Professional Documents
Culture Documents
Male Datrc-B13: Dorm Manager Bill of Quantity (Boq) : Provisional Amount Provisional Amount Provisional Amount
Male Datrc-B13: Dorm Manager Bill of Quantity (Boq) : Provisional Amount Provisional Amount Provisional Amount
08/11/2019
FLOOR AREA: 90.00
MALE DATRC- B13: DORM MANAGER BILL OF QUANTITY (BOQ) COST PER SM 46,069.83
Block Masonry (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
4.01
Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project requirements
Plastering (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
4.02
Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project requirements
4.02.01 Exterior Plastering sq.m. 56.75 571.50 32,432.63
4.02.02 Interior plastering sq.m. 116.29 508.00 59,075.32
Subtotal for 4.02.01- Exterior Plastering 91,507.95
Roof Deck Topping (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per Architect/ Engineer's specification, approval and
4.03
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project requirements
50mm Concrete Topping on roofdecks;
4.03.01 sq.m. - 342.75 -
Verify specifications
Subtotal for 4.03- Roof Deck Topping (Supply and
-
installation of contracted scope with fittings and
5 METALS 260,887.21
Structural Metal Framing (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's
5.01 specification, approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance
with the project requirements
5.01.01 Structural Steel Framing Beams and Columns including Base kgs - 104.08 -
Plates, Anchor Bolts and nuts, washers and other accessories to
complete the system
5.01.02 Roof Framing; Rafters, Trusses, Purlins, including base plates, sq.m. 2,506.60 104.08
anchor bolts and nuts, washers and other accessories to
complete the system 260,887.21
Metal Fabrications (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
5.02 approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project
requirements
5.02.01 Stair Railings l.m. - 4,737.47 -
5.02.02 Stair metal nosing l.m. - 1,016.00 -
Subtotal for 5- METALS 260,887.21
6 CARPENTRY/CASEWORK 23,285.85
Casework (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per Architect/ Engineer's specification, approval and
6.01 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
Male MaleDorm Manager; Pantry, CAB-B1 with CAB-B3A set(s) 1.00 23,285.85 23,285.85
Subtotal for 6.01- Casework 23,285.85
7 THERMAL AND MOISTURE PROTECTION 187,559.08
Damp Proofing and Water Proofing (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
7.01 approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project
requirements
7.01.01 Polyethelene sheet, 6mil damp proofing for footings and slabs sq.m. 72.00 63.50 4,572.00
on ground
7.01.02 WP-1: Solvent free Liquid-applied elastomeric waterproofing sq.m.
membran
7.01.03 WP-2: 2 component cementitious waterproofing system sq.m. - 1,905.00 -
7.01.04 WP-3: Potable Water Grade 2 component epoxy coating sq.m.
7.01.05 WP-4: Xypex Crystalline Waterproofing sq.m.
Hot-applied Membrane Water Proofing for roof decks,
7.01.06 sq.m.
verify specifications
Subtotal for 7.01- Damp Proofing and Water Proofing
4,572.00
(Supply and installation of contracted scope with fittings
7.02
Thermal Protection (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project requirements
Ceiling Finishes (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
9.05 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
9.05.01 C1 600 mm x 600 mm Tegular Bevealed Acoustic Tiles sq.m. 47.97 882.10 42,311.11
9.05.02 C2 12 mm THK Boral Echostop sq.m. 942.63 -
9.05.03 C3 12 mm THK Moisture resistant, Flat Latex Paint Finish sq.m. 27.13 993.86 26,959.02
9.05.04 C4 12 mm THK Moisture resistant, Flat Anti Bacterial Paint Finish sq.m. 1,005.76 -
9.05.05 C6 200 mm Wide Powder Coated Wood sq.m. 48.38 825.50 39,934.20
9.05.06 C7 Exposed Underside of Slab/Beam sq.m. 317.50 -
9.05.07 C8 Exposed Underside of Roof sq.m. 317.50 -
9.05.08 C11 uPVC Wood Grain Ceiling Panels sq.m. 536.58 -
9.05.09 C12 6 mm THK Frosted Acrylic Sheet sq.m. 9,525.00 -
9.05.10 C13 600 x 600 mm Aluminum Powder Coated Ceiling sq.m. 1,764.20 -
Subtotal for 9.05- Ceiling Finishes 109,204.32
10 SPECIALTIES -
10.01 Façade Architectural Louvres and Slats (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to
acquire approval as "approved equivalent" in case the specified are not locally available)
10.01.01 50mmx100mmx1.5mm thk Primed and Painted Tubular Steel lm - 651.48 -
Horizontal Grilles @ 150mm O.C on 50 mm x 100mm Vertical
Steel Frame
Subtotal for 10.01- Façade Architectural Louvres and Slats -
Special Wall Finishes (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
10.02 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
10.02.01 W7 Stone Veneer Cladding sq.m. - 2,000.18 -
Subtotal for 10.02- Special Wall Finishes -
11 MECHANICAL WORKS 906,893.97
11.01 Mechanical Ventilation and Air-Conditioning System (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's
specification, approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem
necessary and or to acquire approval as "approved equivalent" in case the specified are not locally available)
11.01.01 Ductworks
11.01.01.01 GI Rectangular Ducts 1400X800 l.m. 7,423.55 -
11.01.01.02 GI Rectangular Ducts 890X450 l.m. 6,091.65 -
11.01.01.03 GI Rectangular Ducts 450x250 l.m. 3,413.24 -
11.01.01.04 GI Rectangular Ducts 400x200 l.m. 3,117.51 -
11.01.01.05 GI Rectangular Ducts 350x150 l.m. 2,840.50 -
11.01.01.06 GI Rectangular Ducts 300x200 2,542.50 -
11.01.01.07 GI Rectangular Ducts 250x200 l.m. 1,817.52 -
11.01.01.08 GI Rectangular Ducts 200x200 l.m. 1,601.88 -
11.01.01.09 GI Rectangular Ducts 200x150 l.m. 1,460.89 -
11.01.01.10 GI Rectangular Ducts 150x150 l.m. 10.00 1,319.90 13,199.00
11.01.01.11 GI Rectangular Ducts 100x100 l.m. 10.00 1,159.74 11,597.40
11.01.01.12 Ductworks ancillaries including flexible connections, hangers, l.s 1.00 22,179.89 22,179.89
supports and flanges as required.
11.01.01.13 Vent Caps pc(s) 3,044.50 -
11.01.01.14 Ref Net pc(s) 2,500.00 -
11.01.01.15 Supply and fix equipment ancillaries Ventilation fans; including l.s 1.00 155,259.80 155,259.80
all necessary accessories, controls, cables/wirings, conduits and
connections; complete as in the equipment schedule and as
prescribed
11.01.02 Fans and Blowers
11.01.02.01 Ceiling Casette
11.01.02.01.01 1 Phase, 400 V, 60 Hz, 130 LPS set(s) 13,596.00 -
11.01.02.01.02 1 Phase, 230 V, 60 Hz, 95 LPS set(s) 10,782.55 -
11.01.02.01.03 1 Phase, 230 V, 60 Hz, 85 LPS set(s) 10,782.55 -
11.01.02.01.04 1 Phase, 230 V, 60 Hz, 65 LPS set(s) 1.00 10,782.55 10,782.55
11.01.02.01.05 1 Phase, 230 V, 60 Hz, 25LPS set(s) 2.00 10,782.55 21,565.10
11.01.02.03 IN LINE CENTRIFUGAL FAN
11.01.02.03.01 1 Phase, 230 V, 60 Hz, 2000 LPS set(s) - 34,627.50 -
11.01.02.03.02 1 Phase, 230 V, 60 Hz, 150 LPS set(s) 28,537.20 -
11.01.02.03.03 1 Phase, 230 V, 60 Hz, 100 LPS set(s) 28,537.20 -
11.01.02.04 OSCILLATING AND CEILING FANS
11.01.02.04.01 1 Phase, 230 V, 60 Hz, 2,650 LPS set(s) 13,145.87 -
11.01.02.04.02 1 Phase, 230 V, 60 Hz, 1,433 LPS set(s) 13,145.87 -
11.01.02.05 PROPELLER TYPE
11.01.02.05.01 1 Phase, 230 V, 60 Hz, 1878 LPS set(s) 4,280.00 -
11.01.02.06 Range Hood
11.01.02.06.01 Wall Mounted, Ducted Exhaust; 1 Phase, 230 V, 60 Hz, 216 LPS set(s) 32,100.00 -
Division Description Unit Quantity Unit Cost Total Amount Remarks
Subtotal for 12.01.03- Boxes, Pullboxes, Wire Gutter, and other related accessories 5,922.00
12.01.04 Conduits -
12.01.04.01 IMC 15mm dia. pcs 66.00 223.00 14,718.00
Subtotal for 12.01.04- Conduits 14,718.00
12.01.05 Wires and Cables -
12.01.05.01 THWN 3.5 sq.mm m 750.00 24.00 18,000.00
Subtotal for 12.01.05- Wires and Cables 18,000.00
12.01.06 Power Systems and Panel Boards
included in the main BOQ
Subtotal for 12.01.06- Power Systems and Panel Boards
-
TOTAL FOR 12.01 - ELECTRICAL WORKS 108,681.00
Auxiliaries and Electronics(Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
12.02 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
12.02.01 Fire Detection and Alarm System
12.02.01.01 Addressable Smoke Detector Units 15.00 2,500.00 37,500.00
12.02.01.02 Addressable Smoke Detector w/ Base Sounder Units 2,500.00 -
12.02.01.03 Adressable Heat Detector Units 2,500.00 -
12.02.01.04 Addressable Output Module Units 2,500.00 -
12.02.01.05 Addressable Input Module Units 1.00 2,500.00 2,500.00
12.02.01.06 Addressable Manual Pull Station Units 1.00 2,500.00 2,500.00
12.02.01.07 Fire Alarm Speaker w/ Strobe Light Units 1.00 2,500.00 2,500.00
12.02.01.08 UPS-Uniteruptable Power Supply Units 15,000.00 -
12.02.01.09 GAP- Graphical Annunciator Panel Units 5,000.00 -
12.02.01.10 Firemen Telephone Jack Units 2,500.00 -
12.02.01.11 MFACP-Main Fire Alarm Control Panel Units 500,000.00 -
12.02.01.12 SFACP- Seondary Fire Alarm Control Panel Units 426,836.00 -
12.02.01.13 Evacuation Panel Units 1.00 5,000.00 5,000.00
12.02.01.14 Pull Box 25mm x 250mm x150mm Pcs 1.00 200.00 200.00
12.02.01.15 IMC Conduit 25mm Pcs 13.00 402.00 5,226.00
12.02.01.16 IMC Coupling 25mm Pcs 13.00 46.00 598.00
12.02.01.17 Junction Box Pcs 18.00 45.00 810.00
12.02.01.18 Square Box Pcs 15.00 85.00 1,275.00
12.02.01.19 Utility box Pcs 2.00 35.00 70.00
12.02.01.20 Locknut and Bushing 25mm Pcs 88.00 20.00 1,760.00
12.02.01.21 Flexible Metalic Conduit Pcs 15.00 85.00 1,275.00
12.02.01.22 FMC Connector Pcs 30.00 20.00 600.00
12.02.01.23 Hanger and Support mtrs 1.00 50.00 50.00
12.02.01.24 Roogh -In Consumables pcs 1.00 50.00 50.00
12.02.01.25 #16 Twisted Pair Wire mtrs 1,857.37 31.00 57,578.60
12.02.01.26 Cabling Consumables Units 3.00 80.00 240.00
Subtotal for 12.02.01- Fire Detection and Alarm System 119,732.60
12.02.02 IP Based Public Address
12.02.02.01 Network Switch ( Inside IDF) Pcs 1.00 38,967.00 38,967.00
12.02.02.02 Network Manager ( Inside IDF) mtrs 1.00 12,679.00 12,679.00
12.02.02.03 Power Amplifier ( Inside IDF) pcs 1.00 120,000.00 120,000.00
12.02.02.04 UPS Units 1.00 5,000.00 5,000.00
12.02.02.05 6w Ceiling Mounted Speaker set(s) 5.00 1,800.00 9,000.00
12.02.02.06 10w Wall Miunted Speaker set(s) - 2,800.00 -
12.02.02.07 Pull Box 25mm x 250mm x150mm set(s) 1.00 200.00 200.00
12.02.02.08 IMC Conduit 25mm l.m. 21.00 577.00 12,117.00
12.02.02.09 IMC Coupling 25mm Pcs 21.00 46.00 966.00
12.02.02.10 Junction Box Unit 5.00 45.00 225.00
12.02.02.11 Square Box Units 1.00 85.00 85.00
12.02.02.12 Utility box Units 2.00 35.00 70.00
12.02.02.13 Locknut and Bushing 25mm Units 145.00 20.00 2,900.00
12.02.02.14 Flexible Metalic Conduit Units 18.00 85.00 1,530.00
12.02.02.15 FMC Connector Units 36.00 20.00 720.00
12.02.02.16 Hanger and Support Units 61.00 50.00 3,050.00
12.02.02.17 Roogh -In Consumables Units 8.00 50.00 400.00
12.02.02.18 #16 Shielded Twisted Pair Wire pcs 55.30 31.00 1,714.32
12.02.02.19 Cabling Consumables pcs 20.00 80.00 1,600.00
Subtotal for 12.02.02- IP Based Public Address 211,223.32
12.02.03 IP Based CCTV Surveillance System
12.02.03.01 Network Video Recorder units - 15,000.00 -
12.02.03.02 Patch Panel units 1.00 31,784.00 31,784.00
12.02.03.03 POE Switch units 1.00 45,738.00 45,738.00
12.02.03.04 Server units - 65,000.00 -
12.02.03.05 32" LED Spot Monitor units - 18,000.00 -
12.02.03.06 42" LED Spot Monitor units - 25,000.00 -
Division Description Unit Quantity Unit Cost Total Amount Remarks
12.02.03.07 Fixed Colored IP CCTV Camera (Dome Type) units 1.00 15,000.00 15,000.00
12.02.03.08 Fixed Colored IP CCTV Camera (Dome Type) WP units - 15,000.00 -
12.02.03.09 UPS units 1.00 10,000.00 10,000.00
12.02.03.10 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.02.03.11 IMC Conduit 15mm units 4.00 223.00 892.00
12.02.03.12 IMC Coupling 15mm pcs 4.00 23.00 92.00
12.02.03.13 Junction Box pcs 1.00 45.00 45.00
12.02.03.14 Square Box pcs 1.00 85.00 85.00
12.02.03.15 Utility box pcs 1.00 35.00 35.00
12.02.03.16 Locknut and Bushing 25mm pcs 5.00 20.00 100.00
12.02.03.17 Flexible Metalic Conduit pcs 1.00 85.00 85.00
12.02.03.18 FMC Connector pcs 2.00 20.00 40.00
12.02.03.19 Cable Tray 150mm x 150mm mtrs - 5,000.00 -
12.02.03.20 Hanger and Support pcs 11.00 50.00 550.00
12.02.03.21 Roogh -In Consumables Units 3.00 50.00 150.00
12.02.03.22 CAT6A UTP mtrs 10.37 50.00 518.56
12.02.03.23 Cabling Consumables units 20.00 80.00 1,600.00
Subtotal for 12.02.03- IP Based CCTV Surveillance System 106,914.56
12.02.04 CATV System
12.02.04.01 CATV OUTLET units 350.00 -
12.02.04.02 CATV Cabinet units 1,500.00 -
12.02.04.03 Main CATV Panel uniit 15,000.00 -
12.02.04.04 Pull Box 25mm x 250mm x150mm pcs 200.00 -
12.02.04.05 IMC Conduit 25mm pcs 402.00 -
12.02.04.06 IMC Coupling 25mm pcs 46.00 -
12.02.04.07 Junction Box pcs 45.00 -
12.02.04.08 Square Box pcs 85.00 -
12.02.04.09 Utility box pcs 35.00 -
12.02.04.10 Locknut and Bushing 25mm pcs 20.00 -
12.02.04.11 Hanger and Support units 50.00 -
12.02.04.12 Roogh -In Consumables units 50.00 -
12.02.04.13 RG6U 70% Braided m 35.00 -
12.02.04.14 Cabling Consumables units 80.00 -
Subtotal for 12.02.04- CATV System -
12.02.05 Access Control System
12.02.05.01 Network Switch (Inside IDF) units 1.00 30,000.00 30,000.00
12.02.05.02 Patch Panel ( Inside IDF) units 1.00 5,000.00 5,000.00
12.02.05.03 Door Controller units 1.00 25,000.00 25,000.00
12.02.05.04 SD-1 -DOOR SENSOR units 1.00 15,300.00 15,300.00
12.02.05.05 Card Reader units 2,500.00 -
12.02.05.06 Input Module units 2,500.00 -
12.02.05.07 Door Contact units 2,500.00 -
12.02.05.08 UPS units 5,000.00 -
12.02.05.09 MDF units 15,000.00 -
12.02.05.10 Server - Complete Set units 65,000.00 -
12.02.05.11 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.02.05.12 IMC Conduit 25mm pcs 3.00 402.00 1,206.00
12.02.05.13 IMC Coupling 25mm units 3.00 46.00 138.00
12.02.05.14 Junction Box pcs 1.00 45.00 45.00
12.02.05.15 Square Box pcs 1.00 85.00 85.00
12.02.05.16 Utility box pcs 35.00 -
12.02.05.17 Locknut and Bushing 25mm pcs 5.00 20.00 100.00
12.02.05.18 Flexible Metalic Conduit mtrs 1.00 85.00 85.00
12.02.05.19 FMC Connector pcs 2.00 20.00 40.00
12.02.05.20 Hanger and Support units 7.00 50.00 350.00
12.02.05.21 Roogh -In Consumables units 1.00 50.00 50.00
12.02.05.22 #16 Shielded Twisted Pair mtrs 7.71 31.00 238.98
12.02.05.23 Cabling Consumables units 4.00 80.00 320.00
Subtotal for 12.02.05- Access Control System 78,157.98
12.02.07 Structured Cabling System
12.07.07.01 IDF units 1.00 150,000.00 150,000.00
12.07.07.02 Network Switch (Inside IDF) units 1.00 28,113.00 28,113.00
12.07.07.03 Patch Panel ( Inside IDF) units 1.00 3,792.00 3,792.00
12.07.07.04 Dual Port Universal Information Outlet (Table Mounted) units 10.00 550.00 5,500.00
12.07.07.05 Dual Port Universal Information Outlet (Wall Mounted) units - 550.00 -
12.07.07.06 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.07.07.07 IMC Conduit 25mm pcs 37.00 402.00 14,874.00
12.07.07.08 IMC Coupling 25mm pcs 37.00 46.00 1,702.00
12.07.07.09 Junction Box pcs 7.00 45.00 315.00
12.07.07.10 Square Box pcs 1.00 85.00 85.00
12.07.07.11 Utility box pcs 1.00 35.00 35.00
Division Description Unit Quantity Unit Cost Total Amount Remarks