General Consultant: AECOM Asia-PADECO-Dar AL-Handasah-TY Lin International Consortium Date: 23-03-18
DATE:- 11-01-2023
1 Coarse and Fine Aggregates Testing (TIPL & MS Infra) :- Sieve Analysis, Moisture Content, Silt content Testing at Daewoo-TPL-JV QC Lab Ulwe.
Grade of No. of
Sl. No. Date of casting Structure Date of testing Testing Location
Concrete Cubes
1 08-01-2023 S-70 MP-165-166 RHS Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
2 08-01-2023 S-60 MP-164-165 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
3 08-01-2023 S-48 MP-169-170 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
4 08-01-2023 RS-41 MP-169-170 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
5 08-01-2023 S-43 MP-163-164 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
6 08-01-2023 RS-13 MP-193-194 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
7 08-01-2023 S-20 MP-167-168 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
1 04-01-2023 S-46 MP-163-164 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
2 04-01-2023 S-19 MP-167-168 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
3 04-01-2023 S-60 MP-164-165 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
JMP-1 (Diaphragm) & MP-252-MJP-3, MJP-3-MJP-6,MJP-6-
4 04-01-2023 Diaphragm & Deck Slab Opening M60 3 11-01-2023 Daewoo TPL JV QC Lab
MJP-9, MJP-9-MJA-2 (Deck Slab Opening)
5 04-01-2023 S-08 MP-166-167 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
6 04-01-2023 MP-240-239 Outer LHS (Crash Barrier) Crash Barrier M45 3 11-01-2023 Daewoo TPL JV QC Lab
8 04-01-2023 S-42 MP-163-164 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
10 04-01-2023 MP-172 LHS (Pier Cap) Pier Cap M55 9 11-01-2023 Daewoo TPL JV QC Lab
11 04-01-2023 S-47 MP-154 LHS &S-61 MP-155 LHS (Wet Joint) Wet Joint M60 3 11-01-2023 Daewoo TPL JV QC Lab
1 14-12-2022 Ultratech Cement OPC 53 Grade Week No-49 Week No.49 OPC 53 3 11-01-2023 Daewoo TPL JV QC Lab
2 14-12-2022 S-41 MP-163-164 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
3 14-12-2022 S-53 MP-164-165 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
4 14-12-2022 S-26 MP-162-163 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
5 14-12-2022 S-03 MP-166-167 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
6 14-12-2022 Raft at AM Retaining Wall (CH 43.861 to CH 73.861) AM Retaining Wal M45 12 11-01-2023 Daewoo TPL JV QC Lab
7 14-12-2022 MP-245 RHS (Diaphragm) Diaphragm M60/A10 3 11-01-2023 Daewoo TPL JV QC Lab
8 14-12-2022 S-27 MP-187-188 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
9 14-12-2022 MP-258-257 LHS Outer (Crash Barrier) Crash Barrier M45 3 11-01-2023 Daewoo TPL JV QC Lab
11 14-12-2022 MP-229-228 LHS Outer (Crash Barrier) Crash Barrier M45 3 11-01-2023 Daewoo TPL JV QC Lab
1 16-11-2022 S-21 MP-162-163 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
2 16-11-2022 S-46 MP-158-159 RHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
3 16-11-2022 S-08 MP-161-162 LHS (Segment) Segment M60 3 11-01-2023 Daewoo TPL JV QC Lab
4 16-11-2022 Haunch at JM Retaining Wall (CH-30 to 55.454 LHS) JM Retaining Wall M45 3 11-01-2023 Daewoo TPL JV QC Lab
5 16-11-2022 PCC at AM Ramp (CH-34.595 to 43.861) PCC M15 3 11-01-2023 Daewoo TPL JV QC Lab
S-67 MP-160-161 LHS (Segment) & MP-245-255 RHS
6 16-11-2022 Segment & Segment Lifting Hole M60 3 11-01-2023 Daewoo TPL JV QC Lab
(Segment Lifting Hole)
S-17 MP-162-163 RHS (Segment) & MP-238-216 RHS
7 16-11-2022 Segment & Segment Lifting Hole M60 3 11-01-2023 Daewoo TPL JV QC Lab
(Segment Lifting Hole)
S-54 MP-189-190 LHS (Segment) & MP-243 RHS (Seismic
8 16-11-2022 Segment & Seismic Restrainer M60 3 11-01-2023 Daewoo TPL JV QC Lab
Restrainer)
9 16-11-2022 MP-261 to MP-263 LHS Median (Crash Barrier) Crash Barrier M45 3 11-01-2023 Daewoo TPL JV QC Lab
10 16-11-2022 MP-188 LHS (Integral Pier Head Segment) Integral Pier Head Segment M60/A10 6 11-01-2023 Daewoo TPL JV QC Lab
11 16-11-2022 MP-171 RHS (Pier 2nd Lift) Pier M55 3 11-01-2023 Daewoo TPL JV QC Lab