MEMORIA DE CALCULO DE MURO DE CONTECION

MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR,


OBRA:
AMAZONAS, ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON,
BENSAQUE, PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO
POBLADO DE TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO

UBIC. FERNANDO LORES, MAYNAS, LORETO MURO - 1

DISEÑO DE MURO DE CONTENSIÓN H = 3.50 m

g = 1.80 ton / m3 t1

f = 32.00 º

dt = 0.62 kg / cm2 hp = 3.50

f'c = 210.00 kg / cm2 t2


0.40
f'y = 4200.00 kg / cm2
B2 B1
gm = 2.40 ton / m3

FSD = 1.50

FSV = 1.75

Wsc = 2.00 Tn/m2

DESARROLLO

De f = 32.00 º Vaciado IN SITU

f = tg. f = 0.625 £ 0.600 usar f = 0.600

Ka = 0.307

Ka.gs = 0.553 ton / m3

DIMENSIONAMIENTO DE LA PANTALLA

t1 = 0.20 m
M=1/6.Ka..h3 + Ka..ho.h2/2 t1

Mu = 13.12 ton*m

Además:
H=1/2.Ka..hp
3.50
Considerando para la ecuacón ... ( 1 )

f = 0.90

b = 100.00 cm t2 Ka..ho Ka..hp

f'c = 210.00 kg / cm2


MEMORIA DE CALCULO DE MURO DE CONTECION

MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR,


OBRA:
AMAZONAS, ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON,
BENSAQUE, PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO
POBLADO DE TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO

UBIC. FERNANDO LORES, MAYNAS, LORETO MURO - 1

r = 0.004
ho = 1.11 m
w = 0.08

Mu = 5.76 ton*m

d = 26.92 cm d = 20.00 cm
Verificación
t2 = 25.00 cm d = 20.37 cm

facero = 1/2 "

USAR t2 = 25.00 cm
Usar
d = 20.00 cm

VERIFICACIÓN POR CORTE

Vdu=1.7Vd=1.7(0.5).Ka.(hp-d)2 + 1.7.Ka.ho.(hp-d)
Vdu = 8.57 ton

Vdu/f = 10.08 ton

Vc = 15.36 ton

Si As se traslapa en la base:

Vce = 10.24 ton > Vdu/f OK!

DIMENSIONAMIENTO DE LA ZAPATA

hz = 40.00 cm

h = 3.90 m

B1 / (h+ho) ³ 0.288

B1 ³ 1.44 m
0.20
B1 = 1.57 m

USAR B1 = 1.90 m
3.50
B2 / (h+ho) ³ 0.044
MEMORIA DE CALCULO DE MURO DE CONTECION

MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR,


OBRA:
AMAZONAS, ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON,
BENSAQUE, PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO
POBLADO DE TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO

UBIC. FERNANDO LORES, MAYNAS, LORETO MURO - 1

0.25 1.65
B2 ³ 0.171 0.40

USAR B2 = 0.50 m 0.50 1.90

B2min = 0.40 m
MEMORIA DE CALCULO DE MURO DE CONTECION

OBRA: MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR, AMAZONAS,


ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON, BENSAQUE,
PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO POBLADO DE
TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO

UBIC. FERNANDO LORES, MAYNAS, LORETO


MURO - 1

VERIFICACION DE ESTABILIDAD

Brazo de Giro ( X )
Pi Peso ( P ) Ton. P*X (T*mt ) Datos Definitivos
mt.
P1 2.88 1.20 3.46 t1 = 0.20 m
P2 1.68 0.65 1.09 t2 = 0.25 m
P3 0.21 0.53 0.11 B1 = 1.90 m
P4 10.40 1.58 16.37
P5 3.30 1.45 4.79 B2 = 0.50 m
Total 18.47 N 18.47 M 25.82 B= 2.40 m

FSD=f.N/Ha Ha=1/2..Ka.h2 + .Ka.ho.h


P5
FSD = 1.68 > 1.50 OK!

FSV=Mr/Ma
Ma= 10.14 Tn-m 0.20

FSV = 2.55 > 1.75 OK!

P2 P4
PRESIONES SOBRE EL TERRENO

Xo = 0.85 m P3 3.50

e= 0.35 m < 0.40 OK!

Luego: 0.25
P1 0.40
q1 = 14.45 ton / m2
q1 > q2 OK! 0.50 1.90
q2 = 0.94 ton / m2

DISEÑO DE PANTALLA
En la Base:

Mu = 5.76 ton*m

t2 = 0.25 m

d= 0.200 m

As = 8.47 cm2

a= 1.99 cm

As1 = 8.02 cm2 ACERO VERTICAL


MEMORIA DE CALCULO DE MURO DE CONTECION

OBRA: MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR, AMAZONAS,


ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON, BENSAQUE,
PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO POBLADO DE
TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO

UBIC. FERNANDO LORES, MAYNAS, LORETO


MURO - 1
a= 1.89 cm

As2 = 8.00 cm2 1.75 3/4 " @ 57.01 cm

USAR Ø 3/4 @ 0.30 m

Refuerzo Mínimo

As min 3.60 cm2 /m


As min 2.77 cm2 /m

Mmax / 2 = 6.56 = (Ka.gs/6)(hp -hc)3+(Ka.gs/2)(hp-hc)2 hc = 0.85 m Mu= 6.61

Lc = 1.05 m USAR Lc = 1.50 m

REFUERZO HORIZONTAL

Ast = r .b.t.

1) 0.0020 f £ 5/8 "

fy ³ 4200 kg / cm2

2) 0.0025 ; otros casos

Si t2 ³ 25 cm: usar refuerzo horizontal en 2 capas

ARRIBA: 4.00 cm2 / m

2 /3 Ast = 2.67 cm2 2.11 f 1/2 " @ 47.50 cm

USAR Ø 1/2 " @ 0.45 m

1 /3 Ast = 1.33 cm2 1.05 f 1/2 " @ 95.01 cm

USAR Ø 1/2 " @ 0.95 m

Smax = 45 cm

INTERMEDIO: 4.50 cm2 / m

2 /3 Ast = 3.00 cm2 2.37 f 1/2 " @ 42.23 cm

USAR Ø 1/2 " @ 0.50 m


MEMORIA DE CALCULO DE MURO DE CONTECION

OBRA: MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR, AMAZONAS,


ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON, BENSAQUE,
PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO POBLADO DE
TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO

UBIC. FERNANDO LORES, MAYNAS, LORETO


MURO - 1
1 /3 Ast = 1.50 cm2 1.18 f 1/2 " @ 84.45 cm

USAR Ø 1/2 " @ 0.50 m

ABAJO: 5.00 cm2 / m

2 /3 Ast = 3.33 cm2 2.63 f 1/2 " @ 38.00 cm

USAR Ø 1/2 " @ 0.30 m

1 /3 Ast = 1.67 cm2 1.32 f 1/2 " @ 76.01 cm

USAR Ø 1/2 " @ 0.75 m

As montaje Vertical= f 5/8 " @ 0.45 m

s= 36 f = 57.15 cm

USAR Ø 5/8 " @ 0.35 m


MEMORIA DE CALCULO DE MURO DE CONTECION

MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR, AMAZONAS,


OBRA:
ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON, BENSAQUE,
PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO POBLADO DE
TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO
UBIC. FERNANDO LORES, MAYNAS, LORETO MURO - 1

DISEÑO DE LA ZAPATA

Ws = 6.65 ton / m

Wsc = 2.7 ton / m


W= 9.35 ton / m

Wpp = 1.20 ton / m

ZAPATA ANTERIOR

Ws max = 23.48 ton / m

Conservadoramente.

Mu = 1.88 ton*m

hz = 40.00 cm

facero = 5/8 "

d= 31.71 cm

As = 1.74 cm2

a= 0.41 cm

As = 1.58 cm2

As min = 5.71 cm2 2.88 5/8 " @ 34.68 cm

USAR Ø 5/8 " @ 0.30 m

Pasar la mitad del refuerzo vertical de la pantalla

Verificación por cortante : Por Inspección, conforme

ZAPATA POSTERIOR

q'B = 9.28 ton / m

qB = 10.23 ton / m

Wu = 14.77 ton / m

Mu = 12.41 ton-m

As = 11.51 cm2
MEMORIA DE CALCULO DE MURO DE CONTECION

MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR, AMAZONAS,


OBRA:
ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON, BENSAQUE,
PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO POBLADO DE
TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO
UBIC. FERNANDO LORES, MAYNAS, LORETO MURO - 1

a= 2.71 cm

As = 10.82 cm2

As min = 5.71 cm2 5.47 5/8 " @ 18.29 cm

USAR Ø 5/8 " @ 0.20 m

Vds = 15.99 ton

q'd = 6.29 ton / m

Vn = 18.82

Vc = 24.35 ton OK!

REFUERZO TRANSVERSAL

As temp = 5.71 cm2 2.88 5/8 "@ 34.68 cm

USAR Ø 5/8 " @ 0.20 m

As mont. = 36f 5/8 "@ 57.15 cm

USAR Ø 5/8 " @ 0.35 m


MEMORIA DE CALCULO DE MURO DE CONTECION
OBRA:
MEJORAMIENTO DE LAS CALLES 28 DE JULIO, 27 DE JULIO, BOLIVAR,
AMAZONAS, ATAHUALPA, 10 DE DICIEMBRE, MIRAMAR, ORQUIDEAS, KIPERTON,
BENSAQUE, PASAJE VARGAS CHAVEZ Y CALLE SANTA ROSA - CENTRO
POBLADO DE TAMSHIYACU-DISTRITO DE FERNANDO LORES-MAYNAS-LORETO

UBIC. FERNANDO LORES, MAYNAS, LORETO MURO - 1

REPORTE

0.20

VERTICAL
Ø 5/8 " @ 0.35 m VERTICAL
Ø 3/4 " @ 0.30 m

3.50
HORIZONTAL

HORIZONTAL
0

4 @ 0.30 4 @ 0.50
Ø 1/2 : 1 @ 0.05 4 @ 0.3 4 @ 0.5
0

VERTICAL
Ø 3/4 " @ 0.30 m
Ø 1/2 : 1 @ 0.05

1.50

Ø 5/8 " @ 0.30 m


MONTAJE
Ø 5/8 " @ 0.35 m

0.40

Ø 5/8 " @ 0.20 m


Ø 5/8 " @ 0.20 m 0.50 0.25 1.65

2.40