Professional Documents
Culture Documents
18.09.2017 Standard Costing Practice Question
18.09.2017 Standard Costing Practice Question
Namibia Housing Enterprise (NHE) recently replaced the kitchens in all of its housing
inventory. Unfortunately, there has been a problem with the model of oven that they
used and the glass in some of the oven doors shatters when the oven is hot.
Due to the serious nature of the problem and the potential health and safety implications
NHE have decided that the glass in the oven doors should be replaced in all of its 1 200
houses within the next three months at a rate of 16 houses per day.
The manufacturer of the oven offered to replace the glass themselves but do not have
enough replacement parts and do not have the facility to carry out the replacement
within the time scale that NHE requires. NHE’s maintenance manager agreed with the
manufacturer that their (NHE) own maintenance team would carry out the replacements
and that the manufacturer would pay N$512.40 per house for the costs of replacement
based on the following standard cost card:
N$
Replacement glass 459.50 Per unit
Nuts and Bolts 7.90 N$39.50 for a pack of 10. Two are required per
job one on each side of the oven door to hold
the glass in place.
Labour 25.00 10 minutes at a rate of N$150 per hour
Variable overheads 20.00 N$20 per job completed
Total 512.40
The first month of replacement work has taken place. The replacement engineer has
worked six days a week for the four week period and 378 houses had their oven glass
replaced. The following actual costs were incurred:
N$
Replacement glass 163 830 381 units were purchased; 3 were damaged
during transit from house to house and had to
be scrapped.
Nuts and bolts 3 200 N$40.00 was paid per pack of 10.
Required:
a) Prepare a reconciliation between budgeted and actual costs for the four-week
period of glass replacement, include all relevant variances. (11 marks)
b) Interpret the variances calculated, in particular identify any areas that you feel
should be brought to the attention of NHE senior management team. (10 marks)
c) Calculate the total cost of the replacement and the resultant deficit if spending
continues in line with the actual costs incurred so far. (4 marks)
Solution
Question 1
NHE – Reconciliation of budgeted to actual cost for oven glass replacement:
N$ Mark
Budgeted Cost N$512.40per house x 378 houses 193 687.20 1
Glass: Price Variance (SP – AP) x AQ (459.50 – 430) x 381 (w1) 11 239.50 F 1
Usage Variance (SQ – AQ) x SP (378 – 381) x 459.50 1 378.50 A 1
w4 standard is 10 mins per job x 378 jobs completed = 3780 mins / 60 = 63 hours
The price of glass results in a large favourable variance suggesting that a price for bulk buying
has been negotiated. This goes a long way towards balancing the adverse variances.
It would appear that the standard set was based upon an ideal standard and did not take
account of any wastage on materials. As a result of breakage of glass and additional usage of
nuts and bolts there are adverse usage variances.
The standard set also did not take account of the fact that the replacement engineer needed to
travel between jobs. Labour efficiency shows a large adverse variance however the engineer
completed the jobs within the standard time, it was traveling time that created the variance.
Fixed overheads were not included in the standard that was set. Overheads are recharged to
all areas of the organisation based on labour hours and as such should have been included in
the standard set.
This has had a large impact not only because overheads had to be included but also because
of the increased labour hours when traveling is taken into consideration.
Overall management should be aware that the standard that was set was not as accurate as it
should have been. The management accountant is there to support management with issues
such as this and would have been glad to help with the figures before this agreement were
finalised.
Resultant Deficit: