Professional Documents
Culture Documents
Chapter 4 - Rev A
Chapter 4 - Rev A
Chapter 4 - Rev A
N° August 2007
Chapter: 4
Page: 1
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
CHAPTER 4
CONTENTS
1.
GENERAL 3
2.
Pre-commissioning Activities 4
2.2
Commissioning Activities 7
3.
PLANT INSPECTION 10
3.1
Vessels 10
3.1.2
Pumps 14
3.1.3
Electrical Motors 17
3.1.4
Piping Inspection 20
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 2
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
3.2.1
Spring Supports 20
3.3
Instrumentation Preparation 21
3.5
Telecommunications 23
4.
General 24
4.2
Water Flushing 25
4.3
Air Blowing 27
4.4
Steam Blowing 27
4.5
Chemical Cleaning 28
4.5.1
Safety Consideration 31
4.6
Chemical Cleaning 31
4.6.3
Neutralizing Procedure 32
4.6.4
Blinds List 33
5.
TIGHTNESS TESTS 34
5.1
General Procedure 34
5.1.1
Pressure Test 34
5.1.2
Vacuum Test 35
6.
7.
SPECIFIC ACTIVITIES 37
7.1
Cooling Water 38
7.2.5
Fuel Gas 40
7.2.7
Steam System 40
7.2.8
Flare System 41
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 5
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
7.2.9
Thermal Oxidizer 41
7.2.10
1. GENERAL
This chapter covers activities required to bring the plant to a "ready for start up" condition from the
original construction. The commissioning team, in close coordination with construction forces,
implements this part of precommissioning and commissioning activities.
The preliminary works for initial start-up can basically be divided into the following:
Plant inspection, checkout of unit.
Cleaning of piping and equipment.
Checking of control and safety systems
Commissioning of utility systems.
Run-in of drivers and Commissioning of machinery.
Loading of catalyst.
Chemical cleaning.
Air Leak/tightness test.
Boil-out of steam generating system.
Dryout of furnace refractories and process systems
Nitrogen purging.
Although the work will proceed generally in this order, much overlapping may be permitted.
During the preliminary operations, any defect should be disclosed, thus allowing timely
rectification’s to be effected. To obtain complete confidence in the state of the plant and
equipment, site staff must be particularly attentive to systematic checking for possible defects. At
subsequent start-up and partial start-ups, when perhaps only one item of the plant has been isolated
for short maintenance, equal diligence will be applied to appropriate pre-operational checks.
General procedures for preparation are described in the overall plant procedures and only basic
guides are given here. Specific procedures are described in this chapter. For all procedures
described, documentation provided by vendors shall be considered along. This information will
serve as a guide to the plant operators, as commissioning operations will be done using owner
personnel under guidance and supervision of contractor personnel
The result of these activities will be reported on sheets, issued and filled-up on site by
commissioning team. Obviously, some of the static activities hereafter described and implemented
during the construction/mechanical completion phase will be checked/ witnessed by
commissioning team, as they are part of its scope of work and responsibility. So no rigid border
exists between the construction phase and the precommissioning phase, which is achieved with the
Mechanical Completion, system per system.
When Mechanical Completion is reached for a system, the commissioning phase is performed. The
information described hereafter concern the preliminary operations for the first start-up of the new
plant.
In addition, for subsequent start-up, it may happen that some preliminary operations described
hereafter have to be performed or repeated, depending on the current situation (case of shutdowns
for maintenance works, capacities opening, …).
COMPANY Job N° August 2007
COMPANY Doc. N°
Chapter: 4
Page: 7
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Eqpt Inspection
PID Check/ PL
Field Instrum.
Internals Load
Chem Treatmt
Motor run-in
Mech. Clean
Oil Flushing
Water Flush
Steam Blow
Loop check
Pre-Commissioning Activity
Oil Filling
Air Blow
Coupling
31 Unit OSBL
31.002 – 01 HP Steam X X X X
31.002 – 02 MP Steam X X X X
31.002 – 03 LP Steam X X X X
31.011 – 01 Boiler 07-B-1207 A X X X X X X X X X X
31.012 – 01 Boiler 07-B-1207 B X X X X X X X X X X
31.013 – 01 Boiler 07-B-1207 C X X X X X X X X X X
31.020 – 01 Water & Condensate Common X X X X
31.020 – 02 Turbine Condensate X X X
31.020 – 03 MP Condensate X X X X X X
31.020 – 04 LP Suspect Condensate X X X X X X X X
31.021 – 01 Remineralization Package X X X X X X X X
31.022 – 01 Demineralization Package X X X X X X X X X
31.022 – 03 Polishing Package X X X X X X X X
31.022 – 04 Polished Water Distribution X X X X X X X X
31.023 – 01 Drinking Water X X X X X X X X
31.023 – 02 Utility Water X X X X X X X X
31.024 – 01 Deaerator X X X X X
31.024 – 02 VHP Boiler Feed Water X X X X X X X X X
31.024 – 04 HP Boiler Feed Water X X X X X X X X X
31.024 – 05 BFW Phosphate Injection Pack. X X (2) X X X X
31.024 – 06 O2 Scavenger Injection Package X X (2) X X X X
31.024 – 07 Amine Injection Package X X (2) X X X X
31.025 – 01 Cooling Water (OSBL, UG ISBL) X X(1) X X X X X X X X
31.025 – 02 Corrosion Inhibitor Injection Pack X X (2) X X X X
31.025 – 03 Sea Water X X(1) X X X X(1)
31.025 – 04 Sea Water Oxidant Package X X (2) X X X X
31.026 – 01 Fire Water (OSBL & UG ISBL) X X X X X X X X
31.026 – 02 Back Up Fire Water X X
31.027 – 01 Desalinated Water Distribution X X X X X X X X
31.037 – 01 Air Generation X X X X X X X X
31.037 – 02 Plant Air X X X X
31.038 – 01 Air Dryers Package X X X X X X
31.038 – 02 Instrument Air X X X X
31.038 – 03 HP Instrument Air X X X X X X X X
31.039 – 01 Nitrogen X X X X
COMPANY Job N° August 2007
COMPANY Doc. N°
Chapter: 4
Page: 8
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Eqpt Inspection
PID Check/ PL
Field Instrum.
Internals Load
Chem Treatmt
Motor run-in
Mech. Clean
Oil Flushing
Water Flush
Steam Blow
Loop check
Pre-Commissioning Activity
Oil Filling
Air Blow
Coupling
31.040 – 01 FuelGas, Wet Flare Condensates (not used)
31.045 – 01 FuelGas (Boilers, Utilities OSBL) X X X X X
31.045 – 02 Fuel Gas (Furnaces) X X X X X
31.046 – 01 Low Profile Flare Package X X X X X
31.046 – 02 Cold Flare (OSBL) X X X X X
31.046 – 03 Wet Flare (OSBL) X X X X X X X X
31.046 – 04 Cold Drain (OSBL) X X X X
31.050 – 01 Thermal Oxidizer Package X X X X X X X X
31.060 – 01 Waste Water Treatment Package X X X X X X X X X X X
31.060 – 02 Storm Water Treatment Package X X X X X X X X X X
31.060 – 03 Sanitary Water Treatment Pack. X X X X X X X X X X X
31.060 – 04 Effluents X X X X
31.071 – 01 Ethane X X X X X X X
31.072 – 01 Ethylene X X X X X X X X
31.073 – 01 C3/C4 X X X X X X X X
31.074 – 01 Pyrolyse Gasoline Storage & Shipping X X X X X X X X
31.075 – 01 C9+ Storage X X X X X X X X
31.075 – 02 Propane Storage X X X X X
31.075 – 03 Fresh Caustic Storage, Distribut. X X X X X X X X
31.075 – 04 Sulfuric Acid Storage, Distribut. X X X X X X X X
31.075 – 05 Wash Oil Storage & Distribution X X X X X X X X
31.075 – 06 Lube Oil Storage & Distribution X X X X X X X X
31.075 – 07 Mist Oil Storage & Distribution X X X X X X X X
31.080 – 01 Spent Caustic Treatment X X X X X X X X X X
31.080 – 02 Caustic & Acid Close Drains X X X X X X X
31.090 – 01 Oily Water Sewers X X
31.090 – 02 Contamin. Surface Water Sewers X X
31.090 – 03 Clean Roof Water Sewers X X
31.090 – 04 Sanitary Sewers X X X X X X X
31.090 – 05 Methanol, Propanol Inject System X X X X
31.091 – 01 DMDS Storage & Distribution X X X X X X X X
31.092 – 01 Gasoline Station X X X X X X X X
31.092 – 02 Diesel Station X X X X X X X X
31.093 – 01 Emergency Diesel Generator A X X X X X X X X
31.093 – 02 Emergency Diesel Generator B X X X X X X X X
31.096 – 01 Pyrolyse Gasoline Load, Drains X X X X X X X X
31.097 – 01 Ethane Meter Station/ Coalescer X X X X X
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 9
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Notes:
According to the size of lines, Water Flushing can be replaced by Mechanical Cleaning or Air
Blowing.
(1): diameter 60” and above: lines not blown nor washed, to be mechanical cleaned if requested
(2): For displacement pumps, no solo run of motor: replaced by run-in of Pump (refer to
Commissioning part)
COMPANY Job N° August 2007 COMPANY Doc. N°
Chapter: 4
Page: 10
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Run-in
31 Unit OSBL
31.002 – 01 HP Steam X X X X
31.002 – 02 MP Steam X X X X
31.002 – 03 LP Steam X X X X
31.011 – 01 Boiler 07-B-1207 A X X X X X X X X X X X X
31.012 – 01 Boiler 07-B-1207 B X X X X X X X X X X X X
31.013 – 01 Boiler 07-B-1207 C X X X X X X X X X X X X
31.020 – 01 Water & Condensate Common (not used)
31.020 – 02 Turbine Condensate X X X
31.020 – 03 MP Condensate X X X
31.020 – 04 LP Suspect Condensate X X X X
31.021 – 01 Remineralization Package X X
31.022 – 01 Demineralization Package X X ? X
31.022 – 03 Polishing Package X X X
31.022 – 04 Polished Water Distribution X X X X
31.023 – 01 Drinking Water X X X
31.023 – 02 Utility Water X X X
31.024 – 01 Deaerator X X X X
31.024 – 02 VHP Boiler Feed Water X X X X X X
31.024 – 04 HP Boiler Feed Water X X X X X X
31.024 – 05 BFW Phosphate Injection Pack. X X
31.024 – 06 O2 Scavenger Injection Package X X
31.024 – 07 Amine Injection Package X X
31.025 – 01 Cooling Water (OSBL, UG ISBL) X (1)
X X X X X X X
31.025 – 02 Corrosion Inhibitor Injection Pack X X
31.025 – 03 Sea Water X X
31.025 – 04 Sea Water Oxidant Package X X
31.026 – 01 Fire Water (OSBL & UG ISBL) X X X X X X X X
31.026 – 02 Back Up Fire Water X
31.027 – 01 Desalinated Water Distribution X X X
31.037 – 01 Air Generation X X X X X X
31.037 – 02 Plant Air X X X
31.038 – 01 Air Dryers Package X X X X X
31.038 – 02 Instrument Air X X X X X
31.038 – 03 HP Instrument Air X X X X X
31.039 – 01 Nitrogen X X X X X
COMPANY Job N° August 2007 COMPANY Doc. N°
Chapter: 4
Page: 11
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Run-in
31.040 – 01 FuelGas, Wet Flare Condensates (not used)
31.045 – 01 FuelGas (Boilers, Utilities OSBL) X X X X X X X
31.045 – 02 Fuel Gas (Furnaces) X X X X X X X
31.046 – 01 Low Profile Flare Package X X X X X X X
31.046 – 02 Cold Flare (OSBL) X X X X X X X
31.046 – 03 Wet Flare (OSBL) X X X X X X X
31.046 – 04 Cold Drain (OSBL) X X X X
31.050 – 01 Thermal Oxidizer Package X X X X X X X X
31.060 – 01 Waste Water Treatment Package X X X X X
31.060 – 02 Storm Water Treatment Package X X X X X
31.060 – 03 Sanitary Water Treatment Pack. X X X X X
31.060 – 04 Effluents X
31.071 – 01 Ethane X X X X X X X
31.072 – 01 Ethylene X X X X X X X X
31.073 – 01 C3/C4 X X X X X X X X
31.074 – 01 Pyrolyse Gasoline Storage & Shipping X X X X X X X
31.075 – 01 C9+ Storage X X X X X X X
31.075 – 02 Propane Storage X X X X X X X X
31.075 – 03 Fresh Caustic Storage, Distribut. X X X X X
31.075 – 04 Sulfuric Acid Storage, Distribut. X X X X X
31.075 – 05 Wash Oil Storage & Distribution X X X X X X
31.075 – 06 Lube Oil Storage & Distribution X X X X X X
31.075 – 07 Mist Oil Storage & Distribution X X X X X X
31.080 – 01 Spent Caustic Treatment X X X X X
31.080 – 02 Caustic & Acid Close Drains X
31.090 – 01 Oily Water Sewers X
31.090 – 02 Contamin. Surface Water Sewers X
31.090 – 03 Clean Roof Water Sewers X
31.090 – 04 Sanitary Sewers X
31.090 – 05 Methanol, Propanol Inject System X X X X X
31.091 – 01 DMDS Storage & Distribution X X X X X
31.092 – 01 Gasoline Station X X X X X X X
31.092 – 02 Diesel Station X X X X X X X
31.093 – 01 Emergency Diesel Generator A X X X X X X X X
31.093 – 02 Emergency Diesel Generator B X X X X X X X X
31.096 – 01 Pyrolyse Gasoline Load, Drains X X X X X X X X
31.097 – 01 Ethane Meter Station/ Coalescer X X X X X X X
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 12
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Notes:
(1): for the drum area.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 13
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
3. PLANT INSPECTION
The plant should be carefully checked to assure that it is constructed according to the applicable
plans, drawings and specifications. A check-off against the Piping and Instruments Diagrams is
done for piping, equipment and instrumentation. A "punch list" of missing, incomplete, or incorrect
items is then prepared for correction. In addition, temporary identification tags, signs for various
lines, valves and equipment can be installed at this time to assist in subsequent start-up and
operation.
This check is carried out before the end of construction work in order to check that the plant is
satisfactory from an operation point of view. All the individual operations needed for
precommissioning, start-up and shut-down the plant are applied on site.
The work described hereafter is carried out during the final stages of construction work under the
direction of the commissioning team in charge of the plant. Typically, this checking (which can be
called preliminary conformity to PID's check) is useful as soon as construction progress is 70% and
above. Several checks can be made simultaneously depending upon the completeness of each
section or system of plant at that time.
Smooth start-up will depend to a large degree on the thoroughness with which the plant is checked
out beforehand. Every installation details must be checked against the design specifications and
standards and for good construction practice.
3.1.1 Vessels
a. General Inspection
A general inspection of the vessel is made against the design drawings soon after erection. This
check includes:
Verification of temperature/ pressure and vacuum rating on nameplate.
Verification of lining condition (if applicable).
Nozzles location, size, flanges face
Thermo well location and length of immersion
Cleanliness.
When equipment experiences a temperature change it undergoes thermal growth. Supports are
provided to allow and guide this growth. If supports do not function as they are intended, then
damage could result to vessels, columns, heat exchangers nozzles or piping as the case might
be. It is therefore of great importance that all supports are inspected and special attention is
given to large horizontal vessels and heat exchangers.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 14
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Vessels and tower internals must be inspected carefully and checked against the design
documents to ensure that the installation was properly carried out. This check should include:
Trays: number, location, type, spacing, levelness, weir height, downcomers, valve number and
operation, support bolting. (Tightness testing is usual for chimneys trays).
Check that all valves on valve type tray are clean and free to move.
Check that weep holes, where provided, are not plugged.
Distributors: location, alignment, size and number of openings.
Vortex breakers: type, size and orientation
Demisters : size, material, support
Check that baffles in the bottom of the columns are correctly fitted, type, orientation and
levelness
Check that instrument nozzles are clear. Those which are accessible from inside the vessel can
be checked by turning on the aeration air. Those which are accessible only from the outside will
be checked during the air tightness test which will be implemented prior to inerting by
observing that the instrument vent valve is passing air.
Reactors
1. Inlet distributors, quench distributors: metallurgy, type, size, opening sizes, freedom to expand.
2. Vapor / liquid collection and distribution trays: tightness, vertical positioning, liquid tightness of
bubble caps and risers, metallurgy, dimensions, packing, supports, welding, levelness,
cleanliness.
3. Catalyst support grids: metallurgy, grid type and dimensions, screen type and size, supports,
welding.
4. Catalyst unloading nozzles: metallurgy, orientation, length.
5. Thermo wells: orientation, length, and metallurgy.
6. It must be verified that sufficient quantities of bolts, washers and hold downs of the proper size
and metallurgy are available to reassemble any disassembled portions of the reactor internals.
c. Cleaning
All vessels, columns, drums, tanks, etc. have to be inspected and cleaned if required, before
final closure, boxing-up.
The final cleaning is witnessed by the commissioning team, especially if the relevant vessel has
been integrated in a cleaning sequence.
In such case, it is normal practice that the vessel capacity is finally closed/boxed-up after
inspection and information it is clean. If the capacity is used as a buffer capacity, make sure that
air is evacuated from the vessel to lines and not reverse.
When the vessel is used as "collecting device", it must be finally closed only after cleaning.
Vessels’ cleaning is normally done through different ways according to the equipment
materials.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 16
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Caution:
Before entering a vessel, the plant safety precautions should be observed. These include the
following: sampling the vessel for toxic vapors and oxygen concentration wearing a safety
harness and having an attendant outside the vessel. AN UNATTENDED VESSEL SHOULD
NEVER BE ENTERED.
3.1.2 Pumps
a. Initial Checking
The most critical period in the life of a pump is during its initial start and several minutes
immediately thereafter. Proper installation and start-up is essential for trouble-free performance.
Before the equipment is ever started, it should be checked as follows:
Review carefully the manufacturer's operating instructions.
Check that the overall installation is complete.
Verify that the pump and driver are properly aligned.
Verify that cooling water piping is connected and in service where required: pedestals, bearing
jackets, stuffing boxes. etc. Run cooling water through bearing housing, stuffing boxes, etc...
until flushed clear.
Check gland or seal oil piping. Conventionally packed pumps in hot service are generally
furnished with gland oil. When a pump is furnished with mechanical seals, verify that all
components of the flushing system such as strainers, separators, restriction orifices and coolers
have been correctly installed and are clean. It is very important that the flush system be clean as
the loss or dirty flush can cause the loss of seals.
Verify that bearings shafts are clean and properly lubricated. All bearings should be flushed
clean and the correct lubricant in the proper quantity must be provided. Records for type of
lubricant used and date of lubrication follow up will be recorded.
Temporary strainers are provided for the suction of each pump to be installed on the pump side
of the suction block valves. These strainers should be installed after the suction lines are
flushed. These should be cleaned frequently to keep lines free of foreign matter. The strainers
should be cleaned frequently by alternating pumps where possible. Except on severe services
which may require installation of fine mesh on both pumps A and B, it is normally sufficient to
equip only one pump with fine mesh (on all "A" pumps for instance).
Consequently, the "A" pumps will be the ones preferentially started during initial start-up.
Then when temporary strainers are not anymore required they should be removed and only
the permanent strainer installed to prevent further possible pump damage.
Pumps are not field hydrostatically tested.
b. Running Tests
When piping systems are sufficiently complete, means that a system or sub-system can be
released from construction activity to precommissioning activity for dynamic operations, some
pumps will be put into operation to determine whether they are in good mechanical condition
and to verify proper installation of support systems and test running. Keep in mind that medium
other than the design fluid is not always possible. Typical example is when use of water leads to
adverse effect that may damage mechanical seals and introduce water in a system where drastic
drying is being implemented before start-up.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 18
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
The circulating fluid for test running a pump, when applicable, is often water. Due to
differences in specific gravity between water and the design fluid, care must be taken not to
overload the motors on motor driven pumps. The amperage on motor driven centrifugal pumps
should be monitored. If the amount of current drawn is too high the discharge valve should be
throttled until the amperage drawn by the motor is acceptable, keeping in mind that the pump
minimum flow should always be achieved.
Note: Running test of pumps will be done when applicable only. The selection of the pumps
subject to running test with water will be done by the commissioning team, and the relevant list
will be supplied in the Precommissioning Manual.
Centrifugal Pumps
The following steps should be adhered to when test running a centrifugal pump:
Operating personnel should be familiar with the literature furnished by pump and driver
manufacturers and should follow any special instructions therein.
Open up the suction valve from source.
Check that the seal does not leak (if packed seal check that packing nuts are not too slack) and
that the seal flushing and cooling water connections are correctly made.
Rotate centrifugal pump shaft by hand to test for free rotation but never if the starter switch is
not locked.
Confirm that the alignment check has been made on the pump shaft, driver shaft and coupling.
Check that the coupling guard is secured over shaft.
Check that the grounding clip and wire is secured from motor to grounding point.
Check that a discharge pressure gage is installed and functioning
Check that the electrician has tacked the pump power supply in substation.
Check that if a pump is on a closed recirculation loop from a vessel, the vessel is vented to
atmosphere to prevent any possibility of damage by pulling vacuum. A specific procedure will
be issued with marked down PID's for pump running with water prior to actual start-up.
When a run with water has been planned the loop system should be carefully isolated from the
rest of the sections. The water make-up should be sufficient to fill the whole loop and still leave
a good head available to the pumps.
Check arrangements to vent the pump for priming, if the pump is not self venting. Verify that
special connections such as bleeds and drains are properly installed.
Strainers must be installed before aligning pumps. A strainer is provided for each pump suction
line during start-up. To avoid pumps damage during flushing with water the strainers may be
lined temporarily with 20 mesh screens or as specified by the pump manufacturer. Remove this
temporary screen after water flushing is completed and fit the permanent one.
Note:
To prevent equipment damage multistage centrifugal pumps in light product service (specific
gravity less than about 0.8), if any, should not be running with water.
All valves in the loop should be opened except for control valves (manually closed from the
control room) and the discharge valve of the pumps. The operator at the control panel should
then be informed that the system is ready for operation.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 19
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
If possible do not start the motor on a centrifugal pump with the discharge valve open as this
also throws an excessive load on the motor (except if specified to start with fully open valve as
auto start cases).
When a hot pump is being kept hot by circulation of a stream through it from an adjacent pump,
the shaft of the motor may be turning slowly in the direction opposite to normal rotation. If a
pump is running in this manner and is started up, an excessive load is thrown on the motor.
Therefore, if a standby pump is already slowly rotating, cut off or reduce the circulation before
starting up. As a general rule, do not start-up and shutdown any motor more frequently than
necessary since this could cause damage to the motor rotor, especially for high horsepower
motors (not more than 3 starts per hour for medium or high voltage motors are recommended).
The board operator should be on duty and order the start of the pump. The discharge valve
should then be opened gradually so as not to lose suction. From then, the operation should be
controlled from the control room.
Ensure the pump is full of liquid after proper casing venting. The pump can now be started.
Crack open the discharge valve and switch on. The pump will come up to speed. The discharge
pressure gage should be checked immediately. If no pressure is shown the pump should be
stopped to find the cause. If discharge pressure is satisfactory, the discharge valve should be
opened slowly to give the desired flow rate. The pump should not be run with the discharge
block valve closed. Note any vibration or abnormal running condition.
The field operator should check for leaks in the system, overall pump performance and pump
overload.
The bearings of pumps and drivers should be checked for signs of heating. All oil levels should
be rechecked and the stuffing box should be checked for heating. The packing gland (for non
mechanical seal type pumps) should be loosened or tightened as required. It is desirable to allow
considerable leakage in the stuffing box at the beginning to permit packing to run in. Heating of
pump casing may be attributed to internal rubbing.
The pump should be run for approximately 1 hour, then shut off to make any adjustment
necessary and to check parts for tightness. Since it is not possible to run the pump at operating
temperature, a final check could be made during normal operating by switching to spare pump.
Reciprocating Pumps/Dosing Pumps
The following steps should be adhered to, when test running a reciprocating pump:
Check all previous points for centrifugal pumps except hand rotation.
Check that the correct relief valve has been installed relieving from the discharge line to the
suction line.
Check that the manually adjustable stroke control is lubricated and moving freely.
Check that the normal operating level of oil is shown in the sight glass.
Fully open the discharge valve.
Switch the reciprocating pump on and off, observe the stroke and listen for any loud rubbing
noises.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 20
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
All pumps should be watched closely during preliminary circulation and particularly when first
started. When bearings or packing boxes begin to overheat (usually this means hot to the touch)
or other indications of trouble appear, shutdown immediately for inspection. Keep a record of
pump running time, strainer inspections and condition, and final removal of the strainer.
Never run a reciprocating pump with a closed discharge.
Note:
The run of the electrical motor for rotational check is linked with Mechanical Completion
whereas functional test for several hours with records (amps) may be relevant to
precommissioning activities. Nevertheless, as already mentioned, there should be no border
between construction and precommissioning phases and nothing prevent implementing the
motor test (foreseen a few hours) and the rotation check as soon as the relevant electric supply is
energized.
Check that all air fan platform grating is in place and secured.
Check that all stop and start switches are fully installed.
Check that the correct motor oil has been put in and the storage protection (light) oil removed if
any.
Check the fan motor for proper rotation and grounding (never when the motor is energized).
Set the fan blade pitch as per manufacturer's specification. Once the fan is in operation, if motor
amperage is too high or too low, pitch readjustment may be required.
Set the vibration shutdown switches to give the permitted safe vibration level.
If the fan is belt driven adjust the drive belts for proper tension and check belt condition.
Confirm that the fan safety shields are in place.
Remove protection plywood that may have been laid on the tubes.
Check operation of louvers (if any).
When all above checks have been made, proceed to a 4 hours (except otherwise agreed duration)
test run and check the following points:
Check that the amperage of the motors is in the normal range.
Check for any noise from the bearings or other.
Check for any screeching or abnormal noises from the pulleys (belts may be too tight, which will
affect bearings).
Check that all belts remain on the pulleys (belts that constantly come off could indicate offset
pulley).
Check that air fan blades are not making any abnormal noise.
Check that air fans on the same cell are all turning at approximately the same speed.
Stop the air fans one by one and stand underneath to observe and check the following:
Check that no abnormal noise occurs on the rundown.
Check that the air fans slowly come to a stop in a smooth manner.
Check by hand that the motor has not overheated (inform the Electrical discipline if it has).
Warning
If the motor is inside the safety screen cover and if motor overheating is suspected or another
intervention on the fan is required never remove the safety screen by yourself. Inform the
Electrical Specialist which will follow the normal safety procedure of electrical isolation in the
substation by tagging off and locking shut the electrical breaker for the motors.
Complete the run-in before using the air cooler condenser for any heat transfer duty.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 23
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
3.6 Telecommunications
Inspection of all telecommunication equipment is performed to ensure compliance with
specifications, drawings, Codes of Practice, regulations and manufacturer's particular requirements.
In general, inspections should ensure satisfactory jointing and continuity of all conductors,
satisfactory alignment and tightness of bolting, acceptance levels of insulation, and a high standard
of cleanliness.
Main telecommunication systems are:
Message switch system
Radio communication system
Telephone network.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 27
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
4.1 General
Lines and equipment cleaning is intended to eliminate welds rods and slags, abrasive dusts, oxides
and in general other substances which might impede the normal unit operation or damage the
equipment (valves, pumps, compressors, turbines, etc.)
Cleaning is usually carried out either by hand cleaning for large equipment and lines having a large
diameter, by water flushing, by air blowing, chemical cleaning or any other cleaning method as
described hereafter.
Inaccessible piping (in terms of impossibility to access inside for hand cleaning) will be cleaned
using fire water or any other hydraulic or power flushing, or by air or steam blowing including
lines to and from storage. When an exchanger is included in a cleaning circuit, the inlet line is first
disconnected and the piping to it cleaned. After sufficient cleaning the exchanger must be
reconnected for washing the outlet piping.
It must be noticed that this is not always possible, as some lines between exchangers are impossible
to disconnect without complete removal of the line. In such case, the identified line has been
subject to joint inspection between the construction team and commissioning team, after or before
hydrotest inspection (drainage of the hydrotest medium) to confirm the line is sufficiently clean for
final installation.
For the circuits that are not equipped with a pump, a fire hose or a capacity (used as a reservoir)
may be used for washing, or as buffer capacity for air blowing.
Flush the pumps suction line through the strainer door/flange.
When the initial washing is completed, reconnect the suction piping of the pumps and continue the
washing of the lines during the running in of the pump (if applicable) until no more collected
fragments in the strainers at the pump suction.
Even if water flushing method would be foreseen, it is impossible to have the proper and required
velocity to clean lines over a certain size with water, without unreasonably sized temporary
facilities (process pumps do not allow such flows).
The cleaning of lines and associated equipment, which forms the various systems to be
mechanically completed then ready for start-up, will be treated during the construction and
precommissioning phases in two steps:
1. During the construction phase, preliminary checking is implemented to avoid pipelines retaining
construction materials until the actual cleaning takes place later, when practically feasibly and
applicable with the required efficiency.
2. Then to reach the readiness for start-up, a cleaning is implemented for each system/subsystem.
This cleaning will use efficient methods that could be implemented only after part of the plant is
available.
As a summary, only above (1) can be implemented at the hydraulic test stage of the work. The
cleaning (2) of course will be performed as soon as the site facilities allow for it, the optimum
being that both cleanings are implemented in sequence.
To make easier the understanding of the sequence of events, the cleaning sequence that will be
applied is the following:
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 28
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Pipes installation after the prefabricated spools have been transferred to the site must be
checked for removal (by gravity) any foreign material as tools, gloves, etc. (They are placed
vertically before installation).
For big lines, inspection is carried out by construction group after each spool is welded, and a
manual rubbing/wiping is performed, if necessary.
After the hydrotest, the hydrotesting medium (mainly water) is drained, through drain valves or
one open flange (if water is dirty, the network is rinsed until clean).
The relevant pipes are then air-swept to remove free water.
When the system or part of the hydrotested system (so called Test Pack) is released, a
provisional reinstatement is implemented, with exceptions list agreed by commissioning team
and list given to construction to allow the use of permanent facilities (columns/vessels/pipes
themselves) to perform the actual cleaning to meet the precommissioning cleanliness
requirement.
Some of this cleanings may need the utilities, (such as instrument air, utility air, service
water, etc.), in this case of course utilities should have been precommissioned before with
the normal required checks.
Above step is the period of time where the plant is actually cleaned and is followed by final
reinstatement and conformity to PIDs checks, air tightness test, etc.
The requirements for start-up are such that a cleaning as per above does not meet, for all
systems, the requirements for readiness for start-up. However, some lines could not be
subject to additional cleaning (such as some columns overhead lines, flare headers, etc.). For
these lines, above steps should be well monitored and controlled, and it is normal practice for
these cases that the commissioning team witnesses and records the status of these lines
before (or after) hydrotest.
When practical, lines should always be flushed away from a vessel rather than into a vessel. Any
vessel that has been flushed or blown into should be opened and manually cleaned following
flushing.
Flushing should be preferentially from the highest elevation to the lowest elevation. This restrain is
not compulsory for blowing.
Vessels and systems should be vented when filling or emptying to prevent vacuum pulling.
During flushing, maximum volume and velocity should be used to ensure through cleaning, the rate
of flushing medium should be regulated at the source.
Control valves should be rolled out of the piping system during flushing to prevent damage, except
some butterfly valves that can remain installed if wide open.
Orifice plates should be installed after cleaning is completed.
Instruments (i.e. pressure gages and transmitters, differential flow meter transmitters, moisture and
other in-line analyzers, etc.) should be positively isolated from the system during cleaning.
All drains should be flushed through to check for blockage.
Where possible, open-end lines should be flushed through. This is the case of process units
provided with end flanges for all utilities lines which make easier either flushing / air blowing /
steam blowing. Flow should not be restricted drastically.
Pump suction and discharge lines should be flushed while protecting the pump casing (by flushing
through the open strainer or a metal plate at pump flange).
Lines should be flushed in the following sequences, where possible :
first the main header,
then each sub-header,
at last, each branch line.
Always flush through a by pass when it exists, to an open end before flushing through equipment.
Lines should not be flushed into exchangers without flushing at the inlet first. Only when the inlet
is checked clean, and when the exchangers is not equipped with a bypass, flushing is allowed to
pass through the exchangers if required to proceed further.
Flushing should continue in each line or piece of equipment until the water is reasonably clean (or
as clear as the make-up water).
Unit Piping and Instruments Diagrams should be used as a cleaning check off record to ensure that
lines are flushed cleaned including lines to and from tankage. This marked-up PID set will be
referred as the "Cleaning Master PID Set".
After completion of the flushing operations, the water should be kept in the unit to facilitate
pump run-in if this was not done during the flushing operation and if run-in of pumps with
water is applicable. If pump run-in has been completed or will not follow the flushing operation
immediately, all water should be drained from the unit. If necessary, break flanges at low points
to facilitate drainage and air blow as required to remove as much water as possible.
COMPANY Job N° COMPANY Doc. N° August 2007
Chapter: 4
Page: 30
QC2-0007 RC2-31-COMT-OPM-00-000-0001 Rev: A
Note:
It is essential that the agreed path flushing procedure is adhered to more personnel it has been
established for in the field. The list of breakpoints should be made known to the construction
group as early as possible to avoid putting final gaskets in place of temporary gaskets and also
to have the required amount of correctly rated and sized gaskets in the hands of the
commissioning team.
The wall charts should be kept up to date and the final gaskets should add up to the same
amount as the temporary gaskets received (ideal situation).
Close follow-up eliminates problems during start-up and identical procedures can be used in
removing all temporary blinds after the completion of the hydrostatic test. A color code system
can be very useful at this stage (for flanges equipped with temporary gaskets).
When the headers are warm, the drain valves should be opened, blown vigorously for a few
moments before closure. Each lateral to heater, exchangers, or service lines should be blown in the
same manner, usually not more than one at a time. Condensate lines may be cleaned in the same
manner as steam lines, but close observation of the pressure on the condensate line is necessary
since the working pressure and temperature of the condensate lines are generally lower than of the
steam headers. A temporary movable silencer could be used to avoid exceeding noise level
limitations during the steam blowing operation, if necessary. Nevertheless, this minimizes the
efficiency of the steam blowing and steam blowing without silencer is preferable. (Coordination
with people working in the vicinity is required).
When blowing of the steam system is completed, equipment that was removed prior to the blowing
can be reconnected. The system can then be preheated and placed in service, after it has passed the
steam test.
Completion and effectiveness of steam blowing will be determined as follows:
Steam piping at inlet of turbine, desuperheater and outlet of boiler.
An aluminium target located at the vent point will be observed.
Blowing of this piping system will be considered completed and cleaned when on two consecutive
targets, collected after blowing carried out as above described, are present less than two pits per
square cm with a maximum diameter of 0.3 mm.
This is given as a guideline, and waiver can be admitted for boilers outlet.
Targets made from aluminium sheet will be inserted, on temporary vent only after that three - four
blowings (depending on the experience on site) have been carried out and the steam appears to be
clean.
Other steam piping and steam piping to turbine less than 4"
Piping system blowing will be considered completed when steam at the exit of vent point will
appear clean. (The steam has not to be orange dust color).
When blowing of the steam system is completed, traps and other equipment that were removed
prior to the blowing may be reconnected. The system can then be reheated and placed in service,
after it has passed the steam test.
After the surfaces are clean and dry, the pipe shall be filled with nitrogen and sealed. The nitrogen
pressure shall be 0.1 to 0.2 bar g.
PICKLING PROCEDURE
General
Pickling procedure is not required for Stainless Steel Piping.
The pickling (or chemical cleaning) of the carbon steel piping which follows cleaning or
degreasing may be carried out by the following recommended procedure.
Procedure for Carbon Steel
a. Immerse the piping in an acid pickling bath containing a 10 % wt solution of hydrochloric
(muriatic) acid in water. Rodine, Pyridine or other suitable inhibitors should be added to the
solution in accordance with the Supplier's instructions to prevent the piping from rusting quickly
when removed from the acid bath.
Piping and/or solution is agitated to ensure the flow of solution through the piping.
The bath temperature should be between 60 and 70°C and the time of immersion required to
remove all scale and rust will depend on the strength of the solution and condition of the
pipe. Normally, 12 to 14 hours are required and 6 hours should be taken as a minimum.
b. Remove piping from acid bath, drain it and immediate wash with cold water to remove all traces
of acid.
5. TIGHTNESS TESTS
7. SPECIFIC ACTIVITIES
When the drum is close to the working level open nitrogen and put in service the 091-PCV-0005
blanketing.
suction. Next operation is cleaning of discharge lines of pumps 67-P-1202 A/B/C and 67-P-1224
A/B/C. These pumps are equipped with a temporary strainer during this activity.
Start the pumps according to vendor’s instructions.
Start to circulate water trough the pumps, cleaning the pumps suction strainers as necessary. Outlet
line is opened to atmosphere.
Operate only one of these pumps, (67-P-1202 A) driven by an electrical motor, circulating water
trough the line up to the inlet line to the furnaces. The VHP BFW header line is open to the
atmosphere at inlet of each furnace (furnace inlet block valves).
Operate only one of these pumps, (67-P-1224 A) driven by an electrical motor, circulating water
trough the line up to the inlet line to the boilers. The HP BFW header line is open to the
atmosphere at inlet of each boiler (boiler inlet block valves). Circulate water up to desuperheating
valves of the different steam levels.