1;
Hinge Type H-1 (4pcs); Lockset Type L-8 (1pc); Threshold Type T-
1; Door Silencer (M-1)
8.01.02.02 Solid Core Flush Wood Door Type B; Single Leaf; Vision Panel VP- set(s) 1.00 16,716.70 16,716.70
1; Swing Type; 800Wx2400H; HPL Door Face Finish; Jamb Type J-
1; Hinge Type H-1 (4pcs); Lockset Type L-2 (1pc); Door Stop Type
S-3 (1pc) Door Silencer (M-1)
8.01.03 Aluminum Framed Glass Door Type K
8.01.03.01 Aluminum Framed Glass Door Type K; Single Leaf; Double Action; set(s) 1.00 33,567.13 33,567.13
900Wx2400H; Jamb Type J-8; Hinge Type H-6 (2pcs); Lockset
Type L-19 (2pcs); Door Pull Type P-1 (4pcs); Threshold Type T-4;
Weather Strip (M-4)
8.01.04 Frameless Glass Door Type N
Frameless Glass Door Type N; Single Leaf; Door Action Type set(s) 1.00 11,678.44 11,678.44
Swing; 900Wx2400H; Jamb Type J-11; Hinge Type H-5 (1pc);
Lockset Type L-19 (1pc); Door Pull Type P-1 (2pcs)
Subtotal for 8.01- Doors 92,760.80
8.02 Windows (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per Architect/ Engineer's specification, approval and instructions. Manner of
Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as "approved
equivalent" in case the specified are not locally available)
8.02.01 Aluminum Framed Awning Window
8.02.01.01 6mm thk Tempered Glass on Powder Coated Aluminum Frames; set(s) 1.00 4,545.55 4,545.55
650Hx900W
8.02.02 Aluminum Framed Fixed Window and Operable Awning
Window
8.02.02.01 6mm thk Tempered Glass on Powder-coated Aluminum Frames set(s) 5.00 43,357.54 216,787.69
with Insect Screen; 1550Hx3600W
8.02.02.02 6mm thk Tempered Glass on Powder-coated Aluminum Frames set(s) 3.00 10,839.38 32,518.15
with Insect Screen; 1550Hx900W
Subtotal for 8.02- Windows 253,851.39
9 FINISHES 305,118.68
Partitions (Supply and installation of the system, complete as per the Architect/ Engineer's specification, approval and instructions. Material Sample/s have to be provided when deem necessary
9.01
and or to acquire approval as "approved equivalent" in case the specified are not locally available)
9.01.01 P-8 96mm th Drywall System sq.m. - 1,390.24 -
Subtotal for 9.01- Partitions -
Floor Finishes(Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
9.02 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
9.02.01 F1 300 mm x 300 mm x 3 mm THK sq.m. 671.24 -
9.02.02 F3 2 mm THK Sheet Vinyl: Regular, Anti-Bacterial sq.m. 1,558.75 -
9.02.03 F6 600 mm x 600 mm Homogenous Matte Floor Tiles sq.m. 64.29 1,409.91 90,642.57
9.02.04 F7 600 mm x 600 mm Homogenous Non Skid Floor Tiles sq.m. 1,414.71 -
9.02.05 F8 300 mm x 300 mm Homogenous Non Skid Floor Tiles sq.m. 2.13 1,310.80 2,794.91
9.02.06 F9 300 mm x 600 mm Homogenous Non Skid Stair Thread Tiles sq.m. 1,274.34 -
9.02.07 F10 Polyurethane-Based Epoxy sq.m. 1,112.61 -
9.02.08 F11 Exterior Paver Tiles sq.m.
Subtotal for 9.02- Floor Finishes 93,437.48
Wall Finishes (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
9.03 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
9.03.01 W1 Textured Elastomeric Exterior Wall Coating System sq.m. 878.38 -
9.03.02 W2 Semi- Gloss Acrylic Latex Paint Finish sq.m. 141.25 527.03 74,442.57
9.03.03 W3 Anti-Bacterial Paint Semi-Gloss Finish sq.m. 658.78 -
9.03.04 W5 300 mm x 300 mm ceramic polished tiles sq.m. 15.00 1,172.87 17,593.01
9.03.05 W6 600 mm x 600 mm Homogenous Polished Tiles sq.m. 1,414.71 -
9.03.06 W7 Stone Veneer Cladding sq.m. - Included in Division 10
Subtotal for 9.03- Wall Finishes 92,035.57
Baseboards(Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions. Manner
9.04 of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as "approved
equivalent" in case the specified are not locally available)
9.04.01 B1 10 mm High Baseboard Tile l.m. - 127.00 -
9.04.02 B2 10 mm High Splayed Baseboard Tile l.m. 635.00 -
9.04.03 B3 10 mm High PVC Baseboard Tile l.m. 54.81 190.50 10,441.31
9.04.04 B4 10 mm High Cover Sheet Vinyl with Capping Seal l.m. 222.25 -
9.04.05 B5 10 mm High Epoxy Painted Baseboard l.m. 317.50 -
Subtotal for 9.04- Baseboards 10,441.31
Division Description Unit Quantity Unit Cost Total Amount Remarks

Ceiling Finishes (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
9.05 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
9.05.01 C1 600 mm x 600 mm Tegular Bevealed Acoustic Tiles sq.m. 47.97 882.10 42,311.11
9.05.02 C2 12 mm THK Boral Echostop sq.m. 942.63 -
9.05.03 C3 12 mm THK Moisture resistant, Flat Latex Paint Finish sq.m. 27.13 993.86 26,959.02
9.05.04 C4 12 mm THK Moisture resistant, Flat Anti Bacterial Paint Finish sq.m. 1,005.76 -
9.05.05 C6 200 mm Wide Powder Coated Wood sq.m. 48.38 825.50 39,934.20
9.05.06 C7 Exposed Underside of Slab/Beam sq.m. 317.50 -
9.05.07 C8 Exposed Underside of Roof sq.m. 317.50 -
9.05.08 C11 uPVC Wood Grain Ceiling Panels sq.m. 536.58 -
9.05.09 C12 6 mm THK Frosted Acrylic Sheet sq.m. 9,525.00 -
9.05.10 C13 600 x 600 mm Aluminum Powder Coated Ceiling sq.m. 1,764.20 -
Subtotal for 9.05- Ceiling Finishes 109,204.32
10 SPECIALTIES -
10.01 Façade Architectural Louvres and Slats (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to
acquire approval as "approved equivalent" in case the specified are not locally available)
10.01.01 50mmx100mmx1.5mm thk Primed and Painted Tubular Steel lm - 651.48 -
Horizontal Grilles @ 150mm O.C on 50 mm x 100mm Vertical
Steel Frame
Subtotal for 10.01- Façade Architectural Louvres and Slats -
Special Wall Finishes (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
10.02 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
10.02.01 W7 Stone Veneer Cladding sq.m. - 2,000.18 -
Subtotal for 10.02- Special Wall Finishes -
11 MECHANICAL WORKS 906,893.97
11.01 Mechanical Ventilation and Air-Conditioning System (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's
specification, approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem
necessary and or to acquire approval as "approved equivalent" in case the specified are not locally available)
11.01.01 Ductworks
11.01.01.01 GI Rectangular Ducts 1400X800 l.m. 7,423.55 -
11.01.01.02 GI Rectangular Ducts 890X450 l.m. 6,091.65 -
11.01.01.03 GI Rectangular Ducts 450x250 l.m. 3,413.24 -
11.01.01.04 GI Rectangular Ducts 400x200 l.m. 3,117.51 -
11.01.01.05 GI Rectangular Ducts 350x150 l.m. 2,840.50 -
11.01.01.06 GI Rectangular Ducts 300x200 2,542.50 -
11.01.01.07 GI Rectangular Ducts 250x200 l.m. 1,817.52 -
11.01.01.08 GI Rectangular Ducts 200x200 l.m. 1,601.88 -
11.01.01.09 GI Rectangular Ducts 200x150 l.m. 1,460.89 -
11.01.01.10 GI Rectangular Ducts 150x150 l.m. 10.00 1,319.90 13,199.00
11.01.01.11 GI Rectangular Ducts 100x100 l.m. 10.00 1,159.74 11,597.40
11.01.01.12 Ductworks ancillaries including flexible connections, hangers, l.s 1.00 22,179.89 22,179.89
supports and flanges as required.
11.01.01.13 Vent Caps pc(s) 3,044.50 -
11.01.01.14 Ref Net pc(s) 2,500.00 -
11.01.01.15 Supply and fix equipment ancillaries Ventilation fans; including l.s 1.00 155,259.80 155,259.80
all necessary accessories, controls, cables/wirings, conduits and
connections; complete as in the equipment schedule and as
prescribed
11.01.02 Fans and Blowers
11.01.02.01 Ceiling Casette
11.01.02.01.01 1 Phase, 400 V, 60 Hz, 130 LPS set(s) 13,596.00 -
11.01.02.01.02 1 Phase, 230 V, 60 Hz, 95 LPS set(s) 10,782.55 -
11.01.02.01.03 1 Phase, 230 V, 60 Hz, 85 LPS set(s) 10,782.55 -
11.01.02.01.04 1 Phase, 230 V, 60 Hz, 65 LPS set(s) 1.00 10,782.55 10,782.55
11.01.02.01.05 1 Phase, 230 V, 60 Hz, 25LPS set(s) 2.00 10,782.55 21,565.10
11.01.02.03 IN LINE CENTRIFUGAL FAN
11.01.02.03.01 1 Phase, 230 V, 60 Hz, 2000 LPS set(s) - 34,627.50 -
11.01.02.03.02 1 Phase, 230 V, 60 Hz, 150 LPS set(s) 28,537.20 -
11.01.02.03.03 1 Phase, 230 V, 60 Hz, 100 LPS set(s) 28,537.20 -
11.01.02.04 OSCILLATING AND CEILING FANS
11.01.02.04.01 1 Phase, 230 V, 60 Hz, 2,650 LPS set(s) 13,145.87 -
11.01.02.04.02 1 Phase, 230 V, 60 Hz, 1,433 LPS set(s) 13,145.87 -
11.01.02.05 PROPELLER TYPE
11.01.02.05.01 1 Phase, 230 V, 60 Hz, 1878 LPS set(s) 4,280.00 -
11.01.02.06 Range Hood
11.01.02.06.01 Wall Mounted, Ducted Exhaust; 1 Phase, 230 V, 60 Hz, 216 LPS set(s) 32,100.00 -
Division Description Unit Quantity Unit Cost Total Amount Remarks

11.01.02.07 WALL MOUNTED


11.01.02.07.01 1 Phase, 230 V, 60 Hz, 191 LPS set(s) 5,350.00 -
11.01.02.07.02 1 Phase, 230 V, 60 Hz, 152 LPS set(s) 5,350.00 -
11.01.02.07.03 1 Phase, 230 V, 60 Hz, 105 LPS set(s) 5,350.00 -
11.01.02.07.04 1 Phase, 230 V, 60 Hz,97 LPS set(s) 1.00 4,280.00 4,280.00
11.01.02.07.05 1 Phase, 230 V, 60 Hz, 63 LPS set(s) 1.00 4,280.00 4,280.00
11.01.03 Air Conditioning Units
11.01.03.01 Split Type A/C: Fan Coil Units
11.01.03.01.01 5 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 125,300.10 -
11.01.03.01.02 4 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 115,475.79 -
11.01.03.01.03 3 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 107,358.72 -
11.01.03.01.04 2.0 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 1.00 83,874.00 83,874.00
11.01.03.01.05 1.0 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 1.00 29,712.00 29,712.00
11.01.03.01.06 2.5 HP Floor Standing, 230V/1P, 60 Hz set(s) 1.00 115,717.80 115,717.80
11.01.03.01.07 1.5 HP Wall Mounted, 230V/1P, 60 Hz set(s) 47,328.00 -
11.01.03.01.07 1 HP Wall Mounted, 230V/1P, 60 Hz set(s) 41,937.00 -
11.01.03.04 OTHERS
11.01.03.04.01 Refrigerant Pipes, insulation including hangers & supports, l.m. 15.00 782.46 11,736.90
consumables & other accessories to complete the system
11.01.03.04.02 Testing and Commissioning lot 1.00 71,044.60 71,044.60
Subtotal for 11.01 Mechanical Ventilation and Air Conditioning System 555,229.04
11.02 Fire Protection Works (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
11.02.03 Valves,fittings, sprinklers, FHC and accessories
11.02.03.01 FE.36-10 LBS Portable Fire Extinguisher pcs 3,000.00 -
11.02.03.02 CO2 -10 LBS Portable Fire Extinguisher pcs 3,000.00 -
11.02.03.03 50 LBS CO2 Wheeled Type Portable Fire Extinguisher 2.00 20,000.00 40,000.00
11.02.03.04 Fire hose Cabinet pcs 1.00 26,000.00 26,000.00
11.02.03.35 Brackets and hangers lot 0.00 264,550.00 -
Subtotal for 11.02- Fire Protection Works 66,000.00
11.03 Plumbing and Sanitary Works (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
11.03.01 Plumbing Fixtures
11.03.01.01 Water Closets set(s) 2.00 10,500.00 21,000.00
11.03.01.02 Urinals; Wall hung set(s) 6,500.00 -
11.03.01.03 Lavatories; Wall Hung, Elliptical set(s) 2.00 7,000.00 14,000.00
11.03.01.04 Lavatories; Wall Hung, Square set(s) 2.00 5,000.00 10,000.00
11.03.01.05 Flush Valves; for Water Closets, Manual set(s) 2.00 8,395.00 16,790.00
11.03.01.06 Flush Valves; for Urinals, Manual set(s) 7,360.00 -
11.03.01.07 Faucets/(Mixer); for lavatories set(s) 5.00 3,000.00 15,000.00
11.03.01.08 Showers set(s) 2,500.00 -
11.03.01.09 Floor Drains set(s) 1.00 500.00 500.00
11.03.02 Toilet, Shower, Janitor Closet Accessories
11.03.02.01 Paper Holders set(s) 2.00 900.00 1,800.00
11.03.02.02 Soap Holders set(s) 2.00 800.00 1,600.00
11.03.02.03 Soap Dispenser set(s) 2.00 4,550.00 9,100.00
11.03.02.04 Paper Towel Dispenser set(s) 2.00 4,000.00 8,000.00
11.03.02.05 Towel Bar set(s) 2.00 4,000.00 8,000.00
11.03.02.06 Grab Bar; for PWD set(s) 2.00 4,500.00 9,000.00
11.03.02.07 Robe Hook; double; S/S set(s) 2.00 1,100.00 2,200.00
11.03.02.08 Hand Dryer set(s) 1.00 6,500.00 6,500.00
11.03.02.09 Facial Mirrors set(s) 2.00 2,000.00 4,000.00
11.03.02.10 Mop Strip set(s) 2.00 1,500.00 3,000.00
11.03.03 Hot Water Line; including pipes, fittings and other accessories
necessary to complete the system
11.03.03.01 25mmØ" PPR pipe Length 1,880.50 -
11.03.03.02 20mmØ" PPR pipe Length 490.00 -
11.03.03.03 15mmØ" PPR pipe Length 298.00 -
11.03.04 Cold Water Line; including pipes, fittings and other accessories
necessary to complete the system
11.03.04.01 65mmØ" PPR pipe Length 3,838.50 -
11.03.04.02 60mmØ" PPR pipe Length 3,166.33 -
11.03.04.03 50mmØ" PPR pipe Length 5.00 2,665.50 13,327.50
11.03.04.04 40mmØ" PPR pipe Length 3.00 1,880.50 5,641.50
11.03.04.05 32mmØ" PPR pipe Length 1,992.00 -
11.03.04.06 25mmØ" PPR pipe Length 761.00 -
11.03.04.07 20mmØ" PPR pipe Length 490.00 -
11.03.04.08 15mmØ" PPR pipe Length 298.00 -
Division Description Unit Quantity Unit Cost Total Amount Remarks

11.03.05 Storm DrainageSystem; including pipes, fittings and other


accessories necessary to complete the system
11.03.05.01 300mmØ" PVC pipe Length
11.03.05.02 250mmØ" PVC pipe Length 3,785.47 -
11.03.05.03 200mmØ" PVC pipe Length 2,222.00 -
11.03.05.04 150mmØ" PVC pipe Length 1,466.67 -
11.03.05.05 100mmØ" PVC pipe Length 12.00 733.33 8,799.96
11.03.05.06 75mmØ" PVC pipe Length 8.00 550.00 4,400.00
11.03.05.07 Area Drain and Catch Basins set(s) 8.00 14,188.57 113,508.56
11.03.06 Sanitary Line System, Soil/Waste Pipes including fittings
and accessories necessary to complete the system
11.03.06.01 150mmØ" PVC pipe Length 1,466.67 -
11.03.06.02 100mmØ" PVC pipe Length 6.00 733.33 4,399.98
11.03.06.03 75mmØ" PVC pipe Length 550.00 -
11.03.06.04 50mmØ" PVC pipe Length 333.67 -
11.03.07 Sanitary Line System, Vent Pipes including fittings and
accessories necessary to complete the system
11.03.07.01 150mmØ" PVC pipe Length 1,466.67 -
11.03.07.02 100mmØ" PVC pipe Length 733.33 -
11.03.07.03 75mmØ"PVC pipe Length 550.00 -
11.03.07.04 50mmØ" PVC pipe Length 14.00 333.67 4,671.38
11.03.08Others
11.03.08.01 Testing and Commissioning lot 1.00 426.05 426.05
Subtotal for 11.03- Plumbing and Sanitary Works 285,664.93
Conveyances (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
11.04 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
10.04.01 Passenger Elevators unit(s) - 6,000,000.00 -
Subtotal for 11.04- Conveyances -
12 ELECTRICAL WORKS, AUXILIARIES AND ELECTRONICS 859,940.23
Electrical Works (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
12.01 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
12.01.01 Lighting Fixtures
12.01.01.01 Pin Light sets 3.00 1,165.00 3,495.00
12.01.01.02 Pin Light with battery packed sets 2,500.00 -
12.01.01.03 Down Light sets 10.00 1,570.00 15,700.00
12.01.01.04 Direct Light sets 2.00 1,200.00 2,400.00
12.01.01.05 Direct Light with battery packed sets 3,250.00 -
12.01.01.06 Square Light sets 11.00 1,785.00 19,635.00
12.01.01.07 Square Light with battery packed sets 3.00 4,000.00 12,000.00
12.01.01.08 Troffer Light 300X300 sets 2,285.00 -
12.01.01.09 Troffer Light 300X300 with battery packed sets 5,000.00 -
12.01.01.10 Fluorescent Lamp sets 1,250.00 -
12.01.01.11 T5 STRIP LIGHT sets 2,420.00 -
12.01.01.12 Wall mounted Lamp sets 1,785.00 -
12.01.01.12 Exit Sign with direction sets 1.00 3,855.00 3,855.00
12.01.01.13 Emergency light sets 2,500.00 -
Subtotal for 12.01.01- Lighting Fixtures 57,085.00
12.01.02 Wiring Devices
12.01.02.01 One gang switch pcs 5.00 175.00 875.00
12.01.02.02 Two gang switch pcs 1.00 269.00 269.00
12.01.02.03 Three gang switch pcs 364.00 -
12.01.02.04 Duplex convenience outlet pcs 12.00 466.00 5,592.00
12.01.02.05 Duplex convenience outlet (GFCI) pcs 1.00 500.00 500.00
12.01.02.06 Simplex convenience outlet pcs 341.00 -
12.01.02.07 Special Outlet (EF) pcs 2.00 500.00 1,000.00
12.01.02.08 Special Outlet (REF) pcs 1.00 500.00 500.00
12.01.02.09 Special Outlet (HD) pcs 1.00 4,220.00 4,220.00
12.01.02.10 ECB, NEMA 3R, 20AT, 1P assy 600.00 -
12.01.02.11 ECB, NEMA 3R, 30AT, 1P assy 700.00 -
Subtotal for 12.01.02- Wiring Devices 12,956.00
12.01.03 Boxes, Pullboxes, Wire Gutter, and other related
accessories
12.01.03.01 Junction Box pcs 30.00 32.00 960.00
12.01.03.02 Utility box pcs 23.00 30.00 690.00
12.01.03.03 IMC Coupling 15mm pcs 66.00 42.00 2,772.00
12.01.03.04 Locknut and Bushing 15mm pcs
12.01.03.05 Pullbox with cover pcs 3.00 500.00 1,500.00
12.01.03.06 Wire gutter assy 7,400.00 -
12.01.03.07 Hangers and Support lot 1,815.00 -
Division Description Unit Quantity Unit Cost Total Amount Remarks

Subtotal for 12.01.03- Boxes, Pullboxes, Wire Gutter, and other related accessories 5,922.00
12.01.04 Conduits -
12.01.04.01 IMC 15mm dia. pcs 66.00 223.00 14,718.00
Subtotal for 12.01.04- Conduits 14,718.00
12.01.05 Wires and Cables -
12.01.05.01 THWN 3.5 sq.mm m 750.00 24.00 18,000.00
Subtotal for 12.01.05- Wires and Cables 18,000.00
12.01.06 Power Systems and Panel Boards
included in the main BOQ
Subtotal for 12.01.06- Power Systems and Panel Boards
-
TOTAL FOR 12.01 - ELECTRICAL WORKS 108,681.00
Auxiliaries and Electronics(Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
12.02 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
12.02.01 Fire Detection and Alarm System
12.02.01.01 Addressable Smoke Detector Units 15.00 2,500.00 37,500.00
12.02.01.02 Addressable Smoke Detector w/ Base Sounder Units 2,500.00 -
12.02.01.03 Adressable Heat Detector Units 2,500.00 -
12.02.01.04 Addressable Output Module Units 2,500.00 -
12.02.01.05 Addressable Input Module Units 1.00 2,500.00 2,500.00
12.02.01.06 Addressable Manual Pull Station Units 1.00 2,500.00 2,500.00
12.02.01.07 Fire Alarm Speaker w/ Strobe Light Units 1.00 2,500.00 2,500.00
12.02.01.08 UPS-Uniteruptable Power Supply Units 15,000.00 -
12.02.01.09 GAP- Graphical Annunciator Panel Units 5,000.00 -
12.02.01.10 Firemen Telephone Jack Units 2,500.00 -
12.02.01.11 MFACP-Main Fire Alarm Control Panel Units 500,000.00 -
12.02.01.12 SFACP- Seondary Fire Alarm Control Panel Units 426,836.00 -
12.02.01.13 Evacuation Panel Units 1.00 5,000.00 5,000.00
12.02.01.14 Pull Box 25mm x 250mm x150mm Pcs 1.00 200.00 200.00
12.02.01.15 IMC Conduit 25mm Pcs 13.00 402.00 5,226.00
12.02.01.16 IMC Coupling 25mm Pcs 13.00 46.00 598.00
12.02.01.17 Junction Box Pcs 18.00 45.00 810.00
12.02.01.18 Square Box Pcs 15.00 85.00 1,275.00
12.02.01.19 Utility box Pcs 2.00 35.00 70.00
12.02.01.20 Locknut and Bushing 25mm Pcs 88.00 20.00 1,760.00
12.02.01.21 Flexible Metalic Conduit Pcs 15.00 85.00 1,275.00
12.02.01.22 FMC Connector Pcs 30.00 20.00 600.00
12.02.01.23 Hanger and Support mtrs 1.00 50.00 50.00
12.02.01.24 Roogh -In Consumables pcs 1.00 50.00 50.00
12.02.01.25 #16 Twisted Pair Wire mtrs 1,857.37 31.00 57,578.60
12.02.01.26 Cabling Consumables Units 3.00 80.00 240.00
Subtotal for 12.02.01- Fire Detection and Alarm System 119,732.60
12.02.02 IP Based Public Address
12.02.02.01 Network Switch ( Inside IDF) Pcs 1.00 38,967.00 38,967.00
12.02.02.02 Network Manager ( Inside IDF) mtrs 1.00 12,679.00 12,679.00
12.02.02.03 Power Amplifier ( Inside IDF) pcs 1.00 120,000.00 120,000.00
12.02.02.04 UPS Units 1.00 5,000.00 5,000.00
12.02.02.05 6w Ceiling Mounted Speaker set(s) 5.00 1,800.00 9,000.00
12.02.02.06 10w Wall Miunted Speaker set(s) - 2,800.00 -
12.02.02.07 Pull Box 25mm x 250mm x150mm set(s) 1.00 200.00 200.00
12.02.02.08 IMC Conduit 25mm l.m. 21.00 577.00 12,117.00
12.02.02.09 IMC Coupling 25mm Pcs 21.00 46.00 966.00
12.02.02.10 Junction Box Unit 5.00 45.00 225.00
12.02.02.11 Square Box Units 1.00 85.00 85.00
12.02.02.12 Utility box Units 2.00 35.00 70.00
12.02.02.13 Locknut and Bushing 25mm Units 145.00 20.00 2,900.00
12.02.02.14 Flexible Metalic Conduit Units 18.00 85.00 1,530.00
12.02.02.15 FMC Connector Units 36.00 20.00 720.00
12.02.02.16 Hanger and Support Units 61.00 50.00 3,050.00
12.02.02.17 Roogh -In Consumables Units 8.00 50.00 400.00
12.02.02.18 #16 Shielded Twisted Pair Wire pcs 55.30 31.00 1,714.32
12.02.02.19 Cabling Consumables pcs 20.00 80.00 1,600.00
Subtotal for 12.02.02- IP Based Public Address 211,223.32
12.02.03 IP Based CCTV Surveillance System
12.02.03.01 Network Video Recorder units - 15,000.00 -
12.02.03.02 Patch Panel units 1.00 31,784.00 31,784.00
12.02.03.03 POE Switch units 1.00 45,738.00 45,738.00
12.02.03.04 Server units - 65,000.00 -
12.02.03.05 32" LED Spot Monitor units - 18,000.00 -
12.02.03.06 42" LED Spot Monitor units - 25,000.00 -
Division Description Unit Quantity Unit Cost Total Amount Remarks

12.02.03.07 Fixed Colored IP CCTV Camera (Dome Type) units 1.00 15,000.00 15,000.00
12.02.03.08 Fixed Colored IP CCTV Camera (Dome Type) WP units - 15,000.00 -
12.02.03.09 UPS units 1.00 10,000.00 10,000.00
12.02.03.10 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.02.03.11 IMC Conduit 15mm units 4.00 223.00 892.00
12.02.03.12 IMC Coupling 15mm pcs 4.00 23.00 92.00
12.02.03.13 Junction Box pcs 1.00 45.00 45.00
12.02.03.14 Square Box pcs 1.00 85.00 85.00
12.02.03.15 Utility box pcs 1.00 35.00 35.00
12.02.03.16 Locknut and Bushing 25mm pcs 5.00 20.00 100.00
12.02.03.17 Flexible Metalic Conduit pcs 1.00 85.00 85.00
12.02.03.18 FMC Connector pcs 2.00 20.00 40.00
12.02.03.19 Cable Tray 150mm x 150mm mtrs - 5,000.00 -
12.02.03.20 Hanger and Support pcs 11.00 50.00 550.00
12.02.03.21 Roogh -In Consumables Units 3.00 50.00 150.00
12.02.03.22 CAT6A UTP mtrs 10.37 50.00 518.56
12.02.03.23 Cabling Consumables units 20.00 80.00 1,600.00
Subtotal for 12.02.03- IP Based CCTV Surveillance System 106,914.56
12.02.04 CATV System
12.02.04.01 CATV OUTLET units 350.00 -
12.02.04.02 CATV Cabinet units 1,500.00 -
12.02.04.03 Main CATV Panel uniit 15,000.00 -
12.02.04.04 Pull Box 25mm x 250mm x150mm pcs 200.00 -
12.02.04.05 IMC Conduit 25mm pcs 402.00 -
12.02.04.06 IMC Coupling 25mm pcs 46.00 -
12.02.04.07 Junction Box pcs 45.00 -
12.02.04.08 Square Box pcs 85.00 -
12.02.04.09 Utility box pcs 35.00 -
12.02.04.10 Locknut and Bushing 25mm pcs 20.00 -
12.02.04.11 Hanger and Support units 50.00 -
12.02.04.12 Roogh -In Consumables units 50.00 -
12.02.04.13 RG6U 70% Braided m 35.00 -
12.02.04.14 Cabling Consumables units 80.00 -
Subtotal for 12.02.04- CATV System -
12.02.05 Access Control System
12.02.05.01 Network Switch (Inside IDF) units 1.00 30,000.00 30,000.00
12.02.05.02 Patch Panel ( Inside IDF) units 1.00 5,000.00 5,000.00
12.02.05.03 Door Controller units 1.00 25,000.00 25,000.00
12.02.05.04 SD-1 -DOOR SENSOR units 1.00 15,300.00 15,300.00
12.02.05.05 Card Reader units 2,500.00 -
12.02.05.06 Input Module units 2,500.00 -
12.02.05.07 Door Contact units 2,500.00 -
12.02.05.08 UPS units 5,000.00 -
12.02.05.09 MDF units 15,000.00 -
12.02.05.10 Server - Complete Set units 65,000.00 -
12.02.05.11 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.02.05.12 IMC Conduit 25mm pcs 3.00 402.00 1,206.00
12.02.05.13 IMC Coupling 25mm units 3.00 46.00 138.00
12.02.05.14 Junction Box pcs 1.00 45.00 45.00
12.02.05.15 Square Box pcs 1.00 85.00 85.00
12.02.05.16 Utility box pcs 35.00 -
12.02.05.17 Locknut and Bushing 25mm pcs 5.00 20.00 100.00
12.02.05.18 Flexible Metalic Conduit mtrs 1.00 85.00 85.00
12.02.05.19 FMC Connector pcs 2.00 20.00 40.00
12.02.05.20 Hanger and Support units 7.00 50.00 350.00
12.02.05.21 Roogh -In Consumables units 1.00 50.00 50.00
12.02.05.22 #16 Shielded Twisted Pair mtrs 7.71 31.00 238.98
12.02.05.23 Cabling Consumables units 4.00 80.00 320.00
Subtotal for 12.02.05- Access Control System 78,157.98
12.02.07 Structured Cabling System
12.07.07.01 IDF units 1.00 150,000.00 150,000.00
12.07.07.02 Network Switch (Inside IDF) units 1.00 28,113.00 28,113.00
12.07.07.03 Patch Panel ( Inside IDF) units 1.00 3,792.00 3,792.00
12.07.07.04 Dual Port Universal Information Outlet (Table Mounted) units 10.00 550.00 5,500.00
12.07.07.05 Dual Port Universal Information Outlet (Wall Mounted) units - 550.00 -
12.07.07.06 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.07.07.07 IMC Conduit 25mm pcs 37.00 402.00 14,874.00
12.07.07.08 IMC Coupling 25mm pcs 37.00 46.00 1,702.00
12.07.07.09 Junction Box pcs 7.00 45.00 315.00
12.07.07.10 Square Box pcs 1.00 85.00 85.00
12.07.07.11 Utility box pcs 1.00 35.00 35.00
Division Description Unit Quantity Unit Cost Total Amount Remarks

12.07.07.12 Locknut and Bushing 25mm pcs 45.00 20.00 900.00


12.07.07.13 Cable Tray 150mm x 150mm mtrs - 5,000.00 -
12.07.07.14 Cable Tray Fittings pcs - 2,000.00 -
12.07.07.15 Hanger and Support units 110.00 50.00 5,500.00
12.07.07.16 Roogh -In Consumables units 10.00 50.00 500.00
12.07.07.17 LAN Cable Cat 6 UTP mtrs 347.12 50.00 17,355.86
12.07.07.18 Cabling Consumables units 18.00 80.00 1,440.00
Subtotal for 12.02.07- Structured Cabling System 230,311.86
12.02.10 Testing and Commissioning
Testing and Commissioning for all Auxiliaries and Electronics lot 1.00 4,918.92 4,918.92
12.02.10.01
Works
Subtotal for 12.02.10- Testing and Commissioning 4,918.92
TOTAL FOR 12.02 - AUXILIARIES AND ELECTRONICS 751,259.23

ESTIMATED TOTAL CONSTRUCTION COST OF B13 4,146,284.48

You might also like