New York City Transit

NYCT STRUCTURAL FIELD REPORT

Project Name Station Componnet Repairs at (3)


Locations 168th St., 145th St. , and 103rd
St., (8th Avenue Line IND) Borough of
Manhattan Page # 1 of 14
Contract No. A-36956 Day/Date: 12/6/18
Constr. Mgr. George Terreros
Weather Temp: 32F Sky Clear Precip: No Wind: No
:
Work Location: 145 th Street Station Lower Level Platform, Track C2
Activities: Measuring Steel Loss % at Columns 1, 2, 31, and platform girder between columns #31 and #32
NYCT Personnel
Discipline Name and Pass # Phone #
CPM I. Kondrachov 212-690-9080
CPM P. Burkhardt 212-690-9080

Observations:
1- Column #1 – flange loss does not meet criteria for repair, web loss meets criteria for repair .
2- Column #2 - flange loss does not meet criteria for repair, web loss meets criteria for repair .
3- Column #31 – flange loss does not meet criteria for repair, web loss not investigated, no visual corrosion.
4- Platform girder bottom flange loss does not meet criteria for repair.
5-
6-

Remarks /Recommendations:
Obstructions (walls, equipments, concrete column cove bases) prevented measurements of all elements of columns to
be take. Measurements were taken at worst sections, chosen based on visual observation.

I. Kondrachov IgKondr M44265 12/6/18


Print Signature Pass # Date
Column #1 – 145th Street, Lower Level, adjacent to Track C2

Column #1
Column #1 – South Flange,
Track Side

Original thickness = 1.5”


Measured thickness = 1.184”
Steel Loss % = 21%

Column #1 – South Flange,


Track Side

Original thickness = 1.5”


Measured thickness = 1.189”
Steel loss % = 14%
Column #1 – South Flange,
Track Side

Original thickness = 1.5”


Measured thickness = 1.321”
Steel Loss % = 12%

Column #1 – South Flange, Track Side

Original thickness = 1.5”


Measured thickness = 1.387”
Steel Loss % = 8%
Column #1 – Web, Track Side

Original Thickness = 0.5”


Track Side Web Loss = 0.267”
Steel Loss % = 53%
Column #1 – Web, Track Side

Original Thickness = 0.5”


Track Side Web Loss = 0.167”
Steel Loss% = 33%
Column #1 – Photos of Column inside Ejector Room

Column #1 is encased in CMU wall


on two sides. Measurements of north
flange and opposite side of web were
not taken as there was no access to
column in room.

In order to repair column, section of


CMU wall shown must be removed.
Pump equipment, electrical conduit
and water lines may need to be
relocated.

CMU Encasement at
Ejector Room side
of Column #1

CMU Encasement
at Ejector Room
side of Column #1
Column #2 – 145th Street, Lower Level, adjacent to Track C2

Column #2-North Flange, Platf. Side

Original Thickness = 1.5”


Measured Thickness = 1.384”
Steel Loss % = 8%

Column #2 – North Flange, Platf. Side

Original Thickness = 1.5”


Measured Thickness = 1.190”
Steel Loss % = 21%
Column #2 – Web, Platf. Side

Original Thickness = 0.5”


Measured Loss = 0.375”
Steel Loss % = 75%

Column #2 – South Flange, room side

Original thickness = 1.5”


Measured Thickness = 1.316”
Steel Loss % = 12%
Column #2 – Ejector Room Side

Column #2 –
Pump Room Side

Column #2 – Platform Side

Loss measurements for south


flange were inaccessible as
the column is encased within
a terra-cotta wall.

In order to repair column,


wall and corresponding tile
needs to be removed. Space
heater, exhaust fan and
Ejector Room door need to
be temporarily removed.
Column #31 – 145th Street, Lower Level, adjacent to Track C2

Column # 31 – North Flange

Original Thickness = 1.5”


Flange Corrosion Loss = 0.131”
Steel Loss % = 9%

Location of Measurement:
Taken 7’ above platform topping. All
corrosion observed at 7’ and above
platform topping elevation.
Column #31 – North Flange, 7’ above
platform level

Original Thickness = 1.5”


Measured Thickness = 1.393”
Steel Loss % = 7%

Column #31 – North Flange, 12’


above platform level

Original Thickness = 1.5”


Measured Thickness = 1.407”
Steel Loss % = 6%
Platform Girder between Column #31 and Column #32– 145th Street, Lower
Level, adjacent to Track C2

Platform Girder, Platform Side, Probe location 1

Original Thickness = 0.5”


Measured Thickness = 0.494”
Steel Loss % = 1%
Platform Girder, Platform Side, Probe location 2

Original Thickness = 0.5”


Measured Thickness = 0.507”
Steel Loss % = 0%

Platform Girder, Platform Side, Probe location 3

Original Thickness = 0.5”


Measured Thickness = 0.380”
Steel Loss % = 24%