The document outlines best practices for creating high quality project schedules, including ensuring each task has predecessors and successors, replacing lag time with detailed tasks, using finish-to-start dependencies, avoiding hard date constraints, assigning resources to incomplete but not summary tasks, minimizing excessive float, breaking long tasks into several shorter tasks, and correcting invalid dates so planned work is not in the past and completion not in the future.
The document outlines best practices for creating high quality project schedules, including ensuring each task has predecessors and successors, replacing lag time with detailed tasks, using finish-to-start dependencies, avoiding hard date constraints, assigning resources to incomplete but not summary tasks, minimizing excessive float, breaking long tasks into several shorter tasks, and correcting invalid dates so planned work is not in the past and completion not in the future.
The document outlines best practices for creating high quality project schedules, including ensuring each task has predecessors and successors, replacing lag time with detailed tasks, using finish-to-start dependencies, avoiding hard date constraints, assigning resources to incomplete but not summary tasks, minimizing excessive float, breaking long tasks into several shorter tasks, and correcting invalid dates so planned work is not in the past and completion not in the future.
1. Each task should have predecessors and successors.
2. Tasks should not have lead time (negative lag). 3. Lag time should be replaced with tasks that show detail. 4. Most dependencies should be finish-to-start. 5. Avoid hard date constraints. 6. Incomplete tasks should have resources assigned. 7. Summary tasks should not have resources assigned. Schedule Quality Best Practices 2
8. Minimize number of tasks with excessive float.
9. Incomplete tasks should not have negative float. 10. Break tasks with high duration into several tasks. 11. Correct invalid dates: Planned work should not be in the past and complete should not be in the future.