C11' Junction Box Structural Detail

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PRECAST CONCRETE NOTES REINFORCEMENT NOTES

B PIT LID WITH CAST IRON SOLD TOP COVER C B C


P1 ALL PRECAST CONCRETE IS TO COMPLY WITH THE R1 REINFORCEMENT SHOWN ON THE DRAWINGS IS
S01 CLASS D, 200THICK. S01 S01 S01 CONCRETE NOTES ON THESE DRAWINGS, AS 3600 REPRESENTED DIAGRAMMATICALLY AND NOT
AND AS3850. NECESSARILY SHOWN IN TRUE PROJECTION.
150 P2 FOR LOCATIONS AND DIMENSIONS OF PRECAST R2 SPLICES IN REINFORCEMENT SHALL BE MADE
PANELS REFER TO ARCHITECTURAL DRAWINGS. ONLY IN THE POSITION SHOWN ON THE
PANELS NOTED AS SIMILAR ON THESE DRAWINGS DRAWINGS OR AS OTHERWISE APPROVED BY THE

150
ARE ONLY STRUCTURALLY SIMILAR, AND MAY ENGINEER. WHERE THE LAP LENGTH IS NOT
HAVE ARCHITECTURAL DIFFERENCES SUCH AS SHOWN IT SHALL BE SUFFICIENT TO DEVELOP
DIMENSIONS, GROOVES, FERRULES, MINOR THE FULL STRENGTH OF THE REINFORCEMENT.
PENETRATIONS, ETC. REFER TO ARCHITECTS BAR LAPS IN MILLIMETRES ARE TO BE AS SHOWN
DRAWINGS FOR DETAILS. BELOW UNLESS SHOWN OTHERWISE:-
P3 FOR ARCHITECTURAL FIXINGS AND REBATES N12 500 LAP
SL81 CENTRAL. REFER TO ARCHITECTS DRAWINGS. N16 650 LAP
A A P4 ALL PANELS ARE TO BE CONSTRUCTED FROM

900
150 SL81 CENTRAL N20 950 LAP
S01 S01 NORMAL WEIGHT CONCRETE. N24 1100 LAP
P5 SHOP DRAWINGS ARE TO BE DRAWN AND N28 1400 LAP
SUBMITTED AT LEAST 14 DAYS PRIOR TO N32 1700 LAP
N12-250, 500 EACH LEG. N12-250
FABRICATION OF PANELS TO THE ENGINEER TO N36 900 FOR COMPRESSION LAP
ENABLE CHECKING AND ALTERATIONS IF MECHANICAL SPLICE FOR TENSION LAP
NECESSARY TO BE MADE PRIOR TO FABRICATION.
R3 BUNDLED BARS SHALL BE TIED TOGETHER AT 30
P6 THE PANELS HAVE BEEN DESIGNED FOR THE IN BAR DIAMETER CENTRES WITH 3 WRAPS OF TIE

150
PLACE CONDITION (I.E. : LOADS THE PRECAST WIRE.
PANELS ARE SUBJECTED TO AFTER ERECTION ON
500 SITE) AND THE CONTRACTOR MUST MAKE HIS R4 REINFORCEMENT SYMBOLS :
OWN ASSESSMENT AS TO ANY EXTRA N GRADE 500 DEFORMED REINFORCING BARS,
REINFORCEMENT, LIFTING FITTINGS, DUCTILITY CLASS N TO AS 4671.
JUNCTION BOX PLAN VIEW SECTION D STRONGBACKS, ETC., THAT MAY BE REQUIRED TO R GRADE 250 PLAIN REINFORCING BARS TO AS
SCALE 1 : 20 SCALE 1 : 20 S01 SUIT HIS PROPOSED TRANSPORTATION, 1302.
HANDLING AND ERECTION METHODS. ANY SUCH W HARD DRAWN STEEL REINFORCING WIRE,
EXTRA MATERIALS OR OTHER HANDLING GRADE 500 DUCTILITY CLASS L TO AS 4671.
1300 SQ TM HARD DRAWN STEEL TRENCH MESH, GRADE 500
REQUIREMENTS MUST BE ALLOWED FOR IN THE
TENDER. THE CONTRACTOR SHALL SUBMIT FOR DUCTILITY CLASS L TO AS 4671.
50 RL RECTANGULAR RIB MESH, GRADE 500
REVIEW BY THE ENGINEER, FULL DETAILS AND
COMPUTATIONS BY A CHARTERED ENGINEER DUCTILITY CLASS L TO AS 4671.
50 B A A SL SQUARE RIB MESH, GRADE 500
EXPERIENCED IN THIS TYPE OF WORK. THESE
900SQ CLASS D COVER, BY OTHERS. 50mm HIGH STRENGTH, NON-SHRINK GROUT MIN, S01 900SQ CLASS D COVER, BY OTHERS. S01 DUCTILITY CLASS L TO AS 4671.
S01 SHALL COVER THE HANDLING PROCEDURE OF THE
PROVIDE REBATE TO CONCRETE AS PER VARIES. REFER CIVIL DRAWINGS FOR FALL. THE NUMBER FOLLOWING THE BAR SYMBOL IS THE
UNITS THROUGHOUT ALL STAGES INCLUDING
MANUFACTURERS REQUIREMENTS. 1300 NOMINAL BAR DIAMETER IN MILLIMETERS.
STRIPPING, LIFTING, STACKING,
TRANSPORTATION AND ERECTION. CONCRETE R5 REINFORCEMENT ABBREVIATIONS :-
200 EF EACH FACE
C STRESSES THROUGHOUT HANDLING SHALL NOT
200

NF NEAR FACE
400 MAX

S01 CAUSE CRACKING. COMPUTATIONS AND DETAILS


SHALL INCLUDE LOCATION AND SIZE OF INSERTS FF FAR FACE
900 SL81 CENTRAL. EW EACH WAY
N12-250 SL81 CENTRAL. AND TESTS PROVING ANCHORAGE CAPACITY OF
2-N12 PERIMETER LIFTING FERRULES. T TOP
BARS P7 ALL SHOP DRAWINGS ARE TO BE APPROVED BY B or BTM BOTTOM

150
THE MAIN CONTRACTOR PRIOR TO C CENTRAL
CONSTRUCTION COMMENCING. THE LV LENGTH VARIES
CONTRACTOR SHALL BE RESPONSIBLE FOR ALL R6 WELDING OF REINFORCEMENT IS NOT PERMITTED
500 N12-250 N12-250 DIMENSIONAL CHECKS AND CO-ORDINATION OF UNLESS SHOWN ON THE DRAWINGS OR
THE CONTRACT DOCUMENTS AND SITE APPROVED BY THE ENGINEER.
SL81 CENTRAL. SL81 CENTRAL R7 ALL REINFORCING BARS SHALL BE FIRMLY
DIMENSIONS. ANY DISCREPANCY SHALL BE
BROUGHT TO THE ARCHITECT'S ATTENTION SUPPORTED ON PLASTIC CHAIRS OR CONCRETE
PRIOR TO MANUFACTURE COMMENCING. CHAIRS AT SPACING NOT GREATER THAN 60 BAR
SL81 CENTRAL SL81 CENTRAL P8 ALL FERRULES AND CAST -IN ITEM USED SHALL BE DIAMETERS. MESH SHALL BE SUPPORTED ON
2460 MAX

D D D PLASTIC OR CONCRETE CHAIRS AT 750 MAXIMUM


GALVANISED STEEL IN ACCORDANCE WITH
S01 S01 S01 AS4680, MINIMUM COATING THICKNESS 600g/m² OR CENTRES. ALL REINFORCEMENT SHALL BE
OTHERWISE APPROVED, AND FITTED WITH SECURELY TIED WITH WIRE TIES AND ALL TIE

2310 MAX
150 3880 150 150 900 150 ANCHORAGE BARS OF MINIMUM 10mm DIAMETER. ENDS SHALL BE TURNED INWARD CLEAR OF THE
A MINIMUM M20 DIAMETER FERRULE IS TO BE COVER ZONE.
R8 MINIMUM LAPS IN MESH SHALL BE THE LARGER
ADOPTED UNLESS NOTED OTHERWISE.
SPACING OF TRANSVERSE WIRES UNLESS
P9 FERRULES THAT WILL BE EXPOSED AFTER
SHOWN OTHERWISE.
COMPLETION OF ERECTION ARE TO BE
N12-250 PIPE BY OTHERS OMITTED RECESSED 30mm BELOW THE CONCRETE R9 MESH SHALL NOT BE LAID ON THE GROUND AND
PULLED INTO POSITION THROUGH THE
SURFACE AND ARE TO BE GROUTED ON
COMPLETION. CONCRETE.
P10 PROVIDE 20mm LOCATING DOWELS TO THE BASE R10 CLEAR COVER TO REINFORCEMENT SHALL BE AS
OF ALL WALLS, WITH A MINIMUM OF 2 PER PANEL, SHOWN ON THE DRAWINGS.
500

SL81 CENTRAL N12-250 R11 REINFORCEMENT DEVELOPMENT LENGTHS SHALL


SL81 CENTRAL. UNLESS NOTED OTHERWISE.
P11 ALL CORBELS TO THE PRECAST PANELS TO BE EQUAL LAP LENGTHS.
POURED MONOLITHICALLY WITH THE PANEL.
150

P12 ALL EXPOSED AND BUTTING EDGES OF PANELS


SHALL HAVE A 15mm CHAMFER. R12 WHERE DISTRIBUTION BARS TO MAIN
REINFORCEMENT ARE NOT SHOWN ON THE
P13 ALL PANELS SHALL BE CAST ON A BOND BREAKER
DRAWINGS, PROVIDE MINIMUM N12-300, LAPPED
500
N12-250
CENTRAL.
SECTION A
N12-250
CENTRAL.
SECTION B SECTION C APPLIED IN STRICT ACCORDANCE WITH THE
MANUFACTURER'S RECOMMENDED PROCEDURE.
500mm AT SPLICES.
SCALE 1 : 20 S01 SCALE 1 : 20 S01 SCALE 1 : 20 S01 R13 ALL RE-ENTRANT CORNERS OF PENETRATIONS
THE BOND BREAKER SHALL REDUCE ADHESION
THROUGH WALLS AND SLABS SHALL BE TRIMMED
TO A LEVEL LESS THAN 50 % OF THE PANEL
USING MINIMUM 3-N12 DIAGONAL CORNER BARS
DEAD LOAD.
2000mm LONG.
P14 THE PANELS MUST BE STACKED IN SUCH A WAY
R14 REINFORCEMENT SET-OUT DIMENSION ARE
THAT :
SHOWN IN RELATION TO COLUMN CENTRELINES,
A) CRACKING WILL NOT OCCUR;
QUARTER SPAN POINTS OR WALL / BEAM EDGES
B) WARPING IN EXCESS OF THAT GIVEN IN THE
U.N.O.
RELEVANT CODES WILL NOT OCCUR
P15 THE CONTRACTOR SHALL TRANSPORT, ERECT ON R15 REINFORCING BARS SHALL BE EVENLY
SITE, AND PROP THE PANELS USING A MINIMUM DISTRIBUTED THROUGH THE WIDTH OF THE STRIP
OF TWO PROPS PER PANEL. U.N.O.
1300 P16 PROPS SHALL BE USED IN ACCORDANCE WITH R16 REINFORCEMENT SHALL NOT BE CUT OR BENT ON
THE SUPPLIER'S OR MANUFACTURER'S SITE UNLESS APPROVED BY THE ENGINEER. THE
B RECOMMENDATIONS AND LOAD LIMITS, AND REINFORCEMENT CAN ONLY BE HEATED IF
S01 SHALL BE FIXED TO FOOTINGS DESIGNED BY THE APPROVED IN WRITING BY THE ENGINEER.
CONTRACTOR. R17 AT SLAB EDGES INCLUDING CONSTRUCTION AND
P17 HIGH-STRENGTH PLASTIC PACKERS USED FOR OTHER JOINTS, AT LEAST ONE REINFORCING BAR
C LEVELLING UNDER SUPPORT POINTS OF LOAD- OR FABRIC WIRE SHALL BE LOCATED PARALLEL
S01 BEARING PRECAST PANELS MAY BE LEFT TO AND WITHIN 75mm OF THE SLAB EDGE.
PERMANENTLY PROVIDED THEY ARE CENTRALLY R18 AT PENETRATIONS WITH DIMENSIONS LESS THAN
900 SQ LOCATED BETWEEN THE FACES OF THE PANELS, 400mm DO NOT CUT REINFORCEMENT, RATHER
HAVE A MINIMUM OF 50mm GROUT COVER AND A GATHER REINFORCEMENT TO EACH SIDE OF
BEARING PRESSURE OF LESS THAN 7MPa. PENETRATION U.N.O. ON THE PLANS. AT
PACKERS USED BETWEEN NON-LOAD BEARING PENETRATIONS WITH DIMENSIONS LESS THAN
PANELS SHALL BE REMOVED IMMEDIATELY 600mm LAY REINFORCEMENT IN REQUIRED
2-N12 CRACK BARS EACH FACE 2-N12 CRACK BARS EACH FACE FOLLOWING THE INSTALLATION OF THE PANELS. POSITION AND CUT OUT TO SUIT PENETRATION.
BOTH SIDES OF JUNCTION BOX. BOTH SIDES OF JUNCTION BOX. P18 CONNECT ALL PANELS AT BUTT JOINTS AND PROVIDE ADDITIONAL BARS TO MATCH THE SIZE,
3-N12 @ 100 CTS LENGTH AND NUMBER OF BARS CUT, AND PLACE
CRACK BARS EACH INTERSECTIONS AS INDICATED. WHERE BOLTED
300

CONNECTIONS ARE USED AS PANEL-TO-PANEL EQUALLY ON EACH SIDE OF THE PENETRATION


FACE BOTH SIDES U.N.O. ON PLANS.
OF JUNCTION BOX. FIXINGS PLACE BOLTS CENTRALLY IN BOLT HOLE
TO GIVE MAXIMUM TOLERANCE IN ALL R19 CONCRETE SHALL NOT BE DELIVERED UNTIL FINAL
APPROVAL FOR REINFORCEMENT INSPECTION IS
2700 MAX

D DIRECTIONS.
P19 ALL GAPS SHALL BE PROPERLY SEALED WHEN OBTAINED.
S01
GROUTING UP THE PRECAST CONNECTIONS TO
2400 MAX

AVOID THE GROUT FILLING THE GAP BETWEEN


THE PANEL AND THE STRUCTURE AND TO AVOID
GROUT SPOILING THE FACE OF THE PANELS.
1500

P20 GROUT TO BE USED SHALL BE NON-SHRINK, AND


SHALL HAVE A 28 DAY CHARACTERISTIC
ø9 ø ø STRENGTH OF 40 MPa. DETAILS OF THE
00 90 90
0 0 PROPOSED GROUT TO BE SUBMITTED TO THE
ENGINEER FOR APPROVAL.
P21 ALL JOINTS SHALL BE PROPERLY CAULKED AND
SEALED AS REQUIRED AND FIRE-RATED WHERE
NECESSARY. TO ARCHITECTURAL
SPECIFICATIONS. ACID ETCHING AND ACID
CLEANING OF PANELS IS NOT ALLOWED.
P22 DETAILS OF SURFACE TREATMENT ARE TO BE
SUBMITTED TO THE ENGINEER FOR APPROVAL
PRIOR TO MANUFACTURE.
P23 VENEERED CONSTRUCTION AND USE OF
DIFFERENT MIXES AND MIXES FROM DIFFERENT
150 3880 150
SUPPLIERS ARE NOT ALLOWED.

JUNCTION BOX ELEVATION ADDITIONAL REINFORCEMENT ISO VIEW OF JUNCTION BOX


SCALE 1 : 20
EARTHWORKS OMITTED FOR CLARITY, REFER CIVIL DRAWINGS FOR LEVELS AND LAYOUT

ISSUE DATE DESCRIPTION CHECKER INITIAL CLIENT PROJECT DRAWING TITLE


A 20/12/22 ISSUED FOR
ISSUED CERTIFICATION
FOR CONSTRUCTION RT SGP ISSUED FOR CERTIFICATION DECHELLIS HOMES 43 AVNUE ROAD, PARADISE JUNCTION BOX DETAILS AND
NOT FOR CONSTRUCTION
NOTES
CONSULTING ENGINEERS
Level 14, Suite 2, 276 Flinders Street Melbourne VIC 3000
03 9923 7455 www.mlei.com.au
DATE PROJECT NUMBER DRAWING SCALE DRAWING NUMBER SIZE REV
DRAFTER DESIGN ENGINEER REVIEWER PROJECT MANAGER DEC 22 A2021-11772 As indicated
SGP MM RT RT DO NOT SCALE FROM THIS DRAWING S01 A1 A

You might also like