PROCEDURE FOR SAND FILLING, EARTH FILLING & ROAD BED PREPARATION

1.0 Preamble:
around the world because sedimentation—the
The purpose of this paper is to describe the sand natural process of sand and silt washing
and earth filling procedure in the river bank of downstream—gradually fills channels and harbors.
Teesta. Normally navigability of river Teesta does
Dredging often is focused on maintaining or
not allow large dredger to be installed. However, a
number of locally made Cutter Suction dredgers increasing the depth of navigation channels,
used to mitigate the navigation problems. Although anchorages, or berthing areas to ensure the safe
the production and suction is little less in this passage of boats and ships. Vessels require a
process, but the customized machine serves the
certain amount of water in order to float and not
requirements. Regarding Earth filling the source of
earth, cohesion quality of earth and compact ability touch bottom. This water depth continues to
will be the main concern on the slope protection. increase over time as larger and larger ships are
Road bed preparation is also inside the scope of
deployed. Since massive ships carry the bulk of the
this write up.
goods imported into the country, dredging plays a
vital role in the nation's economy. In Bangladesh it
1.1 Relevant Data & Information is effectively used to extract filling sand in nearby
areas from the river bed.
a. Total volume of filling sand
= 888000 cum
1.1.2 Setting up dredging Machine:
b. Approximate area of the Yard
= 575000 sqm
c. Depth of filling The first step for sand filling is to set up the
= 1.5m to 2.0m dredging machine. A suitable space to be selected
d. Dredger to yard distance
on the river bank where the river depth is more than
= 700m-800m
e. Approximate distance of source 10(ten) feet. The dredger placement to be selected
dredge sand for cutting from in such a way that there should be navigable way to
dredging point
carry to the place. This would be a main challenge
= 3000 m
f. Time limit for complete filling as the navigability is a problem in Teesta river
= 30 days recently. After selecting the proper place for setting
Estimated volume of filling per day
= 30000 cum we have to select the capacity of dredger. We are
planning to use 04(four) cutter suction dredger. The
dredgers are custom made. The capacity of the
1.1.1 Dredging Description dredger is 600-800 meter cube per hour. Suction
end of dredger would be 200-250 mm. Main engine
Dredging is the removal of sediments and debris
power is around 350 KW. Maximum dredging depth
from the bottom of lakes, rivers, harbors, and other
is 10 meter. Delivery line diameter is 200 mm. The
water bodies. It is a routine necessity in waterways
dredger can deliver 1000 meter from the place

1
PROCEDURE FOR SAND FILLING, EARTH FILLING & ROAD BED PREPARATION

sand is extracted. Delivery pipe is to be set up in


1.1.4 Pre-measurement:
such a way that very less (maximum 04 bend) in
1000meter. Power type is diesel engine. During setting up the dredger we will start a joint
pre-measurement along with the selected
Delivery pipe is 150- 200 mm. The delivery
representatives of the employer/client. We will use
head capacity is 1500 meter . We are planning modern Total station for measuring the present
to run 04(four) dredger of 800 meter cube per levels before sand filling. We will keep the output of
hour so that with 70% capacity we can this level survey duly signed by both parties (client
and implementer) for future reference.
complete the work within 20(twenty) days.

Picture-02: Total Station

1.1.5 Setting the boundary of filling

We have to set the filling area with proper boundary


Picture-01 : A cutter suction dredger used in with permanent sand filled bags or any other
means so that the sand does not washed away
Bangladesh. (Customized)
from the filling area.

1.1.6 Compaction:
1.1.3 Manpower and Maintenance
As the dredger used sand has water with itself.
There will be expert dredger driver and maintenance When the water goes down along the pores the
engineer full time employed for smooth running of sand is compacted to 70%. After that with every
the dredger. Manpower for dredger operations are 300 mm filling we will use chain dozer to spread
as follows: and compact . We will then ask the employer to
test the soil compaction by compaction testing
equipment and certify whether compaction is
Sl. No Designation Number
alright or not. If the compaction is not adequate, we
01 Sr. dredger driver 02(one)
02 Jr.dredger driver 03(three) will use chain dozer for further period to achieve the
03 Experienced Senior Mechanic 01(one) desired compaction. Here again, we ensure we will
04 Jnr Mechanic 01 (one) do layer by layer compaction.
05 Delivery Pipe Handler 02(two )
1.1.7 Final Measurement:

2
PROCEDURE FOR SAND FILLING, EARTH FILLING & ROAD BED PREPARATION

After achieving desired level of sand filling with compactor of 10 ton capacity to compact the soil.
proper compaction we will again arrange Total After rolling 03 times to and fro ask the employer to
Station Level survey jointly with the Employers’ test CBR whether compaction achieved to a desired
representative to finally declare the amount of sand level or not.
compacted to the yard. This amount will be put in
black and white in measurement book.

2 Clearing and Grubbing: 5 Approach Roadway Sand filling:

We will first take the width of the area where we Dredged soil can be pumped to the road bed when
have to do clearing and grubbing. We will mark the compaction is satisfactory. After filling 150 mm
trees and inform the employer to take permission watering the sand is necessary for natural
from the local government to hack the trees. During compaction. Then the road roller to be rubbed at
clearing and grabbing we will make sure no least 03 times to achieve mechanical compaction.
embedded logs and roots of trees remain Then again next layer of sand is applied to the road
underground at least up to 0.3 meter depth. All bed with similar system of compaction mentioned
overhanging branches which will create problems before.
will be hacked down. If any government authority
permission for cutting the trees and branches is
6 Equipment and Manpower Required:
required, the employer needs to arrange.

3 Earth Filling in Grade:


Equipments Required:
First of all we have to select a source of land where
proper adhesive soil for slope protection is
available nearby. After getting the adhesive soil, we
will arrange excavator and dump truck to carry the Sl Name of Purpose Quantity Rema
extracted soil to proper place. We will fill the soil in No. the rks
Equipment
150 mm layer by layer and compact with vibro-
1 Dredger Sandfilling 04 nos
compactor to achieve the desired compaction on 2. Delivery Sand Filling 500-
1:2 slope. When vegetation and grass grows on the Pipes 700m
compacted sloped soil the slope will become 3. Excavator Excavation 01 Nos
stable. We will chamfer on the top as per 4 Dozer Spreading 01 Nos
requirement of design. 5 Road Compaction 01 Nos
Roller(8-
4 Approach Roadway Excavation: 10 ton)
6. Vibro- Slope 01 No
Excavating the approach road with desired width compacto Compaction
and depth to with excavator. Create proper shoulder r
as per design provided with the excavated soil. 7 Total Level Survey 01 No
Station
Remove extra soil from the road bed not more that
8 Dump Soil Carrying 05 Nos
30 meter with small dump truck. Use extect labor Truck
for final leveling and dressing. Arrange a roller

3
PROCEDURE FOR SAND FILLING, EARTH FILLING & ROAD BED PREPARATION

Manpower Required:

Sl Name of the Quantity Remarks


No. Equipment
1 Dredger driver 04 nos
2. Pipe handler 02 nos
3. Excavator driver 01 Nos
4 Dozer driver 01 Nos
5 Roller driver 01 Nos
6. compactor 01 No
7 Total Station 02 No
operator
8 Dump Truck driv 05 Nos
9 Road Workers 20 nos
10 Sr. Diploma Engr. 01 Nos

7. Conclusion:

In conclusion we want to ensure that we will


execute the work in a professional way to achieve
the desired result. This is why we will deploy
Diploma Engineer in the project management .
Lastly, but not the least, we will follow Civil
Engineering procedure for the entire work along
with proper documentation.

Submitted by

Mr. Hasan Tariq

Managing Director,

Bangladesh Foundry Engineering Works Ltd.