Professional Documents
Culture Documents
Fire Extinguisher Inspection
Fire Extinguisher Inspection
Fire Extinguisher Inspection
Sariwijaya
Group Condition Good / Bad
pressure Gauge
Expire Date
Insp Date
Pint lack
No Type / Manufacture Class SWJ No Cap Unit
Nozzle
Handle
Hoses
Remarks
1 KPK.BPN ABC POWDER FE.01 12 KG 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 22,07 FRONT OFFICE
2 KPK.BPN FOAM AFFF FE.02 9 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 22,07 PANEL INSTALATION AREA
3 INDOLOK .BU ABC POWDER FE.03 9 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 FRONT STORE
4 KPK.BPN ABC POWDER FE.04 6 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 MESS EXECUTIVE
5 KPK.BPN ABC POWDER FE.05 6 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 22,07 SECOND FLOOR
6 KPK.BPN ABC POWDER FE.06 9 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 CANTEEN
7 INDOLOK .BU ABC POWDER FE.07 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 FEB 20,07 ST. SUMBA
8 INDOLOK .BU ABC POWDER FE.08 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 JULY 25,07 ST. WIJAYA 5
9 INDOLOK .BU CO 2 FE.09 5 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 FRONT FUEL TANK
10 KPK.BPN CO 2 FE.10 6.8 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 FRONT GENERATOR ROOM
11 INDOLOK .BU ABC POWDER FE.11 9 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 FEB 20,07 ST. WIJAYA 2
12 INDOLOK .BU ABC POWDER FE.12 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 DEC 14,06 FRONT JETTY
13 KPK.BPN ABC POWDER FE.13 9 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 STOCK
14 KPK.BPN CO 2 FE.14 5 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 22,07 ST. WIJAYA 1
15 KPK.BPN FOAM AFFF FE.15 9 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 22,07 STOCK
16 KPK.BPN ABC POWDER FE.16 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 FEB 20,07 ST. WIJAYA 1
17 KPK.BPN CO 2 FE.17 5 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 22,07 ST. WIJAYA 2
18 KPK.BPN ABC POWDER FE.18 4,5 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 22,07 ST. WIJAYA 3
19 KPK.BPN CO 2 FE.19 5 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 JULY 25,07 ST. WIJAYA 5
20 INDOLOK .BU CO 2 FE.20 5 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 ST. WIJAYA 3
21 INDOLOK .BU ABC POWDER FE.21 9 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 FRONT FUEL TANK
22 INDOLOK .BU ABC POWDER FE.22 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 MESS EXECUTIVE
Inspected by :
Name : Muzakky Position : Safety Officer Signature :
INSTRUMENT , ELECTRICAL & MECHANICAL
pressure Gauge
Expire Date
Insp Date
Pint lack
Nozzle
No Type / Manufacture Class SWJ No Cap Unit
Handle
Hoses
Remarks
23 INDOLOK .BU ABC POWDER FE.23 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 FEB 20,07 FRONT SAND BLASTING
24 INDOLOK .BU ABC POWDER FE.24 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 FRONT LAUNDRY
25 INDOLOK .BU ABC POWDER FE.25 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 JULY 25,07 FRONT OFFICE SK
26 INDOLOK .BU ABC POWDER FE.26 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 DEC 14,06 SECOND FLOOR
27 INDOLOK .BU ABC POWDER FE.27 6 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 JULY 31,06 SEND TO BPP
28 INDOLOK .BU ABC POWDER FE.28 9 1 EA GOOD GOOD GOOD GOOD GOOD Dec 8,06 AUGT 21,07 SECOND FLOOR
29 INDOLOK .BU ABC POWDER FE.29 6 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 FEB 20,07 FRONT ENGINEER
30 INDOLOK .BU CO 2 FE.30 6.8 1 EA NONE GOOD GOOD GOOD GOOD Dec 8,06 AUGT 22,07 ST. SUMBA
Inspected by :
Name : Position : Safety Officer Signature :