Professional Documents
Culture Documents
3rd Floor Building F
3rd Floor Building F
3. WORK DESCRIPTION (Refer to JHA for details of work to be done, potential hazards and safety precautions)
Installatin of new Fire Pump Exact location ATEX Zone
(checked by permit issuer)
Tie-in new line from the new fire pump Fire Pump area
5. REQUIRED ATTACHMENTS
Clearance certificate is required if any of energy isolations is required: Electricity hydraulic Pneumatic Mechanical Thermal Valve Chemical
Gas test certificate is required: once ____ hours
Job Hazard Analysis (JHA) Confined Space Entry Permit Excavation Permit Hot Work Permit
List of Contractor Employees Electrical Permit Heavy Lifting Permit Work at Height Permit
1.2. Working w/o permits or unsigned permits. 1.2a. Making and approval of permits before start
of any activities inside the ESI premises.
1.2b. Personnel authorize to sign the permit shall
be responsible taking all precautionary measure
requires to prevent the danger of fire and
explosion and to assure the safety of the
personnel and equipment esp. the terminal plant.
1.2c. Make sure all the documents and
certifications needed is provided to ESI TM/TS for
them to approved or sign the permit.
1.2d. All concern personnel should given task to
coordinate each other for safety measures as a
given/instructed by; foreman/supervisor, terminal
representative and safety officer.
2. Inspection and checklist of machine, power 2.1. Defective and Malfunction 2.1a. Provide Checklist to inspected or evaluated
tools and oxy acetylene to be used ( CHECKLIST) by terminal representative and safety officer.
2.1b. All Hand/Power tools, Cables, Machine, Oxy
Acetylene etc. should be inspect/check if it is in
good condition.
3. Working area preparation and TIE-IN 3.1. Uncoordinated works or scope of works 3.1a. Conduct Safety talk/Tool box Talk On-site.
preparation. 3.1b. All workers should explained and
understand scope of work, to be given or
instructed by Supervisor, Terminal Representative
and Safety Officer.
5. Draining of water in the pipe line. 5.1. Pressurized water 5.1a. Wear complete/proper PPE at all time
5.1b. Ensure that all gate valves are closed, apply
LOTO if applicable.
5.1c. Don’t go beyond or make distance in the
direction of the puff pressured water.
5.2. Watery/Wet area 5.2a. Ensure that the water removed from the
pipe goes to the right disposal to prevent slips and
it us not the cause of electrocution.
5.2b make some way/solution for the work place
totally dry.
6. Cutting of pipes by using of GRINDER or OXY 6.1. Lack of knowledge or incompetent personnel. 6.1a. Deploy competent/certified personnel
ACCETELINE to perform the said activities.
6.2. Possible cause of fire and explosion due to
open flame cause by grinding and using oxy 6.2a. Ensure valid hot work permit before starting
acceteline. any hot work activities.
6.2b. Gast test the work area before commencing
any hot work activities to ensure that there is no
flammable gases near the working area.
6.3c. Eliminate all possible causes of fire near the
working area.
6.3d. Deploy competent workers and fire watcher
equipped with complete fire fighting equipment
( fire extinguisher , fire hose ).
6.3e. Set up temporary booth (COBOL) to
eliminate spreading of sparks.
6.4. Body injuries, cut and burns. 6.4a. Wear complete/proper PPE at all time.
6.4b. Ensure machine guard of the grinder on
place or functioning.
7. Full out the equal tee and the cuted pipe 7.1. Human errror 7.1a. The leadman/foreman should instruct all the
workers the procedure of the said activities to
eliminate/avoid human errors.
7.2. Handling of materials and tools cause of 7.2. Remove slowly the bots and nuts on the
pinched. flanges in both sides to avoid injuries or pinched.
8. Install blind flanges at both end/side. 8.1. Faillure of tight (bolts and nuts) 8.1a. Do not substitute plier for wrench when
turning or tightening the bolts and nuts.
81b. Ensure that the bolts ant nuts are enough
tight before leaving and proceeding another step
of job to prevent leakage.
9. Re-start the old fire pump. 9.1. Un authorized personnel 9.1a. Authorized personnel should only the one
who re-start the fire pump machine.
10. Take all removed pipe out of fire pump area to 10.1. Slip and trip hazard 10.1a. Keep all scattered tools, materials used in
be repair or fabricate ( bring all in Echo 4 proper places, and clear the passage.
temporary work shop) 10.1b. All workers should spot tripping hazard and
have them removed before start travelling of said
material.
2. Permit holder
Contractor Company JO MAR BUILDERS No. of contractor employees 6
Permit holder REMAR JOHN ESTEBAN Mobile No. 09560970518
3. Job description
Exact location of work FIRE PUMP AREA ATEX zone (validated by permit issuer)
4. Origin of flame/spark
drilling cutting (arc, oxygen, saw) welding lamp electrical equipment
heating grinding oxyacetylene welding internal combustion engines
sand blasting camera arc welding impact works
others___________
5. Pre-job checklist
a. Persons have license/certificate for the particular work? Yes NA
b. Clearance required (e.g. mechanical, electrical, thermal, radioactive, pipe, valve, etc.)? Yes NA Use clearance certificate.
c. Fire safety equipment in place? (e.g. fire extinguisher) Yes NA
d. Flammable materials and products removed from the working area? Yes NA
e. No venting at the proximity? Yes NA
f. Protective screen in place? (flame-proof, spark-proof) Yes NA
g. Gas detector required? Yes NA If yes, once every _______ hours.
h. LPG sales/operation stopped? Yes NA
i. Restricted the access of unqualified persons from the worksite: Signs/tags Barricades Attendant: name/signature _________________
7. Permit approval
Permit holder Permit issuer
I have conducted joint pre-job site inspection. I have conducted joint pre-job site inspection.
I will stay at the worksite for continuous supervision. I will stay at the worksite for continuous supervision.
Signature: __________ Signature: __________
Name: __________ Name: __________
Date/Time: __________ Date/Time: __________
8. Completion/Termination
Job completed Status if job is incomplete Permit holder Permit issuer
Job incomplete Signature: __________ Signature: __________
Isolation is removed Name: __________ Name: __________
Worksite is clean and safe Date/Time: __________ Date/Time: __________