Earned Schedule

Source: https://www.earnedschedule.com/

Earned Value Management (EVM) is a wonderful management system, integrating in a very intriguing way, cost
…schedule …and technical performance. It is a system, however, that causes difficulty to those just being introduced
to its concepts. EVM measures schedule performance not in units of time, but rather in cost, i.e. dollars. After
overcoming this mental obstacle, we later discover another quirk of EVM: at the completion of a project which is
behind schedule, Schedule Variance (SV) is equal to zero, and the Schedule Performance Index (SPI) equals
unity. We know the project completed late, yet the indicator values say the project has …perfect schedule
performance!!

ES resolves the long-standing dilemma of the EVM schedule indicators


providing false information for late performing projects.

Earned Schedule (ES) is a breakthrough analytical technique that resolves the EVM dilemma. It is derived from and
is an extension to EVM. No additional data is needed for acquiring the ES measures; only the data from EVM is
needed. In contrast to the cost-based indicators from EVM, the ES schedule performance indicators are time-based,
making them easier to comprehend. The ES indicators provide a status and predictive ability for schedule, analogous
to the facility for cost using EVM.
ES provides the ability to predict project completion dates and is the bridge
for performing meaningful schedule analysis from the EVM data.

Because the Earned Schedule metrics use time based measures, they augment traditional EVM and integrated
schedule analysis. Earned Schedule is the bridge between EVM and schedule analysis. It has been shown that ES
can be used for detailed schedule analysis and that it has the potential to improve both cost and schedule prediction

This site aggregates the available information concerning Earned Schedule (published papers, conference
presentations and terminology) and provides the availability to download the ES calculator spreadsheet. News
concerning ES is posted for keeping everyone as informed as possible. Also, for convenience, we have listed in
Contacts those available to provide assistance with your application. Sites of interest are identified which may help in
your search for an answer to your question or problem.

It is noted that Earned Schedule has been integrated into EVM guidance. Significantly, the International Standards
Organization has included ES in its recent publication, ISO 21508:2018, Earned Value Management in Project and
Programme Management.