C3 Class Problem - Excel - Answers
C3 Class Problem - Excel - Answers
Quantity Quantity
Price Price
Total Value Total Value
Oil + Copper-Cost=$18,000+$10,500-$25,000=$3500
Cost of delay
Revenue if released today $2,000,000,000
Revenue if delayed $ 1,600,000,000
Interest rate 8%
$ 108,500,000
$ 104,000,000
Calculate using PV
N
i
PV
pmt
FV
Present Value
Calculate using PV
N 10
i 6%
PV ($8,375.92)
pmt 0
FV 15000
N
i
PV
pmt
FV
Present Value
N 5
i 4%
PV ($1,643,854)
pmt 0
FV $ 2,000,000