Aggregate Planning2
Aggregate Planning2
Operations
⚫ Aggregation
◆ Product families
◆ Workforce
◆ Time
Scheduling Scheduling
• Employee schedules • Employee and equipment schedules
• Facility schedules • Production order schedules
• Customer schedules • Purchase order schedules
Cost Definition
Regular time Regular-time wages plus benefits and pay for vacations
Overtime Wages paid for work beyond the normal workweek exclusive
of fringe benefits
Hiring and layoff Cost of advertising jobs, interviews, training programs, scrap
caused by inexperienced employees, exit interviews,
severance pay, and retraining
Inventory holding Capital, storage and warehousing, pilferage and
obsolescence, insurance, and taxes
Backorder and stockout Costs to expedite past-due orders, potential cost of losing a
customer
Figure 14.3 – Sales and Operations Plan for Make-to-Stock Product Family
Finalize Executive
Consensus
and S&OP
meeting
communicate meeting
4
6 5
1 2 3 4 5 6 Total
Forecasted demand 6 12 18 15 13 14 78
Quarter
1 2 3 4 Total
Forecasted 6,000 12,000 19,000 9,000 46,000
demand (hrs)
Workforce level 12 24 37 18 91
(workers)
Undertime (hours) 240 480 240 360 1,320
Overtime (hours) 0 0 0 0 0
Utilized time 6,000 12,000 19,000 9,000 46,000
(hours)
Hires (workers) 1 12 13 0 26
Layoffs (workers) 0 0 0 19 19
19,000
1.20w = = 36.54 employee-period equivalents
520
w = 30.45 or 31 employees
Quarter
1 2 3 4 Total
Forecasted 6,000 12,000 19,000 9,000 46,000
demand (hrs)
Workforce level 31 31 31 31 124
(workers)
Undertime (hours) 10,120 4,120 0 7,120 21,360
Overtime (hours) 0 0 2,880 0 2,880
Utilized time 6,000 12,000 16,120 9,000 43,120
(hours)
Hires (workers) 20 0 0 0 20
Layoffs (workers) 0 0 0 0 0
Several solutions are possible. The key idea in creating this one
is hiring only 7 employees in quarter 3, while using overtime to its
maximum limit and eliminating undertime for that quarter. Hiring
fewer in quarter 3 allows the number of layoffs in quarter 4 to
drop to only 13, down from 19.
Job 4/17 4/18 4/19 4/20 4/21 4/22 4/23 4/24 4/25 4/26
Start activity
Time
12
Workstation 7am 8am 9am 10am 11am pm 1pm 2pm 3pm 4pm 5pm 6pm
Dr. Jon
Operating Adams Dr. Aubrey Brothers Dr. Alaina Bright
Room A
Dr. Jeff
Operating Dr. Gary Case Dow Dr. Madeline Easton
Room B
Day M T W Th F S Su
Required number of employees 6 4 8 9 10 3 2
M T W Th F S Su Employee Comments
6 4 8 9 10 3 2 1 The S–Su pair has the lowest total requirements. Assign
Employee 1 to a M-F schedule.
5 3 7 8 9 3 2 2 The S–Su pair has the lowest total requirements. Assign
Employee 2 to a M-F schedule.
4 2 6 7 8 3 2 3 The S–Su pair has the lowest total requirements. Assign
Employee 3 to a M-F schedule.
3 1 5 6 7 3 2 4 The M–T pair has the lowest total requirements. Assign
Employee 4 to a W-Su schedule.
3 1 4 5 6 2 1 5 The S–Su pair has the lowest total requirements. Assign
Employee 5 to a M-F schedule.
2 0 3 4 5 2 1 6 The M–T pair has the lowest total requirements. Assign
Employee 6 to a W-Su schedule.
2 0 2 3 4 1 0 7 The S–Su pair has the lowest total requirements. Assign
Employee 7 to a M-F schedule.
1 0 1 2 3 1 0 8 Four pairs have the minimum requirement and the
lowest total. Choose the S–Su pair according to the tie-
breaking rule. Assign Employee 8 to a M-F schedule.
0 0 0 1 2 1 0 9 Arbitrarily choose the Su–M pair to break ties because
the S–Su pair does not have the lowest total
requirements. Assign Employee 9 to a T-S schedule.
0 0 0 0 1 0 0 10 Choose the S–Su pair according to the tie-breaking rule.
Assign Employee 10 to a M-F schedule.
M T W Th F S Su Employee Comments
6 4 8 9 10 3 2 1 The S–Su pair has the lowest total requirements. Assign
Employee 1 to a M-F schedule.
5 3 7 8 9 3 2 2 The S–Su pair has the lowest total requirements. Assign
Employee 2 to a M-F schedule.
4 2 6 7 8 3 2 3 The S–Su pair has the lowest total requirements. Assign
Employee 3 to a M-F schedule.
3 1 5 6 7 3 2 4 The M–T pair has the lowest total requirements. Assign
Employee 4 to a W-Su schedule.
3 1 4 5 6 2 1 5 The S–Su pair has the lowest total requirements. Assign
Employee 5 to a M-F schedule.
2 0 3 4 5 2 1 6 The M–T pair has the lowest total requirements. Assign
Employee 6 to a W-Su schedule.
2 0 2 3 4 1 0 7 The S–Su pair has the lowest total requirements. Assign
Employee 7 to a M-F schedule.
1 0 1 2 3 1 0 8 Four pairs have the minimum requirement and the
lowest total. Choose the S–Su pair according to the tie-
breaking rule. Assign Employee 8 to a M-F schedule.
0 0 0 1 2 1 0 9 Arbitrarily choose the Su–M pair to break ties because
the S–Su pair does not have the lowest total
requirements. Assign Employee 9 to a T-S schedule.
0 0 0 0 1 0 0 10 Choose the S–Su pair according to the tie-breaking rule.
Assign Employee 10 to a M-F schedule.
A
B
C
D
E
A 0 + 25 = 25 29 0 15 40
B 25 + 16 = 41 27 14 12 53
C 41 + 10 = 51 48 3 10 61
D 51 + 14 = 65 68 0 5 70
E 65 + 12 = 77 80 0 0 77
0 + 14 + 3 + 0 + 0
Average days past due = = 3.4 days
5
40 + 53 + 61 + 70 + 77
Average flow time = = 60.2 days
5
D
E
C
B
A
C 0 + 10 = 10 48 0 10 20
E 10 + 12 = 22 80 0 0 22
D 22 + 14 = 36 68 0 5 41
B 36 + 16 = 52 27 25 12 64
A 52 + 25 = 77 29 48 15 92
0 + 0 + 0 + 25 + 48
Average days past due = = 14.6 days
5
20 + 22 + 41 + 64 + 92
Average flow time = = 47.8 days
5
This schedule reduces the average flow time from to 60.2 to
47.8 days—a 21 percent improvement. However, the past
due times for jobs A and B have increased.
Copyright © 2010 Pearson Education, Inc. 14 – 46
Software Support
SOLUTION
B 0 + 16 = 16 27 0 12 28
A 16 + 25 = 41 29 12 15 56
D 41 + 10 = 51 48 3 10 61
C 51 + 14 = 65 68 0 5 70
E 65 + 12 = 77 80 0 0 77
B 0 + 16 = 16 27 0 12 28
A 16 + 25 = 41 29 12 15 56
D 41 + 10 = 51 48 3 10 61
C 51 + 14 = 65 68 0 5 70
E 65 + 12 = 77 80 0 0 77
Day M T W Th F S Su
Day
M T W Th F S Su
Requirements 3 4 5 5 4 7 8
Clerk 1 off off X X X X X
Requirements 3 4 4 4 3 6 7
Clerk 2 off off X X X X X
Requirements 3 4 3 3 2 5 6
Clerk 3 X X X off off X X
Requirements 2 3 2 3 2 4 5
Clerk 4 X X X off off X X
Day
M T W Th F S Su
Requirements 1 2 1 3 2 3 4
Clerk 5 X off off X X X X
Requirements 0 2 1 2 1 2 3
Clerk 6 off off X X X X X
Requirements 0 2 0 1 0 1 2
Clerk 7 X X off off X X X
Requirements 0 1 0 1 0 0 1
Clerk 8 X X X X off off X
Requirements 0 0 0 0 0 0 0
Planning Period 1 2 3 4