Hydrostatic Test Procedure For Ug Non-Metallic Piping System
Hydrostatic Test Procedure For Ug Non-Metallic Piping System
Hydrostatic Test Procedure For Ug Non-Metallic Piping System
052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 1 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 2 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
Record of Revisions
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 3 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
TABLE OF CONTENTS
1.0 SCOPE.............................................................................................................................. 4
3.0 RESPONSIBILITIES......................................................................................................... 4
Attachments
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 4 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
1. SCOPE
This procedure describes the general requirements and procedures for field pressure testing of
underground pressure GRE/GRP piping system, connected equipment and integral components to
assure mechanical strength and tightness.
1.1 Purpose
This procedure explains objectives and requirements of steps to be followed during Field hydro
testing of GRE/GRP piping system for KNPC-Clean Fuels Project.
3. RESPONSIBILITIES
3.1 Project manager shall be responsible for the overall implementation of the company safety &
Quality plan and ensure efficient execution of the works in accordance with the project specifications.
3.2 QA/QC manager shall oversee all the activities, whether all are executed as per the quality plan and
project specifications.
3.3 Construction manager shall be responsible to give correct instructions to supervisor for
implementing project quality and safety plan.
3.5 Foreman shall lead the work force and workmanship during the execution of the work.
3.6 QC supervisor shall see that all records pertaining to the particular works are maintained and
accepted by PMC.
3.7 QC Inspector shall ensure that all works are carried out as per IFC drawings, project specifications
and standards and he has to co-ordinate with PMC QC inspectors for the inspections.
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 5 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
4. GENERAL
4.1 Upon completion of installation, U/G GRE/GRP pressure piping systems shall be hydrostatically
pressure tested. The system / loop shall be both strength and leak tested in several sections
separately depending on the readiness of the construction. The entire system (all sections) shall be
Leak/strength tested at one time once the entire system shall be ready.
4.2 PREPARATION
A formal risk assessment should be carried out prior to the system hydro test. All supports, guides,
and anchors shall be in place prior to pressure testing. Temporary supports and restraints shall be
added if required. Pipe systems containing check valves shall have the source of test pressure
located on the downstream side. All adhesive-bonded and laminated joints shall be fully cured prior
to pressure testing. Threaded connections and the bolts of flanged joints shall be made up to the
correct torque prior to pressure testing in accordance with Manufacturers recommendations.
4.3.1 Manifold, pressure gauges, Relief valves, test blinds, pressure Hoses, air compressor, hand
pump, torque wrench, hand tools etc...
All inspection, measuring and testing equipment shall be maintained and calibrated, as described
in ISO 9001, with following additional requirements:
b) The deadweight tester shall be applied to final entire 4 hours strength test and 24 hours
leak test.
CONFIDENTIAL OR PROPRIETARY INFORMATION
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 6 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
c) All pressure measuring devices shall be calibrated to certified standard every six months.
4.3.3 A pressure relief valve shall be installed on the discharge of the test pump. This PRV shall be set
at 110% of test pressure. (DEP 74.00.10.10-Gen. Clause 3.1).
4.3.4 The Relief valve shall be tested, dated and tagged prior to the pressure test.
Internal cleaning of pipe shall be done by air blowing prior to hydrostatic test.
4.8 Company Line check and punch listing prior to NFI for testing.
5.2 Test pressure for hydrostatic test shall be 1.5 times design pressure.
Leak tightness test pressure shall be 1.1 times design pressure.
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 7 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
6.2 Gaskets required for service shall be used during hydrostatic pressure test (DEP 74.00.10.10
Clause 3.3.1)
6.3 Temporary bolts and nuts shall be same length/ diameter as used in service with colour
coding(Silver).
7. TEST PROCEDURE
7.1.1 A Hydro test pack for the loop or section to be tested shall be submitted to Company minimum 48
hours prior to test for approval.
7.1.2 It is recommended to limit the testing length to not more than one half kilometres for better quality
of work. However the test sections length can vary depending on site requirements.
7.1.4 In case the line does not include flanges, it will be necessary to connect temporary flanges or test
end-caps for testing purposes. Any additional flanges for pressure testing shall be removed
afterwards and replaced by pipe.
7.1.5 Steel blind flanges with suitable flange face to be used during hydro testing shall meet the
thickness required as mentioned in attachment 2.
7.1.6 For U/G piping, the section of pipeline to be tested should be partially backfilled up to one x
diameter above pipe crown (minimum 300mm but shall not exceed 1 meter) to ensure proper
support. Temporary supports (e.g. sandbags) or backfilling as required should be provided close to
fittings and at changes of direction during the test. All joints shall be left exposed for inspection
during the test.
7.1.7 Remove any instruments or other items that may be damaged by hydro testing such as valves,
bellows, strainers, flow meters etc. The items to be removed shall be clearly marked in the test pack
and the section closed with blind flanges or a suitable spool piece.
7.1.8 Clean the face of GRE/GRV flanges, blind flanges, gaskets, bolts, nuts and washers.
7.1.9 All gaskets, nuts, washers and bolts used for hydro test shall be replaced after final testing.
7.1.10 Install Kroll and Ziller gasket and blind flanges including bolts, nuts, washers to its appropriate
location. Apply torque using calibrated torque wrench and bolt sequence as per document no.
VV216A-109-A-808.
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 8 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
7.1.11 Required temporary piping arrangements like blind flanges and dummy spools will be installed in
appropriate locations.
7.1.12 Pressure gauges, Pressure/Temperature recorder, Deadweight tester and pressurizing pump are
connected to the line at the blind flanges/test ends. The pressure gauge shall be installed at the
highest point of the piping system being tested.
7.1.13 Piping section to be hydro tested shall be filled from the lowest point. Vents or other high point
connections shall be opened to expel air from the line.
7.1.14 All valves in the test system shall be full opened position.
7.1.15 Vents should be closed only when clear water with no air bubbles comes through the vent. All air
shall be removed from the piping system by venting before hydrostatic test pressure is applied.
7.1.16 The line shall be filled with water at a steady controlled filling rate. After closing all vents the water
filling will be stopped.
7.1.17 A pressure/temperature recorder and Deadweight tester shall be used during overall final test
governing test for both the Leak and Strength test. The chart will be signed at the start and finish of
the test.
Piping systems shall have been completely checked prior to hydro testing by Subcontractor,
Contractor and Company. All Category-(I) Punch Items shall be closed prior to the hydro test.
Subcontractor shall receive the scan copy of approved test package for each piping system from
Contractor test team. The latest drawings (Isometric drawing, PEFS & etc.) shall be attached on
the test package. Subcontractor shall conduct line check and punch clearing with this scan copy.
Subcontractor shall submit to Contractor for Contractor’s line check after cleared Subcontractor
category (l) punch items. Then, Contractor generate punch list and pass to Subcontractor for
clearing. When Subcontractor cleared all category (l) punch items, the test package shall be
treated as test package line completion. Contractor’s internal punch will be closed by Contractor,
not Company.
Once Contractor closes all punch items, Company shall be called for Company’s punch inspection.
Company inspection will be cancelled if more than two category (I) punch items are found at any
time in the inspection and the test pack returned to Contractor for Contractor’s re-inspection.
Company shall verify close out of Company raised punch items.
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 9 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
7.2.3 All lines shall be checked to ensure the entire system can be completely drained after testing.
7.2.4 Vents, drains and relief valves shall be utilized to prevent damage to the piping system due to
thermal expansion or other hazardous conditions during the test period.
7.2.5 Short pieces of piping which must be removed to permit installation of a blind or blank shall be
tested separately or, where possible, tied together and tested at the same time.
7.2.6 Lines containing check valves shall have the source of pressure located in the piping upstream of
the check valve and checked to insure that the entire length of piping can be completely filled with
water. If this is not possible, remove or jack up the check valve completely and provide necessary
filler piece or blinds.
7.2.7 Systems that include expansion joints shall be investigated to see that any required temporary
restraints, anchors, guides, etc., are installed prior to test.
7.3.1 The specific procedure for application of piping pressure test is given in DEP 31.40.10.19-Gen.
7.3.3 Time-frame for stabilization is 24 hours. Contractor will perform the temperature stabilization before
hydrostatic pressure test.
7.3.4 Once the temperature has stabilised, a strength test shall be carried out at a pressure equal to 1.5
times the system design pressure and held section by section for a minimum of 4 hours, and no
longer than 6 hours. The pressure will be raised up to the strength test pressure in the following
steps:
1) Raise the pressure to 0.5 X Test pressure with half hour stabilization and monitoring.
2) Raise the pressure to 0.8 X Test pressure with half hour stabilization and monitoring.
3) Raise the pressure to final test pressure. The rate of pressurisation shall not exceed 2 bar per
minute.
7.3.5 Only after acceptable Strength Test has been carried out then a Leak tightness test shall be carried
out at pressure equal to 1.1 times the system design pressure. The test pressure shall be held for a
minimum of 24 hours during which time no water shall be added to or removed from the pipeline.
7.3.6 During both the strength test and leak tightness test, the pressure and temperature shall be recorded
continuously and deadweight tester readings shall be recorded every 30 minutes. The original
pressure and temperature recordings shall be kept in the installation quality records.
7.3.7 As an additional check to determine whether any pressure variation has been caused by a
temperature change or whether a leak is present, the theoretical pressure change resulting from the
measured temperature change shall be calculated using the formulae given in Appendix B of DEP
31.40.10.19-Gen. (Refer to Attachment-4).
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 10 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
7.3.8 Any leaking or weeping shall constitute a defect , the test shall be terminated and a repair effected.
Joint shall be cut out and Pup piece installed. Then the test procedure shall be repeated.
7.3.9 Over-torquing of flanges to stop leaks shall not be permitted. Leaking flanges shall be remade with
new gaskets and retested. If leakage still occurs, flanges shall be replaced.
7.3.10 The strength test shall be successfully concluded if no leakage is observed by visual check and no
pressure drop is recorded. This is derived from Manufacturer procedure for field hydrostatic testing
of GRE/GRV pipe system(VV216A-109-A-809).For any pressure change due to temperature change,
this shall be calculated using the formulae given in Appendix B of DEP 31.40.10.19-Gen. (Refer to
Attachment-4).
7.3.11 The system shall be drained and dried after successful completion of the test.
Multi –Section Hydro tests shall be generally be used when the pipe to be tested is long and
Contractor desires to perform partial backfilling to support the construction schedule. Multi-Section
tests shall be composed of 2 or more sections depending on length. Each section shall be receive a
Partial Test which is intended to verify the integrity of the piping and allow the excavation between
the two ends of the pipe section to be backfilled. The Partial Test is NOT the governing test. A final
overall test of all sections joined together shall also be performed and this shall be considered the
final test.
The test method for Multi-Section tests shall be the same as noted above in Sections 7.3.1 through
7.3.12 except as noted below:
NFI shall be issued and Company invited to each Partial Test. Company approval of the Partial
test is not required, but any defects noted by Company shall be corrected prior to backfilling.
The ends of each Partial Test test section shall not be backfilled until the final overall hydro test
of all sections together is successfully completed.
The final overall test which incorporates all Partial Test Sections will be the final governing test.
With this partial test, integrity of piping system and soundness of field joints can be confirmed. After
completion of partial test, all tested piping components including joints will be backfilled except joints
the end points which shall be left exposed until the final overall test is complete.
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 11 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
Final Overall strength test and leaks test to be done with the all sections connected and end
points/joints between sections exposed during the tests.
Records shall be made of each piping system test, utilizing the forms titled, "Pressure test report
(JGSK-QC-6000-17)", “Pressure and temperature record during pressure test (JGSK-QC-6000-
41)” . These forms, when completed, shall be retained in the field QC document as a permanent
record. Refer to Attachments-3 and 5.
Test package will be handed over to commissioning team for further pre-commissioning cleaning
activity after reinstatement is completed and punch items are cleared unless commissioning team
request otherwise.
After completion of pre-commissioning activity, reinstatement can be completed and test package
will be submitted to the Company for confirmation once Contractor confirms all category (ll) punch
items are cleared and line is reinstated completely. After confirmation by Company, test package
shall be transferred to hand over team to upload into the hand over system.
In case a certain punch item cannot or should not be cleared until after achievement of
PTOP(Provisional Turn Over Package) due to commissioning reasons, these category (ll) punches
would be changed to category (lll) subject to agreement between Company and Contractor.
Category (lll) punch will be transferred into system punch and re-categorized as per system punch
definition.
8. SAFETY
8.2 To the possible extent, movement of men and equipment should be avoided.
8.3 Only authorized testing personnel will be allowed in the test area.
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 12 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
“Sample”
The latest format shall be referred to “S-000-1670-0401V”
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 13 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
40 10 10 10 10 11
50 11 10 10 10 10 10 11 10 11
80 11 10 10 10 10 10 11
100 11 10 10 10 10 10 11 10 11 11
150 17 15 14 14 17 15 17 17
200 22 20 19 19 22 22 22
250 28 24 24 24 28 28 28
300 33 29 28 28 33 33
350 39 33 39 39
400 44 39 38 38 44 44
450 49 42 42 49
500 55 48 47 47 55
600 66 58 56 66 66
700 66
800 88 77 75 77
900 86 84 86
1000 96 94
1300 121
1400 131
1500 140
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 14 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
“Sample”
The latest format shall be referred to “S-000-1670-0401V”
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 15 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
D R A
IN
21-JU
L - 2 016
Kuwait National Petroleum Company (K.S.C.) P6011MAA.000.10.51.052
Clean Fuels Project (CFP) REV F1
KNPC Contract No. CFP/EPC/0054-MAA Page 16 of 16
Contractor JOB CODE : 0-6798-20-0000 S-000-3168-0003V
“Sample”
The latest format shall be referred to “S-000-1670-0401V”
D R A
IN
21-JU
L - 2 016