CBT 25
CBT 25
CBT 25
7. APCS-4 is a/an
(a) Coal tar epoxy coating system for immersion service
(b) Polyamide epoxy coating for atmospheric service
*(c) Alkyd .coating system for atmospheric service
(d) Chlorinated rubber system for chemical service
Page 1 of 6
8. When two air blowers are required to ventilate the tank, they should be fixed
*(a) One blower to blow fresh air inside and the other to suck the impure air outside;
(b) Both the blower to blow air inside,
(c) Only one blower to blow the air inside and the other keep as spare
(d) Both the blowers to blow air outside.
10. The Swedish standard designation for near white metal blast cleaning is
(a) Sa 2 *(b) Sa 2-1/2 (c) Sa 3 (d) Sa 1
13. Blasting and spray application for 'a critical coating can be performed only when a
minimum difference of
*(a) 3 degree C between the metal temperature and dew point,
(b) 5 degree C between the metal temperature and dew point.
(c) 10 degree C between the metal temperature and air temperature.
(d) 1 degree C between metal temperature and air temperature.
14. A daily quality control log sheet shall be prepared for all critical coating job and
submitted to Saudi Aramco Coating Inspector for review. The form to be filled is:
(a) Attachments “B" & "D" of SAEA-H-100.
(b) Site log book entry
*(c) Attachment "C" of SAES-H-100
(d) Operators plant log book
Page 2 of 6
15. If a coating operation requires only 5 liter of epoxy coating and the painter has only 20
liters of coating which consists of a base can and a hardener can. Then he should
mix:
(a) By taking 1/4 can of base and 1/4 can of hardener
(b) By taking 1/2 can of base and 1/2 can of hardener
*(c) Full can of base with full can of hardener
(d) He should not mix at all but wait for arrival of new 5 liter cans.
16. When a cone roof water tank is to be completely blasted and coated internally, the
abrasive blaster shall start.
*(a) Blasting from the bottom floor of the tank.
(b) Blasting from the roof of the tank.
(c) Blasting from the shell of the tank.
(d) Blasting the roof, shell and bottom at the same time.
17. If an internal coating job needs to be carried out in a crude tank, the bottom floor of
the tank shall be prior to blast cleaning.
(a) Detergent washed and disinfected.
(b) Water washed to remove any debris.
*(c) Solvent cleaned to remove oil and grease.
(d) Acid cleaned to remove chemical contaminations.
19. The tip size of an airless spray gun is denoted as 421. This means
(a) The fan width is 4 degrees and the nozzle size is 0.021 inches.
(b) The fan width is 400 degrees and the nozzle size is 21 microns.
(c) The fan width is 40 degrees and the nozzle size is 0.02 mm.
*(d) The fan width is 40 degree and the nozzle is 0.021 inches.
20. Many type of abrasives are used in blast cleaning and the best among them in the
environmental and occupational health safety point of view is
(a) Coal slag grit abrasive.
*(b) Garnet abrasive.
(c) Copper slag abrasive.
(d) Approved sand abrasive.
Page 3 of 6
22. The following coating defects may be seen immediately after a thick film of epoxy
coating is sprayed on a vertical plat.
(a) Checking, and cracking.
(b) Alligatoring and fish eye.
(c) Mud cracking and chalking
*(d) Sagging and curtain.
24. The coating system that is hand applied on a splash zone area at offshore is;
(a) APCS-20
*(b) APCS-19A
(c)APCS-113
(d) APCS-22
28. An immersion coating of a water tank shall be ___________ before the tank is put
back in service.
(a) 'Dried With hot air.
(b) Wetted with water to test the coating.
(c) Wetted With oil to test the coating.
*(d) Holiday tested and repaired.
(e) Fully cured and hardened.
Page 4 of 6
29. The surface profile of blasted steel surface can be obtained by using.
(a) A comparator with magnifying glass and standards.
(b) A calibrated dial gage.
(c) A press-o-film gage.
*(d) All of the instruments,
(e) None of the above instruments,'
31. Grounding shall be carried out for the below mentioned equipment:
(a) Air compressor
(b) Blasting nozzle.
(c) Air receiver drum
(d) Airless spray machine
*(e) All of the above equipment
36. The most widely used coating application method in Saudi Aramco is by
(a) Conventional spray *(b) Airless spray
(c) Rollers (d) Brushes
(e) All of the above (f) only (a) and (b).
37. The holiday test of a tank bottom internal coating shall be carried out using:
(a) 3000 volts high voltage comb type holiday tester
(b) 2000volts high voltage comb type holiday tester
(c) 100 volts low voltage wet sponge holiday tester.
*(d) 67.5 volts low voltage wet sponge .type holiday tester.
(e) 37.5 volts low voltage wet sponge type holiday tester;
Page 5 of 6
38. Abrasive blasting and spray coating application shall not be done in:
(a) Rainy weather condition:
(b) Strong windy conditions that blowout sand and contaminants in to coating.
(c) Snowing and icy cold weather condition.
*(d) All the above weather conditions
40. A blotter test shall be performed to determine air quality. The distance between blotter
or absorbent paper to a clip board.
(a) Approximately 25-50 cm with 50 psig
(b) Approximately 45-60 cm with 50 psig*
(c) Approximately 70-75 cm with 70 psig
(d) None of the above.
41. To aid in avoiding pinholes and bubbles occurring in the intermediate coat of epoxy,
be applied to the inorganic zinc primer.
(e) a mist-coat thinned 30 to 50%
(f) *a mist-coat thinned 10 to 20%
(g) a mist-coat thinned 20 to 40%
(h) none of the above
Page 6 of 6