Male Datrc-B12: Activity Center Bill of Quantity (Boq) : Provisional Amount Provisional Amount Provisional Amount

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

PROPOSED DRUG ABUSE TREATMENT

AND REHABILITATION CENTER


Brgy. Osorio, Trece Martires, Cavite

08/11/2019
FLOOR AREA: 835.70
MALE DATRC- B12: ACTIVITY CENTER BILL OF QUANTITY (BOQ) COST PER SM 26,792.51

Division Description Unit Quantity Unit Cost Total Amount Remarks

2 SITE DEVELOPMENT 827,157.50


(Manner of Installation/ Execution shall be compliant with the standard methodology and acceptable norms and shall follow the Architect/ Engineer's further instruction)
2.01 Site Preparations
2.01.01 Clearing and Grubbing sq.m. 835.70 31.75 26,533.48
2.01.02 Demolition Works lot 1.00 4,567.49 4,567.49 Provisional Amount
2.01.03 Disposal of Debris from demolition cu.m. 7.19 2,523.11 18,148.51 Provisional Amount
2.01.04 Dayworks lot 1.00 72,344.87 72,344.87 Provisional Amount
Subtotal for 2.01 - Site Preparations 121,594.35
2.02 Earthworks
2.02.01 Structural Excavation for Building Foundations cu.m. 257.93 762.00 196,538.85
2.02.02 Hauling and Disposal of excavated unsuitable material cu.m. 51.59 1,270.00 65,512.95
2.02.03 Backfilling and Compaction cu.m. 206.34 1,270.00 262,051.80
2.02.04 Disposal of Water (Dewatering) lot 1.00 11,418.74 11,418.74 Provisional Amount
2.02.05 Trimming Works sq.m. 214.51 635.00 136,213.85
2.02.06 Soil Poisoning sq.m. 224.75 127.00 28,543.25 Provisional Amount
2.02.07 Gravel Bedding (100mm thk.) cu.m. 2.08 2,540.00 5,283.71
Subtotal for 2.02 - Earthworks 705,563.14
3 CONCRETE WORKS 2,587,842.63
(Supply and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions. Manner of
Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project requirements

3.01A Reinforcing Steel Bars; Grade 60


3.01.01 Foundations kgs 915.06 77.47 70,889.37
3.01.02 Columns kgs 1,544.46 77.47 119,649.67
3.01.03 Concrete Walls kgs 77.47 -
3.01.04 Beams and Girders kgs 4,924.60 77.47 381,508.98
3.01B Reinforcing Steel Bars; Grade 40
3.01.05 Suspended Slabs; Slabs on-grade kgs 2,372.66 75.97 180,251.28
3.01.06 Stairs kgs 75.97 -
3.01.07 Sewage and Sump pits kgs
Subtotal for CONCRETE WORKS- 752,299.30
3.02 Formworks; including shoring and bracing work
3.02.01 Foundations sq.m. 10.77 2,778.15 29,920.68
3.02.02 Columns sq.m. 16.08 2,778.15 44,672.65
3.02.03 Concrete Walls sq.m. 2,778.15 -
3.02.04 Beams and Girders sq.m. 258.34 2,778.15 717,710.74
3.02.05 Suspended Slabs; Slabs on-grade sq.m. - 2,778.15 -
3.02.06 Stairs sq.m. - 2,778.15 -
3.02.07 Sewage and Sump pits sq.m.
Subtotal for 3.02- Formworks; including shoring and 792,304.07
3.03 Cast-in-place
bracing work Concrete
3.03.01 Foundations cu.m. 16.74 6,854.95 114,731.30
3.03.02 Columns cu.m. 8.08 6,854.95 55,381.14
3.03.03 Concrete Walls cu.m. 6,854.95 -
3.03.04 Beams and Girders cu.m. 59.22 6,854.95 405,967.28
3.03.05 Suspended Slabs; Slabs on-grade cu.m. 63.99 6,854.95 438,632.48
3.03.06 Stairs cu.m. 6,854.95 -
3.03.07 Sewage and Sump pits cu.m.
Subtotal for 3.03- Cast-in-place Concrete 1,014,712.20
3.04 Concrete Accessories
3.04.01 Waterstops l.m. 3.60 1,090.50 3,921.93 Provisional Quantity
3.04.02 Contraction Joints l.m. 17.98 652.40 11,731.63 Provisional Quantity
3.04.03 Expansion Joints l.m. 17.98 652.40 11,731.63 Provisional Quantity
3.04.04 Block-outs sets 3.60 317.50 1,141.87 Provisional Quantity
Subtotal for 3.04- Concrete Accessories 28,527.06
4 MASONRY 957,056.76

Block Masonry (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
4.01
Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project requirements

4.01.01 CHB Laying 150mm sq.m. 255.24 1,079.50 275,531.58


4.01.02 CHB Laying 100mm sq.m. 213.12 889.00 189,463.68
Subtotal for 4.01- Block Masonry (Supply and installation
464,995.26
of contracted scope with fittings and hardware to
Division Description Unit Quantity Unit Cost Total Amount Remarks

Plastering (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
4.02
Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project requirements
4.02.01 Exterior Plastering sq.m. 255.24 571.50 145,869.66
4.02.02 Interior plastering sq.m. 681.48 508.00 346,191.84
Subtotal for 4.02.01- Exterior Plastering 492,061.50
Roof Deck Topping (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per Architect/ Engineer's specification, approval and
4.03
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project requirements
50mm Concrete Topping on roofdecks;
4.03.01 sq.m. - 342.75 -
Verify specifications
Subtotal for 4.03- Roof Deck Topping (Supply and
-
installation of contracted scope with fittings and
5 METALS 4,675,117.12
Structural Metal Framing (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's
5.01 specification, approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance
with the project requirements
5.01.01 Structural Steel Framing Beams and Columns including Base kgs 22,304.29 104.08 2,321,430.19
Plates, Anchor Bolts and nuts, washers and other accessories to
complete the system
5.01.02 Roof Framing; Rafters, Trusses, Purlins, including base plates, sq.m. 22,614.21 104.08
anchor bolts and nuts, washers and other accessories to
complete the system 2,353,686.93
Metal Fabrications (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
5.02 approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Testing shall be strictly adhered in accordance with the project
requirements
5.02.01 Stair Railings l.m. - 4,737.47 -
5.02.02 Stair metal nosing l.m. - 1,016.00 -
Subtotal for 5- METALS 4,675,117.12
6 CARPENTRY/CASEWORK -
Casework (Supply, fabrication and installation of the contracted scope with fittings and hardware to complete. All materials shall be as per Architect/ Engineer's specification, approval and
6.01 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
Subtotal for 6.01- Casework -
7 THERMAL AND MOISTURE PROTECTION 1,937,780.39
Damp Proofing and Water Proofing (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
7.01 approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project
requirements
7.01.01 Polyethelene sheet, 6mil damp proofing for footings and slabs sq.m. 836.46 63.50 53,115.21
on ground
7.01.02 WP-1: Solvent free Liquid-applied elastomeric waterproofing sq.m.
membran
7.01.03 WP-2: 2 component cementitious waterproofing system sq.m. - 1,905.00 -
7.01.04 WP-3: Potable Water Grade 2 component epoxy coating sq.m.
7.01.05 WP-4: Xypex Crystalline Waterproofing sq.m.
Hot-applied Membrane Water Proofing for roof decks,
7.01.06 sq.m.
verify specifications
Subtotal for 7.01- Damp Proofing and Water Proofing
53,115.21
(Supply and installation of contracted scope with fittings
7.02
Thermal Protection (Supply and installation of contracted scope with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Relative Testing shall be strictly adhered in accordance with the project requirements

7.02.01 Rigid Thermal Insulation for Roof Decks sq.m. - 952.50 -


7.02.02 Roof Thermal Insulation, verify specifications sq.m. 1,884.34 184.15 347,001.28
Subtotal for 7.02- Thermal Protection (Supply and
347,001.28
installation of contracted scope with fittings and
7.03 Roof Covering (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
7.03.01 Preformed Pre-painted G.I. "Banawe" Type Roof, ga. 24, l.m. 1,129.63 1,361.21 1,537,663.90
including Bended Accessories, Metal Gutters 0.6mm thk and
consumables
7.03.02 Reinforced Concrete Gutter l.m. - 1,905.00 -
7.03.03 Laminated Glass Skylight, verify specs sq.m. - 1,769.57 -
Subtotal for 7.03- Roof Covering (Supply and installation
1,537,663.90
of the system with fittings and hardware to complete. All
8 OPENINGS 5,578,257.78
8.01 Doors (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions. Manner of
Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as "approved
equivalent" in case the specified are not locally available)
8.01.01 Solid Core Flush Wood Door Type B
8.01.01.01 Solid Core Flush Wood Door Type B; Single Leaf; With Louver; set(s) 1.00 18,806.29 18,806.29
Swing Type; 900Wx2400H; HPL Door Face Finish; Jamb Type J-1;
Hinge Type H-1 (4pcs); Lockset Type L-8 (1pc); Threshold Type T-
1; Door Silencer (M-1)
Division Description Unit Quantity Unit Cost Total Amount Remarks

8.01.01.02 Solid Core Flush Wood Door Type B; Single Leaf; With Louver; set(s) 2.00 16,716.70 33,433.40
Swing Type; 800Wx2400H; HPL Door Face Finish; Jamb Type J-1;
Hinge Type H-1 (4pcs); Lockset Type L-8 (1pc); Threshold Type T-
1; Door Silencer (M-1)
8.01.01.03 Solid Core Flush Wood Door Type B; Single Leaf; Vision Panel set(s) 1.00 18,806.29 18,806.29
Type VP-1 (1pc); Swing Type; 900Wx2400H; HPL Door Face
Finish; Jamb Type J-1; Hinge Type H-1 (4pcs); Lockset Type L-2
(1pc); Closer Type C-1 (1pc); Door Stop Type S-3 (1pc) Door
Silencer (M-1)
8.01.01.04 Solid Core Flush Wood Door Type B; Single Leaf; With Louver; set(s) 1.00 16,716.70 16,716.70
Swing Type; 800Wx2400H; HPL Door Face Finish; Jamb Type J-1;
Hinge Type H-1 (4pcs); Lockset Type L-18 (1pc); Armor/Kick Plate
Type KP-1 (1pc); Push Plate Type PP-1 (1pc); Threshold type T-2;
Door Pull Type P-2 (1pc); Door Silencer (M-1)
8.01.01.05 set(s) 1.00 37,612.58 37,612.58
Solid Core Flush Wood Door Type B; Double Leaf; Swing Type;
2@900Wx2400H; HPL Door Face Finish; Jamb Type J-1; Hinge
Type H-4 (8pcs); Lockset Type L-15 (1pc); Flushbolt Type FB-1
(1pc); Door Silencer (M-1)
Subtotal for 8.01- Doors 125,375.26
8.02 Windows (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per Architect/ Engineer's specification, approval and instructions. Manner of
Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as "approved
equivalent" in case the specified are not locally available)
8.02.01 Built Up Lattice Grilles
8.02.01.01 Primed and Painted Steel Lattice Grilles on Tubular Steel set(s) 1.00 65,314.29 65,314.29
Frames; 3000Hx6000W
8.02.01.02 Primed and Painted Steel Lattice Grilles on Tubular Steel set(s) 5.00 39,188.57 195,942.86
Frames; 1800Hx6000W
8.02.01.03 Primed and Painted Steel Lattice Grilles on Tubular Steel set(s) 1.00 52,251.43 52,251.43
Frames; 3000Hx4800W
8.02.01.04 Primed and Painted Steel Lattice Grilles on Tubular Steel set(s) 1.00 43,107.43 43,107.43
Frames; 1800Hx6600W
8.02.02 Fixed Mechanical Storm Resistant Louvers
8.02.02.01 Primed and Painted Storm Resistant Steel Louvers; set(s) 10.00 190,692.85 1,906,928.54
2800Hx6000W
8.02.02.02 Primed and Painted Storm Resistant Steel Louvers; set(s) 4.00 423,270.03 1,693,080.12
(2800+2850)Hx6600W
8.02.02.03 Primed and Painted Storm Resistant Steel Louvers; set(s) 2.00 384,790.94 769,581.87
(2800+2850)Hx6000W
8.02.02.04 Primed and Painted Storm Resistant Steel Louvers; set(s) 6.00 68,104.59 408,627.54
1000Hx6000W
8.02.02.05 Primed and Painted Storm Resistant Steel Louvers; set(s) 2.00 159,024.22 318,048.44
(1000+1335)Hx6000W
Subtotal for 8.02- Windows 5,452,882.52
9 FINISHES 1,678,021.83
Partitions (Supply and installation of the system, complete as per the Architect/ Engineer's specification, approval and instructions. Material Sample/s have to be provided when deem necessary
9.01
and or to acquire approval as "approved equivalent" in case the specified are not locally available)
9.01.01 P-8 96mm th Drywall System sq.m. - 1,390.24 -
Subtotal for 9.01- Partitions -
Floor Finishes(Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
9.02 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
9.02.01 F1 300 mm x 300 mm x 3 mm THK sq.m. 671.24 -
9.02.02 F3 2 mm THK Sheet Vinyl: Regular, Anti-Bacterial sq.m. 1,558.75 -
9.02.03 F6 600 mm x 600 mm Homogenous Matte Floor Tiles sq.m. 9.49 1,409.91 13,386.56
9.02.04 F7 600 mm x 600 mm Homogenous Non Skid Floor Tiles sq.m. 1,414.71 -
9.02.05 F8 300 mm x 300 mm Homogenous Non Skid Floor Tiles sq.m. 68.70 1,310.80 90,056.15
9.02.06 F9 300 mm x 600 mm Homogenous Non Skid Stair Thread Tiles sq.m. 1,274.34 -
9.02.07 F10 Polyurethane-Based Epoxy sq.m. 681.90 1,112.61 758,688.47
9.02.08 F11 Exterior Paver Tiles sq.m.
Subtotal for 9.02- Floor Finishes 862,131.18
Wall Finishes (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
9.03 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
9.03.01 W1 Textured Elastomeric Exterior Wall Coating System sq.m. 878.38 -
9.03.02 W2 Semi- Gloss Acrylic Latex Paint Finish sq.m. 657.00 527.03 346,256.76
9.03.03 W3 Anti-Bacterial Paint Semi-Gloss Finish sq.m. 658.78 -
9.03.04 W5 300 mm x 300 mm ceramic polished tiles sq.m. 316.44 1,172.87 371,142.06
9.03.05 W6 600 mm x 600 mm Homogenous Polished Tiles sq.m. 1,414.71 -
Division Description Unit Quantity Unit Cost Total Amount Remarks

9.03.06 W7 Stone Veneer Cladding sq.m. - Included in Division 10


Subtotal for 9.03- Wall Finishes 717,398.82
Baseboards(Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions. Manner
9.04 of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as "approved
equivalent" in case the specified are not locally available)
9.04.01 B1 10 mm High Baseboard Tile l.m. - 127.00 -
9.04.02 B2 10 mm High Splayed Baseboard Tile l.m. 635.00 -
9.04.03 B3 10 mm High PVC Baseboard Tile l.m. 12.47 190.50 2,375.54
9.04.04 B4 10 mm High Cover Sheet Vinyl with Capping Seal l.m. 222.25 -
9.04.05 B5 10 mm High Epoxy Painted Baseboard l.m. 12.90 317.50 4,095.75
Subtotal for 9.04- Baseboards 6,471.29
Ceiling Finishes (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
9.05 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
9.05.01 C1 600 mm x 600 mm Tegular Bevealed Acoustic Tiles sq.m. 882.10 -
9.05.02 C2 12 mm THK Boral Echostop sq.m. 942.63 -
9.05.03 C3 12 mm THK Moisture resistant, Flat Latex Paint Finish sq.m. 92.59 993.86 92,020.54
9.05.04 C4 12 mm THK Moisture resistant, Flat Anti Bacterial Paint Finish sq.m. 1,005.76 -
9.05.05 C6 200 mm Wide Powder Coated Wood sq.m. 825.50 -
9.05.06 C7 Exposed Underside of Slab/Beam sq.m. 317.50 -
9.05.07 C8 Exposed Underside of Roof sq.m. 317.50 -
9.05.08 C11 uPVC Wood Grain Ceiling Panels sq.m. 536.58 -
9.05.09 C12 6 mm THK Frosted Acrylic Sheet sq.m. 9,525.00 -
9.05.10 C13 600 x 600 mm Aluminum Powder Coated Ceiling sq.m. 1,764.20 -
Subtotal for 9.05- Ceiling Finishes 92,020.54
10 SPECIALTIES 322,401.95
10.01 Façade Architectural Louvres and Slats (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification,
approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to
acquire approval as "approved equivalent" in case the specified are not locally available)
10.01.01 50mmx100mmx1.5mm thk Primed and Painted Tubular Steel lm 494.88 651.48 322,401.95
Horizontal Grilles @ 150mm O.C on 50 mm x 100mm Vertical
Steel Frame
Subtotal for 10.01- Façade Architectural Louvres and Slats 322,401.95
Special Wall Finishes (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
10.02 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
10.02.01 W7 Stone Veneer Cladding sq.m. - 2,000.18 -
Subtotal for 10.02- Special Wall Finishes -
11 MECHANICAL WORKS 1,925,033.39
11.01 Mechanical Ventilation and Air-Conditioning System (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's
specification, approval and instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem
necessary and or to acquire approval as "approved equivalent" in case the specified are not locally available)
11.01.01 Ductworks
11.01.01.01 GI Rectangular Ducts 1400X800 l.m. 7,423.55 -
11.01.01.02 GI Rectangular Ducts 890X450 l.m. 6,091.65 -
11.01.01.03 GI Rectangular Ducts 450x250 l.m. 10.00 3,413.24 34,132.40
11.01.01.04 GI Rectangular Ducts 400x200 l.m. 10.00 3,117.51 31,175.07
11.01.01.05 GI Rectangular Ducts 350x150 l.m. 2,840.50 -
11.01.01.06 GI Rectangular Ducts 300x200 6.00 2,542.50 15,255.00
11.01.01.07 GI Rectangular Ducts 250x200 l.m. 1,817.52 -
11.01.01.08 GI Rectangular Ducts 200x200 l.m. 1,601.88 -
11.01.01.09 GI Rectangular Ducts 200x150 l.m. 8.00 1,460.89 11,687.12
11.01.01.10 GI Rectangular Ducts 150x150 l.m. 15.00 1,319.90 19,798.50
11.01.01.11 GI Rectangular Ducts 100x100 l.m. 1,159.74 -
11.01.01.12 Ductworks ancillaries including flexible connections, hangers, l.s 1.00 22,179.89 22,179.89
supports and flanges as required.
11.01.01.13 Vent Caps pc(s) 3,044.50 -
11.01.01.14 Ref Net pc(s) 2,500.00 -
11.01.01.15 Supply and fix equipment ancillaries Ventilation fans; including l.s 1.00 155,259.80 155,259.80
all necessary accessories, controls, cables/wirings, conduits and
connections; complete as in the equipment schedule and as
prescribed
11.01.02 Fans and Blowers
11.01.02.01 Ceiling Casette
11.01.02.01.01 1 Phase, 400 V, 60 Hz, 130 LPS set(s) 13,596.00 -
11.01.02.01.02 1 Phase, 230 V, 60 Hz, 95 LPS set(s) 10,782.55 -
11.01.02.01.03 1 Phase, 230 V, 60 Hz, 85 LPS set(s) 10,782.55 -
11.01.02.01.04 1 Phase, 230 V, 60 Hz, 40 LPS set(s) 1.00 10,782.55 10,782.55
11.01.02.01.05 1 Phase, 230 V, 60 Hz, 25LPS set(s) 10,782.55 -
11.01.02.03 IN LINE CENTRIFUGAL FAN
Division Description Unit Quantity Unit Cost Total Amount Remarks

11.01.02.03.01 1 Phase, 230 V, 60 Hz, 2000 LPS set(s) 6.00 34,627.50 207,765.00
11.01.02.03.02 1 Phase, 230 V, 60 Hz, 150 LPS set(s) 28,537.20 -
11.01.02.03.03 1 Phase, 230 V, 60 Hz, 100 LPS set(s) 28,537.20 -
11.01.02.04 OSCILLATING AND CEILING FANS
11.01.02.04.01 1 Phase, 230 V, 60 Hz, 2,650 LPS set(s) 13,145.87 -
11.01.02.04.02 1 Phase, 230 V, 60 Hz, 1,433 LPS set(s) 13,145.87 -
11.01.02.05 PROPELLER TYPE
11.01.02.05.01 1 Phase, 230 V, 60 Hz, 1878 LPS set(s) 4,280.00 -
11.01.02.06 Range Hood
11.01.02.06.01 Wall Mounted, Ducted Exhaust; 1 Phase, 230 V, 60 Hz, 216 LPS set(s) 32,100.00 -

11.01.02.07 WALL MOUNTED


11.01.02.07.01 1 Phase, 230 V, 60 Hz, 191 LPS set(s) 5,350.00 -
11.01.02.07.02 1 Phase, 230 V, 60 Hz, 152 LPS set(s) 5,350.00 -
11.01.02.07.03 1 Phase, 230 V, 60 Hz, 105 LPS set(s) 5,350.00 -
11.01.02.07.04 1 Phase, 230 V, 60 Hz,97 LPS set(s) 1.00 4,280.00 4,280.00
11.01.02.07.05 1 Phase, 230 V, 60 Hz, 63 LPS set(s) 1.00 4,280.00 4,280.00
11.01.03 Air Conditioning Units
11.01.03.01 Split Type A/C: Fan Coil Units
11.01.03.01.01 5 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 125,300.10 -
11.01.03.01.02 4 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 115,475.79 -
11.01.03.01.03 3 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 107,358.72 -
11.01.03.01.04 2.5 HP Ceiling Cassette 4-way, 230 V/1P, 60 Hz set(s) 86,536.66 -
11.01.03.01.05 4 HP Ceiling Suspended, 230V/1P, 60 Hz set(s) 258,274.50 -
11.01.03.01.06 2 HP Wall Mounted, 230V/1P, 60 Hz set(s) 52,719.00 -
11.01.03.01.07 1.5 HP Wall Mounted, 230V/1P, 60 Hz set(s) 47,328.00 -
11.01.03.01.07 1 HP Wall Mounted, 230V/1P, 60 Hz set(s) 41,937.00 -
11.01.03.04 OTHERS
11.01.03.04.01 Refrigerant Pipes, insulation including hangers & supports, l.m. 5.00 782.46 3,912.30
consumables & other accessories to complete the system
11.01.03.04.02 Testing and Commissioning lot 1.00 71,044.60 71,044.60
Subtotal for 11.01 Mechanical Ventilation and Air Conditioning System 591,552.23
11.02 Fire Protection Works (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
11.02.01 Valves,fittings, sprinklers, FHC and accessories
11.02.01.01 150 mm Ø x 6m Sch 40 B.I Pipe pcs 19,082.00 -
11.02.01.02 100 mm Ø x 6m Sch 40 B.I Pipe pcs 10,996.00 -
11.02.01.03 80 mm Ø x 6m Sch 40 B.I Pipe pcs 7,370.00 -
11.02.01.04 65 mm Ø x 6m Sch 40 B.I Pipe pcs 5,536.00 -
11.02.01.05 50 mm Ø x 6m Sch 40 B.I Pipe pcs 3,578.00 -
11.02.01.06 40 mm Ø x 6m Sch 40 B.I Pipe pcs 2,640.00 -
11.02.01.07 32 mm Ø x 6m Sch 40 B.I Pipe pcs 2,094.00 -
11.02.01.08 25 mm Ø x 6m Sch 40 B.I Pipe pcs 1,622.00 -
11.02.02 Valves,fittings, sprinklers, FHC and accessories
11.02.02.01 Threadolit 2 pcs 518.00 -
11.02.02.02 Threadolit 1-1/2 pcs 410.00 -
11.02.02.03 Threadolit 1-1/4 pcs 246.00 -
11.02.02.04 Threadolit 1 pcs 204.00 -
11.02.02.05 Victaulic Groove Coupling 6"Ø pcs 2,125.50 -
11.02.02.06 Victaulic Clamp 6" pcs 2,125.50 -
11.02.02.07 Alarm Check Valve 6" pcs 38,400.00 -
11.02.02.08 Swing Check Valve 6 pcs 94,800.00 -
11.02.02.09 Flow Meter 4" pcs 21,392.00 -
11.02.02.10 Gate Valve 6 pcs 50,400.00 -
11.02.02.11 Waffer Check Valve 4 pcs 34,200.00 -
11.02.02.12 Rubber Flexible 6" pcs 2,500.00 -
11.02.02.13 Rubber Flexible 2" pcs 800.00 -
11.02.02.14 Pendant Sprinkler Head with escutheon pcs 750.00 -
11.02.03 Valves,fittings, sprinklers, FHC and accessories
11.02.03.01 FE.36-10 LBS Portable Fire Extinguisher pcs 5.00 3,000.00 15,000.00
11.02.03.02 CO2 -10 LBS Portable Fire Extinguisher pcs 1.00 3,000.00 3,000.00
11.02.03.03 Fire hose Cabinet pcs 2.00 26,000.00 52,000.00
11.02.03.04 Angle Valve 2- 12/2 pcs 15,000.00 -
11.02.03.05 Butterly Valve (w/ tamp switch)4 pcs 36,000.00 -
11.02.03.06 Water flow switch (paddle type )4" pcs 11,466.00 -
11.02.03.07 Ball Valve 1-1/4 pcs 1,072.50 -
11.02.03.08 Ball Valve 1 pcs 676.00 -
11.02.03.09 Ball Valve 1/4 pcs 312.00 -
11.02.03.10 Sight Glass 1" pcs 845.00 -
Division Description Unit Quantity Unit Cost Total Amount Remarks

11.02.03.11 Pressure Gauge 300 PSI pcs 3,000.00 -


11.02.03.12 Tee 4 x 4 pcs 906.00 -
11.02.03.13 Tee 2 1/4 x 2 1/4 pcs 646.80 -
11.02.03.14 Tee 2 x 2 pcs 560.40 -
11.02.03.15 Tee 1-1/2 x 1-1/2 pcs 474.00 -
11.02.03.16 Tee 1-1/4 x 1-1/4 pcs 432.00 -
11.02.03.17 Tee 1x 1 pcs 162.00 -
11.02.03.18 Bell Reducer 2 x 1 1/2 pcs 510.00 -
11.02.03.19 Bell Reducer 2 x 1 1/4 pcs 510.00 -
11.02.03.20 Bell Reducer 2 x 1 pcs 510.00 -
11.02.03.21 Bell Reducer 1-1/2 x 1-1/4 pcs 474.00 -
11.02.03.22 Bell Reducer 1-1/2 x 1 pcs 474.00 -
11.02.03.23 Bell Reducer 1-1/4 x 1 pcs 432.00 -
11.02.03.24 Elbow 4" pcs 668.00 -
11.02.03.25 Elbow 2 3/4 x 2 3/4 pcs 533.00 -
11.02.03.26 Elbow 2 1/2 x 2 1/2 pcs 398.00 -
11.02.03.27 Elbow 2 1/4 x 2 1/4 pcs 263.00 -
11.02.03.28 Elbow 2" pcs 128.00 -
11.02.03.29 Elbow 1-1/2 pcs 92.00 -
11.02.03.30 Elbow 1-1/4 pcs 86.00 -
11.02.03.31 Elbow 1 pcs 72.00 -
11.02.03.32 Union Patente 1-1/4 pcs 340.00 -
11.02.03.33 Union Patente 1 pcs 238.00 -
11.02.03.34 Brackets and hangers lot 0.00 264,550.00 -
Subtotal for 11.02- Fire Protection Works 70,000.00
11.03 Plumbing and Sanitary Works (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
11.03.01 Plumbing Fixtures
11.03.01.01 Water Closets set(s) 11.00 10,500.00 115,500.00
11.03.01.02 Urinals; Wall hung set(s) 10.00 6,500.00 65,000.00
11.03.01.03 Lavatories; Wall Hung, Elliptical set(s) 11.00 7,000.00 77,000.00
11.03.01.04 Lavatories; Wall Hung, Square set(s) 5,000.00 -
11.03.01.05 Flush Valves; for Water Closets, Manual set(s) 11.00 8,395.00 92,345.00
11.03.01.06 Flush Valves; for Urinals, Manual set(s) 10.00 7,360.00 73,600.00
11.03.01.07 Faucets/(Mixer); for lavatories set(s) 13.00 3,000.00 39,000.00
11.03.01.08 Showers set(s) 2,500.00 -
11.03.01.09 Floor Drains set(s) 12.00 500.00 6,000.00
11.03.02 Toilet, Shower, Janitor Closet Accessories
11.03.02.01 Paper Holders set(s) 11.00 900.00 9,900.00
11.03.02.02 Soap Holders set(s) 11.00 800.00 8,800.00
11.03.02.03 Soap Dispenser set(s) 11.00 4,550.00 50,050.00
11.03.02.04 Paper Towel Dispenser set(s) 6.00 4,000.00 24,000.00
11.03.02.05 Towel Bar set(s) 4.00 4,000.00 16,000.00
11.03.02.06 Grab Bar; for PWD set(s) 2.00 4,500.00 9,000.00
11.03.02.07 Robe Hook; double; S/S set(s) 6.00 1,100.00 6,600.00
11.03.02.08 Hand Dryer set(s) 3.00 6,500.00 19,500.00
11.03.02.09 Facial Mirrors set(s) 3.00 2,000.00 6,000.00
11.03.02.10 Mop Strip set(s) 2.00 1,500.00 3,000.00
11.03.03 Hot Water Line; including pipes, fittings and other accessories
necessary to complete the system
11.03.03.01 25mmØ" PPR pipe Length 1,880.50 -
11.03.03.02 20mmØ" PPR pipe Length 490.00 -
11.03.03.03 15mmØ" PPR pipe Length 298.00 -
11.03.04 Cold Water Line; including pipes, fittings and other accessories
necessary to complete the system
11.03.04.01 65mmØ" PPR pipe Length 3,838.50 -
11.03.04.02 60mmØ" PPR pipe Length 3,166.33 -
11.03.04.03 50mmØ" PPR pipe Length 35.00 2,665.50 93,292.50
11.03.04.04 40mmØ" PPR pipe Length 11.00 1,880.50 20,685.50
11.03.04.05 32mmØ" PPR pipe Length 4.00 1,992.00 7,968.00
11.03.04.06 25mmØ" PPR pipe Length 6.00 761.00 4,566.00
11.03.04.07 20mmØ" PPR pipe Length 7.00 490.00 3,430.00
11.03.04.08 15mmØ" PPR pipe Length 298.00 -
11.03.05 Storm DrainageSystem; including pipes, fittings and other
accessories necessary to complete the system
11.03.05.01 300mmØ" PVC pipe Length
11.03.05.02 250mmØ" PVC pipe Length 6.00 3,785.47 22,712.82
11.03.05.03 200mmØ" PVC pipe Length 11.00 2,222.00 24,442.00
11.03.05.04 150mmØ" PVC pipe Length 13.00 1,466.67 19,066.71
11.03.05.05 100mmØ" PVC pipe Length 73.00 733.33 53,533.09
Division Description Unit Quantity Unit Cost Total Amount Remarks

11.03.05.06 75mmØ" PVC pipe Length 22.00 550.00 12,100.00


11.03.05.07 Area Drain and Catch Basins set(s) 16.00 14,188.57 227,017.12
11.03.06 Sanitary Line System, Soil/Waste Pipes including fittings
and accessories necessary to complete the system
11.03.06.01 150mmØ" PVC pipe Length 1,466.67 -
11.03.06.02 100mmØ" PVC pipe Length 104.00 733.33 76,266.32
11.03.06.03 75mmØ" PVC pipe Length 550.00 -
11.03.06.04 50mmØ" PVC pipe Length 333.67 -
11.03.07 Sanitary Line System, Vent Pipes including fittings and
accessories necessary to complete the system
11.03.07.01 150mmØ" PVC pipe Length 1,466.67 -
11.03.07.02 100mmØ" PVC pipe Length 733.33 -
11.03.07.03 75mmØ"PVC pipe Length 133.00 550.00 73,150.00
11.03.07.04 50mmØ" PVC pipe Length 333.67 -
11.03.08Others
11.03.08.01 Testing and Commissioning lot 1.00 3,956.10 3,956.10
Subtotal for 11.03- Plumbing and Sanitary Works 1,263,481.16
Conveyances (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
11.04 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
10.04.01 Passenger Elevators unit(s) - 6,000,000.00 -
Subtotal for 11.04- Conveyances -
12 ELECTRICAL WORKS, AUXILIARIES AND ELECTRONICS 1,548,393.64
Electrical Works (Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and instructions.
12.01 Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire approval as
"approved equivalent" in case the specified are not locally available)
12.01.01 Lighting Fixtures
12.01.01.01 Pin Light sets 16.00 1,165.00 18,640.00
12.01.01.02 Pin Light with battery packed sets 2,500.00 -
12.01.01.03 Down Light sets 19.00 1,570.00 29,830.00
12.01.01.04 Direct Light sets 44.00 1,200.00 52,800.00
12.01.01.05 Direct Light with battery packed sets 5.00 3,250.00 16,250.00
12.01.01.06 Square Light sets 1,785.00 -
12.01.01.07 Square Light with battery packed sets 4,000.00 -
12.01.01.08 Troffer Light 300X300 sets 2,285.00 -
12.01.01.09 Troffer Light 300X300 with battery packed sets 5,000.00 -
12.01.01.10 Fluorescent Lamp sets 1,250.00 -
12.01.01.11 T5 STRIP LIGHT sets 2,420.00 -
12.01.01.12 Wall mounted Lamp sets 9.00 1,785.00 16,065.00
12.01.01.12 Exit Sign with direction sets 3,855.00 -
12.01.01.13 Emergency light sets 9.00 2,500.00 22,500.00
Subtotal for 12.01.01- Lighting Fixtures 156,085.00
12.01.02 Wiring Devices
12.01.02.01 One gang switch pcs 11.00 175.00 1,925.00
12.01.02.02 Two gang switch pcs 269.00 -
12.01.02.03 Three gang switch pcs 364.00 -
12.01.02.04 Duplex convenience outlet pcs 13.00 466.00 6,058.00
12.01.02.05 Duplex convenience outlet (GFCI) pcs 1.00 500.00 500.00
12.01.02.06 Simplex convenience outlet pcs 7.00 341.00 2,387.00
12.01.02.07 Special Outlet (EF) pcs 1.00 500.00 500.00
12.01.02.08 Special Outlet (REF) pcs 5.00 500.00 2,500.00
12.01.02.09 Special Outlet (HD) pcs 5.00 4,220.00 21,100.00
12.01.02.10 ECB, NEMA 3R, 20AT, 1P assy 3.00 600.00 1,800.00
12.01.02.11 ECB, NEMA 3R, 30AT, 1P assy 700.00 -
Subtotal for 12.01.02- Wiring Devices 36,770.00
12.01.03 Boxes, Pullboxes, Wire Gutter, and other related
accessories
12.01.03.01 Junction Box pcs 102.00 32.00 3,264.00
12.01.03.02 Utility box pcs 46.00 30.00 1,380.00
12.01.03.03 IMC Coupling 15mm pcs 275.00 42.00 11,550.00
12.01.03.04 Locknut and Bushing 15mm pcs
12.01.03.05 Pullbox with cover pcs 7.00 500.00 3,500.00
12.01.03.06 Wire gutter assy 7,400.00 -
12.01.03.07 Hangers and Support lot 1.00 7,563.00 7,563.00
Subtotal for 12.01.03- Boxes, Pullboxes, Wire Gutter, and other related accessories 27,257.00
12.01.04 Conduits -
12.01.04.01 IMC 15mm dia. pcs 275.00 223.00 61,325.00
Subtotal for 12.01.04- Conduits 61,325.00
12.01.05 Wires and Cables -
12.01.05.01 THWN 3.5 sq.mm m 3,000.00 24.00 72,000.00
Subtotal for 12.01.05- Wires and Cables 72,000.00
Division Description Unit Quantity Unit Cost Total Amount Remarks

12.01.06 Power Systems and Panel Boards


included in the main BOQ
Subtotal for 12.01.06- Power Systems and Panel Boards
-
TOTAL FOR 12.01 - ELECTRICAL WORKS 353,437.00
Auxiliaries and Electronics(Supply and installation of the system with fittings and hardware to complete. All materials shall be as per the Architect/ Engineer's specification, approval and
12.02 instructions. Manner of Installation shall be compliant with the standard methodology and acceptable norms. Material Sample/s have to be provided when deem necessary and or to acquire
approval as "approved equivalent" in case the specified are not locally available)
12.02.01 Fire Detection and Alarm System
12.02.01.01 Addressable Smoke Detector Units 6.00 2,500.00 15,000.00
12.02.01.02 Addressable Smoke Detector w/ Base Sounder Units 2,500.00 -
12.02.01.03 Adressable Heat Detector Units 2,500.00 -
12.02.01.04 Addressable Output Module Units 2,500.00 -
12.02.01.05 Addressable Input Module Units 1.00 2,500.00 2,500.00
12.02.01.06 Addressable Manual Pull Station Units 2.00 2,500.00 5,000.00
12.02.01.07 Fire Alarm Speaker w/ Strobe Light Units 6.00 2,500.00 15,000.00
12.02.01.08 UPS-Uniteruptable Power Supply Units 15,000.00 -
12.02.01.09 GAP- Graphical Annunciator Panel Units 5,000.00 -
12.02.01.10 Firemen Telephone Jack Units 2,500.00 -
12.02.01.11 MFACP-Main Fire Alarm Control Panel Units 500,000.00 -
12.02.01.12 SFACP- Seondary Fire Alarm Control Panel Units 426,836.00 -
12.02.01.13 Evacuation Panel Units 1.00 5,000.00 5,000.00
12.02.01.14 Pull Box 25mm x 250mm x150mm Pcs 1.00 200.00 200.00
12.02.01.15 IMC Conduit 25mm Pcs 37.00 402.00 14,874.00
12.02.01.16 IMC Coupling 25mm Pcs 37.00 46.00 1,702.00
12.02.01.17 Junction Box Pcs 15.00 45.00 675.00
12.02.01.18 Square Box Pcs 6.00 85.00 510.00
12.02.01.19 Utility box Pcs 8.00 35.00 280.00
12.02.01.20 Locknut and Bushing 25mm Pcs 73.00 20.00 1,460.00
12.02.01.21 Flexible Metalic Conduit Pcs 6.00 85.00 510.00
12.02.01.22 FMC Connector Pcs 12.00 20.00 240.00
12.02.01.23 Hanger and Support mtrs 1.00 50.00 50.00
12.02.01.24 Roogh -In Consumables pcs 1.00 50.00 50.00
12.02.01.25 #16 Twisted Pair Wire mtrs 5,641.43 31.00 174,884.21
12.02.01.26 Cabling Consumables Units 3.00 80.00 240.00
Subtotal for 12.02.01- Fire Detection and Alarm System 238,175.21
12.02.02 IP Based Public Address
12.02.02.01 Network Switch ( Inside IDF) Pcs 1.00 38,967.00 38,967.00
12.02.02.02 Network Manager ( Inside IDF) mtrs 1.00 12,679.00 12,679.00
12.02.02.03 Power Amplifier ( Inside IDF) pcs 1.00 120,000.00 120,000.00
12.02.02.04 UPS Units 1.00 5,000.00 5,000.00
12.02.02.05 6w Ceiling Mounted Speaker set(s) 8.00 1,800.00 14,400.00
12.02.02.06 10w Wall Miunted Speaker set(s) 8.00 2,800.00 22,400.00
12.02.02.07 Pull Box 25mm x 250mm x150mm set(s) 1.00 200.00 200.00
12.02.02.08 IMC Conduit 25mm l.m. 63.00 577.00 36,351.00
12.02.02.09 IMC Coupling 25mm Pcs 63.00 46.00 2,898.00
12.02.02.10 Junction Box Unit 8.00 45.00 360.00
12.02.02.11 Square Box Units 1.00 85.00 85.00
12.02.02.12 Utility box Units 2.00 35.00 70.00
12.02.02.13 Locknut and Bushing 25mm Units 408.00 20.00 8,160.00
12.02.02.14 Flexible Metalic Conduit Units 18.00 85.00 1,530.00
12.02.02.15 FMC Connector Units 36.00 20.00 720.00
12.02.02.16 Hanger and Support Units 188.00 50.00 9,400.00
12.02.02.17 Roogh -In Consumables Units 11.00 50.00 550.00
12.02.02.18 #16 Shielded Twisted Pair Wire pcs 182.21 31.00 5,648.59
12.02.02.19 Cabling Consumables pcs 20.00 80.00 1,600.00
Subtotal for 12.02.02- IP Based Public Address 281,018.59
12.02.03 IP Based CCTV Surveillance System
12.02.03.01 Network Video Recorder units - 15,000.00 -
12.02.03.02 Patch Panel units 1.00 31,784.00 31,784.00
12.02.03.03 POE Switch units 1.00 45,738.00 45,738.00
12.02.03.04 Server units - 65,000.00 -
12.02.03.05 32" LED Spot Monitor units - 18,000.00 -
12.02.03.06 42" LED Spot Monitor units - 25,000.00 -
12.02.03.07 Fixed Colored IP CCTV Camera (Dome Type) units 11.00 15,000.00 165,000.00
12.02.03.08 Fixed Colored IP CCTV Camera (Dome Type) WP units - 15,000.00 -
12.02.03.09 UPS units 1.00 10,000.00 10,000.00
12.02.03.10 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.02.03.11 IMC Conduit 15mm units 105.00 223.00 23,415.00
12.02.03.12 IMC Coupling 15mm pcs 105.00 23.00 2,415.00
12.02.03.13 Junction Box pcs 11.00 45.00 495.00
Division Description Unit Quantity Unit Cost Total Amount Remarks

12.02.03.14 Square Box pcs 1.00 85.00 85.00


12.02.03.15 Utility box pcs 11.00 35.00 385.00
12.02.03.16 Locknut and Bushing 25mm pcs 30.00 20.00 600.00
12.02.03.17 Flexible Metalic Conduit pcs 11.00 85.00 935.00
12.02.03.18 FMC Connector pcs 22.00 20.00 440.00
12.02.03.19 Cable Tray 150mm x 150mm mtrs - 5,000.00 -
12.02.03.20 Hanger and Support pcs 314.00 50.00 15,700.00
12.02.03.21 Roogh -In Consumables Units 23.00 50.00 1,150.00
12.02.03.22 CAT6A UTP mtrs 313.41 50.00 15,670.50
12.02.03.23 Cabling Consumables units 20.00 80.00 1,600.00
Subtotal for 12.02.03- IP Based CCTV Surveillance System 315,612.50
12.02.04 CATV System
12.02.04.01 CATV OUTLET units 350.00 -
12.02.04.02 CATV Cabinet units 1,500.00 -
12.02.04.03 Main CATV Panel uniit 15,000.00 -
12.02.04.04 Pull Box 25mm x 250mm x150mm pcs 200.00 -
12.02.04.05 IMC Conduit 25mm pcs 402.00 -
12.02.04.06 IMC Coupling 25mm pcs 46.00 -
12.02.04.07 Junction Box pcs 45.00 -
12.02.04.08 Square Box pcs 85.00 -
12.02.04.09 Utility box pcs 35.00 -
12.02.04.10 Locknut and Bushing 25mm pcs 20.00 -
12.02.04.11 Hanger and Support units 50.00 -
12.02.04.12 Roogh -In Consumables units 50.00 -
12.02.04.13 RG6U 70% Braided m 35.00 -
12.02.04.14 Cabling Consumables units 80.00 -
Subtotal for 12.02.04- CATV System -
12.02.05 Access Control System
12.02.05.01 Network Switch (Inside IDF) units 1.00 30,000.00 30,000.00
12.02.05.02 Patch Panel ( Inside IDF) units 1.00 5,000.00 5,000.00
12.02.05.03 Door Controller units 1.00 25,000.00 25,000.00
12.02.05.04 SD-1 -DOOR SENSOR units 3.00 15,300.00 45,900.00
12.02.05.05 Card Reader units 2,500.00 -
12.02.05.06 Input Module units 2,500.00 -
12.02.05.07 Door Contact units 2,500.00 -
12.02.05.08 UPS units 5,000.00 -
12.02.05.09 MDF units 15,000.00 -
12.02.05.10 Server - Complete Set units 65,000.00 -
12.02.05.11 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.02.05.12 IMC Conduit 25mm pcs 25.00 402.00 10,050.00
12.02.05.13 IMC Coupling 25mm units 25.00 46.00 1,150.00
12.02.05.14 Junction Box pcs 5.00 45.00 225.00
12.02.05.15 Square Box pcs 1.00 85.00 85.00
12.02.05.16 Utility box pcs 35.00 -
12.02.05.17 Locknut and Bushing 25mm pcs 14.00 20.00 280.00
12.02.05.18 Flexible Metalic Conduit mtrs 3.00 85.00 255.00
12.02.05.19 FMC Connector pcs 6.00 20.00 120.00
12.02.05.20 Hanger and Support units 74.00 50.00 3,700.00
12.02.05.21 Roogh -In Consumables units 3.00 50.00 150.00
12.02.05.22 #16 Shielded Twisted Pair mtrs 82.63 31.00 2,561.60
12.02.05.23 Cabling Consumables units 4.00 80.00 320.00
Subtotal for 12.02.05- Access Control System 124,996.60
12.02.07 Structured Cabling System
12.07.07.01 IDF units 1.00 150,000.00 150,000.00
12.07.07.02 Network Switch (Inside IDF) units 1.00 28,113.00 28,113.00
12.07.07.03 Patch Panel ( Inside IDF) units 1.00 3,792.00 3,792.00
12.07.07.04 Dual Port Universal Information Outlet (Table Mounted) units 2.00 550.00 1,100.00
12.07.07.05 Dual Port Universal Information Outlet (Wall Mounted) units - 550.00 -
12.07.07.06 Pull Box 25mm x 250mm x150mm pcs 1.00 200.00 200.00
12.07.07.07 IMC Conduit 25mm pcs 5.00 402.00 2,010.00
12.07.07.08 IMC Coupling 25mm pcs 5.00 46.00 230.00
12.07.07.09 Junction Box pcs 2.00 45.00 90.00
12.07.07.10 Square Box pcs 1.00 85.00 85.00
12.07.07.11 Utility box pcs 1.00 35.00 35.00
12.07.07.12 Locknut and Bushing 25mm pcs 13.00 20.00 260.00
12.07.07.13 Cable Tray 150mm x 150mm mtrs - 5,000.00 -
12.07.07.14 Cable Tray Fittings pcs - 2,000.00 -
12.07.07.15 Hanger and Support units 13.00 50.00 650.00
12.07.07.16 Roogh -In Consumables units 2.00 50.00 100.00
12.07.07.17 LAN Cable Cat 6 UTP mtrs 27.48 50.00 1,373.80
12.07.07.18 Cabling Consumables units 18.00 80.00 1,440.00
Division Description Unit Quantity Unit Cost Total Amount Remarks

Subtotal for 12.02.07- Structured Cabling System 189,478.80


12.02.10 Testing and Commissioning
Testing and Commissioning for all Auxiliaries and Electronics lot 1.00 45,674.94 45,674.94
12.02.10.01
Works
Subtotal for 12.02.10- Testing and Commissioning 45,674.94
TOTAL FOR 12.02 - AUXILIARIES AND ELECTRONICS 1,194,956.64

ESTIMATED TOTAL CONSTRUCTION COST OF B12 22,390,499.98

You might also like