JES-HSE-RP- 47

LIFTING PLAN REV : 01

LIFTING PLAN FOR ERECTION OF UPPER DECK


FOR TUBE MEMBRANE SKID
1. PURPOSE
To prepare a rigging plan that shall be use for off-loading of Upper deck for tube
membrane skid at GTH.

2. HEALTH, SAFETY & ENVIRONMENT

1. Adequate PPE include hard hat, Safety glasses, face shield, coverall with long sleeves,
steel toad safety shoes, appropriate gloves, dust mask (if req) and ear plug ( Other PPE
to be worn as per job requirement).
2. The workers will be made aware of safety requirement related to this activity through
toolbox.
3. Fire stand by and fire prevention precaution as required for hot work will be implemented.
4. All equipment will be inspected by HSE/PROJECT prior to use and inspection record will
be in access.
5. Good Housekeeping should be maintained at site.
6. Fire extinguisher should be available at working area.
7. All waste material should be segregated and ensure proper housekeeping at all times of
the activities and avoid any tripping hazards / blocking of emergency access points.

3. PERSONAL PROTECTIVE EQUIPMENT

All site personnel will ensure use of following PPE:


1. Hard hat
2. Safety glass
3. Coverall
4. Gloves
5. Safety Shoes
6. Safety harness

4. TOOL & EQUIPMENTS

1. Hand Tools
2. Crane
5.

PACKAGE NO DIMENSIONS (mm) GROSS WT

01 15 ton
02 14 ton

03

6. RIGGING GEARS DETAIL

Load Manifest

Description Unit Weight Quantity Total Weight


kg (s) (KGS)
25 ton SWL, Soft eye wire rope sling. 25 04 100

Shackle 25 Tons 05 04 20

Main Hook Block 1000 01 1000

14000 01 14000

Contingency Weight 10 % 3962


Total Weight to be lifted 43582 (kg’s)

7. UPPER DECK FOR TUBE MEMBRANE SKID

Total weight
Crane to be Boom Boom angle, deg Safe lifting Safety
Radius of load to be
used Length (worst case) capacity Factor
lifted
Crane –
19.4 (M) 06 (M) 50-55 deg 14. (T) 33 (T) %
70 Ton

8. PROCEDURE

The following steps shall be carried out during execution of job:


1. Off loading of Office container to work location.
2. Inspection of equipment’s and lifting lugs.
3. Inspection of rigging tools & crane, Crane accessories.
4. Out riggers of crane fully opened.
5. Swing area will be barricaded.
6. Rigging arrangement for heavy equipment.
7. Communication of the lifting operation to all personnel at site.
8. Centering and installation of Upper deck for tube membrane skid.

9. DE-RIGGING

1. The alignment, placement of load and its leveling on the foundation will be confirmed by
mechanical erection team.
2. The slings will then be removed from the lifting eyes of the equipment.
3. The lifting crane will lower the slings to the ground.

10. SAFETY CONTROL MEASURES

1. All lifting equipment’s, accessories, Operators & Riggers shall have valid 3rd party
certificates and are physically inspected prior to use & crane operator must have been
HTV license.
2. A Job safety analysis (JSA) / Task risk assessment (TRA) shall be prepared.
3. All personnel involved in the lifting shall have HSE induction.
4. Rigging activity shall be performed in a professional manner with acceptable
workmanship.
5. All equipment installation works shall be performed in a manner to mitigate the adverse
effects of the environmental condition.
6. All the construction material and tools etc shall be removed from lifting site except those
required for lifting, tightening and leveling on foundation.
7. Lifting area will be properly barricaded and no unauthorized person shall be allowed
accept rigging personnel.
8. All lifting activities shall carried out under the PTW.
9. All personnel involved will have personnel protective equipment's and will have
completed the safety induction for the site.
10. Provision of Ambulance for any unforeseen shall be made at an appropriate place close
to lifting area.