Muhammad Ahmed Khan

CV-134-2020
Sec C

S.no Item Description No.


1 Excavation (LW) 2
(SW) 2

2 Lean concrete (LW) 2


(SW) 2

3 Concrete in foundation (LW) 2


step 1 (SW) 2

Concrete in foundation (LW) 2


step 2 (SW) 2

4 Concrete above NGL (LW) 2


step 3 (SW) 2

5 Block Masonary (LW) 2


(SW) 2

6 Deduction *Door 1
*Window 1 2
*Window2 1
7 Block masonary
after deduction

8 Back fill
Length Width Height/Depth Quantity Unit
20.5 2 1.5 123 cubic ft
8.5 2 1.5 51 cubic ft
Total 174 cubic ft
20.5 2 0.5 41 cubic ft
8.5 2 0.5 17 cubic ft
Total 58 cubic ft
20 1.5 0.5 30 cubic ft
9 1.5 0.5 13.5 cubic ft
Total 43.5 cubic ft
19.5 1 0.5 19.5 cubic ft
9.5 1 0.5 9.5 cubic ft
Total 29 cubic ft
19.25 0.75 1 28.875 cubic ft
9.75 0.75 1 14.625 cubic ft
Total 43.5 cubic ft
19 0.5 10 190 cubic ft
10 0.5 10 100 cubic ft
Total 290 cubic ft
4 0.5 7 14 cubic ft
4 0.5 4 16 cubic ft
6 0.5 4 12 cubic ft
Total 42 cubic ft
Total 248 cubic ft

Total 43.5 cubic ft