Professional Documents
Culture Documents
Or Group Assignment
Or Group Assignment
By Team C9
Sahana D Nayak - 4NM20BA124
Srikalpa - 4NM20BA151
Sukesh - 4NM20BA158
Ullas Shetty - 4NM20BA167
Vikram - 4NM20BA170
1|Page
Project description
Irrigation projects mainly consists engineering structures which collects, convey and deliver
water to areas on which crops are grown. Irrigation project may range from small farm unit to
serving extensive areas of millions of hectares. A small irrigation project may consist of low
diversion weir or inexpensive pumping plant along with small channels. A large irrigation project
includes a large storage reservoir, a huge dam, hundreds of kilometers of canals, control
structures and other works.
2-4 2 Designing the blue print for the estimated irrigation site
2|Page
Drawing network diagram
7
2 2 2 4 311 2 3
101 10 5 4 6 1 8
3 6
3
Activit Duration
y
1-5 10
5-6 4
6-8 1
Total
path
15 days
duration
Path 2 = 1-3-5-6-7-8
3|Page
Activity Duration
1-3 3
3-5 6
5-6 4
6-7 2
7-8 3
Path 3 = 1-2-4-6-7-8
Activity Duration
1-2 2
2-4 2
4-6 1
6-7 2
7-8 3
4|Page
Path 4 = 1-5-6-7-8
Activities Duration
1-5 10
5-6 4
6-7 2
7-8 3
Path 5 = 1-2-4-6-8
Activities Duration
1-2 2
2-4 2
4-6 1
6-8 1
5|Page
Path 6 = 1-3-5-6-8
Activities Duration
1-3 3
3-5 6
5-6 4
6-8 1
To determine the project completion period highest path duration is considered (i.e., 19 ) the
project manager has to wait until all the activities of project are completed
Therefore, minimum path duration is not considered as the project completion period
Therefore, project completion duration is {15,18,10,19,6,14}=19
6|Page
2 4
7
1 5 6 8
We consider E3 to calculate E5
=Maximum of {10,9}= 10
E6= early start for node 6
Duration of (4-6) =1
We consider E4 to consider E6
E6= E4+ duration of (4-6)= 4+1=5
Similarly, duration of (5-6) =6
We consider E5 to calculate E6
= maximum of {6,14}=14
Duration of (6-7)= 2
We consider E6 to calculate E7
Duration of (7-8)= 3
We consider E7 to calculate E8
We consider E6 to calculate E8
8|Page
E8= E6+ duration of (6-8)= 14+1=15
Maximum of {19,15}=19
In order to calculate late finish for each of the activities we have to first determine late finish for
each node
L8= late finish for all the activities that finish on the 8th node
Duration of (7-8)= 3
We consider L8 to calculate L7
Duration of (6-8)= 1
We consider L8 to calculate L6
9|Page
L4= L6 - duration of (4-6)= 14-1=13
L3= late finish for node 3
Duration of (3-5) = 6
We consider L5 to calculate L3
L5- duration of ( 3-5) = 10-6=4
L2= late finish for node 2
Duration of (2-4) = 2
We consider L4 to calculate L2
L4- duration of (2-4) = 13-2=11
L1= late finish for node 1
Duration of (1-2) = 2
We consider L2 to calculate L1
L2 - duration of (1-2) = 11-2=9
L1= late finish for node 1
Duration of (1-3) = 3
We consider L3 to calculate L1
L3- duration of (1-3) = 4-3=1
L1= late finish for node 1
Duration of (1-5) = 10
We consider L5 to calculate L1
L5 - duration of (1-5) = 10-10=0
Minimum of {9,1,0}=0
10 | P a g e
Activity Duration Early Early Finish Late Start Late
Start Finish
Total float is calculated on the difference between the late start & early start or late finish &early
finish
11 | P a g e
Activity Late Start Early Start Total Float
1-2 9 0 9
1-3 1 0 1
1-5 0 0 0
2-4 11 2 9
4-6 13 4 9
6-7 14 14 0
7-8 16 16 0
3-5 4 3 1
5-6 10 10 0 In activity 1-
5,6-7,7-8,5-6
6-8 18 14 4 the total float
for above 4
activities is 0 that means the project manager cannot delay these activities then the project
completion duration will be delayed this means that these activities have to start on 1st day or 0th
moment while the total float of activities 1-2,1-3,2-4,4-6,3-5,6-8 is 9,1,9,9,1,4 .it means that
these activities can be delayed by 9,1,9,9,1,4 days respectively
Free float is determined by calculating the difference between the early start of the next activity
and early finish of the current activity
1-2 0 2
1-3 0 3
1-5 0 10
2-4 2 4
12 | P a g e
4-6 4 5
6-7 14 16
7-8 16 19
3-5 3 9
5-6 10 14
6-8 14 15
EF=3 ES=3
5
1 Present Activity 3 Next Activity
13 | P a g e
Early finish for (1-3)=3
Free float for (1-3)= {early start for 3-5}-{early finish for 1-3}
= 3-3=0
14 | P a g e
Free float for 4-6
EF=5 ES=14
6 7
4
Present Activity Next Activity
ES=14
8
6 7 8
15 | P a g e
Free float for 7-8
EF=19 ES = 19
7 8
Present activity
EF= 15
3 5 6
Present Activity Next Activity
16 | P a g e
Free float for 5-6
EF=14 ES=14
5 6 7
Present Activity Next Activity
ES=14
8
Present activity
EF= 19
17 | P a g e
Calculation of independent float
Independent float assumes that the next activity will start as soon as possible and the previous
activity finishes as late as possible
1-3 3 0 3 4
1-5 10 0 10 10
2-4 2 2 4 13
4-6 1 4 5 14
6-7 2 14 16 16
7-8 3 16 19 19
3-5 6 3 9 10
5-6 4 10 14 14
6-8 1 14 15 19
1 2 4
18 | P a g e
Independent float for 1-2 = {early start of next activity (2-4) -late finish for previous activity-
duration of present activity(1-2)}
= 2-0-2=0
1 3 5
Independent float for 1-3 = {early start of next activity (3-5) -late finish for previous activity-
duration of present activity(1-3)}
= 3-0-3=0
1 5 6
Independent float for 1-5 = {early start of next activity (5-6) -late finish for previous activity-
duration of present activity(1-5)}
= 10-0-10=0
19 | P a g e
Independent float for 2-4
1 2 4 6
Independent float for 2-4 = {early start of next activity (4-6) -late finish of previous activity(1-2)
- duration of present activity(2-4)} = 4-11-2= -9(0)
Independent float for 4-6 = {early start of next activity - late finish for previous activity(2-4) -
duration of present activity
(4-6)} = 14-13-1=0
20 | P a g e
Independent float for 6-7
4 6 7 8
Independent float for 6-7 = {early start of next activity (7-8) -late finish for previous activity(4-
6) - duration of present activity(6-7)} = 16-14-2=0
EF= 19
6 7 8
ES=maximum of {19,15}= 19
Therefore ES=19
Independent float for 7-8 = {early start of activity - late finish for previous activity(6-7) -
duration of present activity(7-8)} = 19-16-3=0
Independent float for 3-5
1 3 5 6
21 | P a g e
Independent float for 3-5 = {early start of next activity (5-6) -late finish for previous activity(1-
3) -duration of present activity(3-5)} = 10-4-6=0
3 5 6 7
EF= 15
LF=14 D=1 ES=19
5 Previous activity 6 present activity 8
7
EF=19
22 | P a g e
ES=maximum of {19,15}=19
Therefore ES=19
Independent float for 6-8 = {early start of activity - late finish for previous activity(5-6) -
duration of present activity(6-8)} = 19-14-1=4
1-2 9 0 0
1-3 1 0 0
1-5 0 0 0
2-4 9 0 -9(0)
4-6 9 9 0
6-7 0 0 0
7-8 0 0 0
3-5 1 1 0
5-6 0 0 0
6-8 4 4 4
23 | P a g e